No Offer Date Project Client Progress
Ref
1 101 5-Apr Flood Light System 9 Lane Diyagama Venora Lost
2 102 6-Apr Emergency Light and Exit New Royal Won
3 103 7-Apr JAT Kotte JAT Lost
4 104 8-Apr Altair General and Lobby Altair Lost
5 105 9-May MOD MOD Abandoned
6 106 10-May Madivaru Air Field Lighting Male Lost
7 107 11-May Sethsiripaya NCC Lost
8 108 11-May Port of Galle Yard Project SLPA Abandoned
9 109 12-May Koala DFHQC MOD Koala Lost
10 110 13-May Tudawe Emg. Exit Signs Tudawe Lost
11 111 14-May Vollyball Courts Badulla Sport Min Lost
12 112 1-Jun AASL Apron Lighitng AASL Lost
13 113 5-Jun Quotation Venora Lost
14 114 8-Jun JAT JAT Lost
15 115 10-Jun DFCC Bank Venora Lost
16 116 12-Jun Ministry of Finance Maldives NCC Lost
17 117 13-Jun Ambathale Orugodawatta Street Lights NCC Lost
18 118 14-Jun Ooredoo Data Center NCC Lost
19 119 15-Jun Switch Yard New Royal Pending
20 120 16-Jun Vincent Dias Sports Complex Badulla Sport Min Lost
21 121 17-Jun 100 Nos of LED Street Lights AASL AASL Lost
22 122 18-Jun BBH Duminda Builders Duminda Builders Lost
23 123 19-Jun 11 Storey Commercial Office NCC Lost
24 124 2-Aug SLPA 160 Nos of LED Lamps Cranes SLPA Won
25 125 3-Aug Cambridge place lighting
26 126 4-Aug MDH Emergency MDH Pending
27 127 5-Aug MDH Outdoor MDH Pending
28 128 24-Aug Ruwan Kalpage House Ruwan Kalpage Lost
29 129 25-Aug Heights Emg Heights Lost
30 130 26-Aug Supply of LinearLights Cargills Lost
31 131 26-Aug Altair Second Offer EMG Altair Abandoned
32 132 27-Aug MOD Recalled MOD Abandoned
33 133 28-Aug Supply of CDN Lights Susen Holdings Lost
34 134 28-Aug Emergency and Exit New Royal Won
35 135 29-Aug Emergency Ventilux New Royal Won
36 136 30-Aug MGD Gass Light MDH Pending
37 137 2-Sep Pinnawala New Royal Lost
38 138 3-Sep SBI Partition Lights Abans
39 139 4-Sep Water Board Project MAGA Maga
40 140 5-Sep WLPL Office
41 141 6-Sep Intercontinental decorative Pearl Hotel Pending
42 142 7-Sep Intercontinental Façade Pearl Hotel Won
43 143 8-Sep Male Sport Court Sanken Won
44 144 9-Sep MDH BOH MDH Lost
45 145 10-Sep Fishery Harbour project at Gandara
46 146 11-Sep STP Project Ruwanwella
47 147 1-Oct Supply of Fuse AASL Lost
48 148 2-Oct Indoor stadium at Kuliyapitiya Micro Constructions Pending
49 149 3-Oct Macksons Properties Macksons Lost
50 150 4-Oct 400W MH Lamp Fittings SLPA Pending
51 151 5-Oct Benedict Hall Stage lighting Benedict Catholic Pending
52 152 6-Oct Hilton Yala Melwa Lost
53 153 7-Oct 8m Pole CESL
54 154 8-Oct Emg and Exit Sign Tudawe Pending
55 155 2-Nov R.Premadasa Stadium THK Pending
56 156 10-Dec CEB Substation New Royal Pending
57 100 5-Jan Radisson Project Tudawe Pending
58 101 6-Jan Melwa Hilton Yala Melwa Lost
