Q1 An insurance company has decided to modernize and refit one of its branch offices Some of
the existing office equipments will be disposed of but the remaining will be returned to the
branch of completion of the renovation work Tenders are invited from a number of selected
contractors The contractors will be responsible for all the activities in connection with
renovation work excepting the prior removal of the old equipment and its subsequent
replacement
a) Draw the network diagram showing the interrelations between the various activities of
the project
b) Calculate total completion time and the critical path
c) Find the effect on the overall duration of the project if the estimates or tenders can be
obtained in two weeks from the contractors by reducing their numbers
Q2 The following network diagram represent activities associated with the project
Activities A B C D E F G H I
Optimistic 5 18 26 16 15 6 7 7 3
time
Pessimistic 10 22 40 20 25 12 12 9 5
time
Most 8 20 33 18 20 9 10 8 4
likely time
F
3
B I 7
6
1 A E
H
2 D 5
C
G
Q 3 A small project is composed of 7 activities whose time estimates are listed in the table below
Activities are identified by their beginning (i) and ending (j) node numbers