59 102 7-Jan National Sports Complex Sugathadasa Won
60 103 5-Feb Sport Court
61 104 6-Feb MOD MOD Pending
62 105 7-Feb EMG Intercontinental DIMO Pending
63 106 8-Feb New Royal Philips New Royal Pending
64 107 9-Feb SLPA Highbay
Handled Submitte
Nature Selling Value Cost Gross profit
by d date
Infrastructure DJ 28-May 106,992,400.00 5,513,400.00
Commercial DJ 28-May 736,400.00 421,176.88 315,223.12
Hospitality DJ 7-May $ 30,351.60 1,224,990.00
Hospitality DJ 8-May $ 85,471.25 3,452,126.00
Commercial DJ 27-May 1,666,000.00 2,072,131.43 406,131.43
Infrastructure DJ 24-Jun $ 625,570.00 $ 435,565.53 $ 190,004.47
Commercial DJ 27-Jun 110,047,710.00 28,573,274.10
Industrial DJ 27-May 1,950,000.00 467,604.47
Commercial DJ 27-May 3,035,500.00 701,799.53
Commercial DJ 7-Jun $ 3,510.50
Infrastructure DJ 21-Jun 867,500.00 170,750.00
Infrastructure DJ 25-Jun 37,055,300.00 4,413,455.61
Commercial DJ 20-Jun 1,399,050.00 279,810.00
Commercial DJ 20-Jun 2,044,900.00 408,980.00
Commercial DJ 26-Jun 2,868,750.00 573,750.00
Commercial DJ 28-Jun $ 189,468.60 $ 37,893.72
Infrastructure DJ 21-Jun 13,142,800.00 3,407,585.94
Commercial DJ 10-Jul $ 25,519.80 $ 7,365.46
Infrastructure DJ
Infrastructure DJ
Infrastructure DJ 23-Jul 6,116,500.00 5,120,738.13 995,761.87
Hospitality DJ 16-Aug 199,520.00 47,575.69
Commercial DJ $ 100,208.60 $ 20,041.72
Industrial DJ 3-Sep $ 40,356.00 $ 6,156.00
DJ
Commercial DJ 9-Aug $ 17,720.00 $ 10,712.80 $ 7,007.20
Commercial DJ 16-Aug $ 3,023.00 $ 600.00
Hospitality DJ 17-Aug 782,340.00 195,585.00
Hospitality DJ 16-Aug 712,800.00 164,584.20
Commercial DJ 26-Aug $ 252,500.00 $ 102,500.00
Hospitality DJ 20-Aug $ 2,300.00 $ 633.00
Commercial DJ 26-Aug 1,666,000.00 2,072,131.43 406,131.43
Commercial DJ 27-Aug 1,033,950.00 238,545.88
Commercial DJ 28-Aug $ 7,615.90 $ 3,333.26
Commercial DJ 29-Aug 1,426,800.00 665,000.00
Hospitality DJ 5-Feb $ 23,975.00 $ 6,670.00
Commercial DJ 787,160.00 533,563.76 253,596.24
DJ
DJ
DJ
Hospitality DJ
Hospitality DJ 1,200,000.00
Infrastructure DJ 14-Jan $ 44,660.00 $ 12,600.00
DJ
DJ
DJ
Infrastructure DJ 3-Oct 1,927,800.00 715,882.86
Infrastructure DJ 11-Oct 1,046,400.00 241,757.47
Commercial DJ 12-Oct $ 53,361.30 $ 42,160.50 $ 11,200.80
Industrial DJ 13-Oct 2,600.00 $ 620.00
Commercial DJ 24-Oct 4,270,700.00 1,419,450.00
Hospitality DJ
DJ
Commercial DJ 31-Oct $ 2,140.00 $ 571.00
Infrastructure DJ 2,492,100.00 649,000.00
Industrial DJ 27-Dec 1,840,510.00 423,317.30
Commercial DJ 20-Jan 12,871,910.00 2,974,454.08
Hospitality DJ 21-Jan $ 23,937.00 $ 16,581.00
Infrastructure DJ 24-Jan 102,800.00
DJ
Commercial DJ
Hospitality DJ 19-Feb $ 9,734.50 $ 4,206.73
Commercial DJ 1,536,960.00 353,500.80
Gp ratio
5%
43%
22%
22%
24%
30%
26%
24%
23%

20%
12%
20%
20%
20%
20%
26%
29%

16%
24%
20%
15%

40%
20%
25%
23%
41%
28%
24%
23%
44%
47%
28%
32%

28%
37%
23%
21%
24%
33%

27%
26%
23%
23%
69%

43%
23%
No Offer Date Project Client Progress
Ref
19 119 15-Jun Switch Yard New Royal Pending
26 126 4-Aug MDH Emergency MDH Pending
27 127 5-Aug MDH Outdoor MDH Pending
36 136 30-Aug MGD Gass Light MDH Pending
41 141 6-Sep Intercontinental decorative Pearl Hotel Pending
48 148 2-Oct Indoor stadium at Kuliyapitiya Micro Constructions Pending
50 150 4-Oct 400W MH Lamp Fittings SLPA Pending
51 151 5-Oct Benedict Hall Stage lighting Benedict Catholic Pending
54 154 8-Oct Emg and Exit Sign Tudawe Pending
55 155 2-Nov R.Premadasa Stadium THK Pending
56 156 10-Dec CEB Substation New Royal Pending
57 100 5-Jan Radisson Project Tudawe Pending
61 104 6-Feb MOD MOD Pending
62 105 7-Feb EMG Intercontinental DIMO Pending
63 106 8-Feb New Royal Philips New Royal Pending
Handled Submitte
Nature Selling Value Cost Gross profit
by d date
Infrastructure DJ
Commercial DJ 9-Aug $ 17,720.00 $ 10,712.80 $ 7,007.20
Commercial DJ 16-Aug $ 3,023.00 $ 600.00
Hospitality DJ 5-Feb $ 23,975.00 $ 6,670.00
Hospitality DJ
Infrastructure DJ 11-Oct 1,046,400.00 241,757.47
Industrial DJ 13-Oct 2,600.00 $ 620.00
Commercial DJ 24-Oct 4,270,700.00 1,419,450.00
Commercial DJ 31-Oct $ 2,140.00 $ 571.00
Infrastructure DJ 2,492,100.00 649,000.00
Industrial DJ 27-Dec 1,840,510.00 423,317.30
Commercial DJ 20-Jan 12,871,910.00 2,974,454.08
Commercial DJ
Hospitality DJ 19-Feb $ 9,734.50 $ 4,206.73
Commercial DJ 1,536,960.00 353,500.80
Gp ratio

1,261,296.00 40%
108,000.00 20%
1,200,600.00 28%
-
241,757.47 23%
111,600.00 24%
1,419,450.00 33%
102,780.00 27%
649,000.00 26%
423,317.30 23%
2,974,454.08 23%
-
757,211.40 43%
353,500.80 23%
9,602,967.05
No Offer Date Project Client Progress
Ref
2 102 6-Apr Emergency Light and Exit New Royal Won
24 124 2-Aug SLPA 160 Nos of LED Lamps Cranes SLPA Won
34 134 28-Aug Emergency and Exit New Royal Won
35 135 29-Aug Emergency Ventilux New Royal Won
42 142 7-Sep Intercontinental Façade Pearl Hotel Won
43 143 8-Sep Male Sport Court Sanken Won
59 102 7-Jan National Sports Complex Sugathadasa Won
Handled Submitte
Nature Selling Value Cost Gross profit
by d date
Commercial DJ 28-May 736,400.00 421,176.88 315,223.12
Industrial DJ 3-Sep $ 40,356.00 $ 6,156.00
Commercial DJ 28-Aug $ 7,615.90 $ 3,333.26
Commercial DJ 29-Aug 1,426,800.00 665,000.00
Hospitality DJ 1,200,000.00
Infrastructure DJ 14-Jan $ 44,660.00 $ 12,600.00
Infrastructure DJ 24-Jan 102,800.00
Gp ratio
315,223.12 43%
1,108,080.00 15%
599,986.25 44%
665,000.00 47%
1,200,000.00
2,268,000.00 28%
-
6,156,289.37