Professional Documents
Culture Documents
Schedule Reading Material PDF
Schedule Reading Material PDF
Project scope definition is the process whereby a project is defined and prepared for
execution. It helps to decide on whether or not to proceed with the project. An incomplete
scope definition in early stages of a project’s life cycle is a common source of difficulty
in construction project development process. Meanwhile, the developing of the project
can affect positively or negatively a variety of interests. Construction projects in specific
bring different degrees of changes on the surrounding environment and people, not only
limited at the construction site. Therefore, project definitions boundaries may be
redefined, or subjected to differing expectations and interpretation by different
stakeholders.
A Work Breakdown Structure (WBS) is a deliverable-oriented grouping of project
components that defines and organizes the total scope of the project; work not in the
WBS is outside the scope of the project. Stated in another way, a WBS is the hierarchy of
work you must accomplish to complete a project. The WBS is structured in levels of
Sequencing can be performed with the aid of a computer (e.g., by using project
management software) or with manual techniques. Manual techniques are often more
effective on smaller projects. Manual and automated techniques may also be used in
combination.
4. Define Project Base Calendars
A base calendar defines the work period of a project organization. Project Base Calendars
cumulatively define the working and non-working periods of the project activities with
respect to the performing organization(s).
Note that Work Calendars can be different for:
• Organizations involved in the project
• Resources
• Activities
Note that each party may also have its designated holidays (non-work periods); for
instance, national day, Independence Day, other company designated holidays, etc. Some
of these non-work periods may be common among the various companies involved while
some may belong to specific organizations only.
Based on logical relationships among activities and time estimates, preparing a time
chart showing the start and finish times for each activity, and hence calculation of total
Construction Planning and Scheduling, Reading Material
Prepared by Mr. Giduma B.
7
project duration by applying network analysis techniques such as forward (backward)
pass and floats calculation; identifying the critical path; carrying out resource smoothing
(or levelling) exercise for critical or scarce resources including re-costing of the schedule
taking into account resource constraints.
When planning a project it is necessary to assign the work on the project to the project
team so that there will be one person responsible for each part of the project and it is clear
who performs the work, with whom it should be consulted, and who is to be informed of
this activity.
The responsibility matrix is a tool used to define the powers of individual project team
members for various parts of project works (work packages). In professional literature, it
ii) Burst event - formed when more than one activity leaves an event.
iii) Merge and burst event – a combination of the two. When more than one
activity come and join together and more than one activity leaves an event.
Illustrations
1. Activity B cannot start until A is completed. (B depends on A or B is preceded by A
or B succeeds A).
A B
2. Activities B and C cannot start until activity A is completed i.e. B and C depends on
A.
B
A
A
C
B D
5. Activity A and B must be completed before activity C can start. Only activity B must
be completed before activity D can start.
A C
B D
A C
B D
A D
B
E
Exercise 1
Draw the following network diagrams
1. Activity Pre-requisite
A -
B -
C A
D B
2. Activity Pre-requisite
A -
Construction Planning and Scheduling, Reading Material
Prepared by Mr. Giduma B.
14
B A
C A
D B
E C
F D&E
3. Activity Preceding activity
A -
B -
C A
D A
E B
F B
G C&E
H C, E, & F
A(-), B(-), C(A), D(B), E(A&C), F(B), G(C&D), H(G&F), I(E), J(H&I), K(J)
Exercise 2
Precedence table for a project is given as follows:
Activity Predecessor Time duration
A - 3
B - 2
C - 2
D A 4
E B 4
F B 7
G C 4
H A, D 2
I B, E 5
J B, C, F, G 6
K A, B, D, E, I, H 3
a) Draw the A-O-N network diagram
b) Determine ES, LS, EF & LF of each activity
c) Find the critical path
d) Find project duration
i) Construct the precedence table, and hence draw the A-O-N network for the project.
ii) Determine the critical path and the project duration using the forward pass and
backward pass method.
iii) Construct a table of the ES, LS, EF, LF, and total float for each activity.
The three-time estimates are combined statistically to develop the expected time (te) for
an activity.
O M te P
Exercise
A project has the following activities and characteristics.
a. Draw the PERT network and, Determine the expected duration, standard
deviation and variance of the project from above information!
The objective of the time-cost trade-off analysis is to reduce the original project duration,
determined form the critical path analysis, to meet a specific deadline, with the least cost.
In general, there is a trade-off between the time and the direct cost to complete an
activity; the less expensive the resources, the larger duration they take to complete an
activity. Shortening the duration on an activity will normally increase its direct cost
which comprises: the cost of labor, equipment, and material.
Indirect costs, on the other hand, are the necessary costs of doing work which cannot be
related to a particular activity. The indirect cost will decrease by decreasing the project
duration, as the indirect cost are almost a linear function with the project duration.
If each activity was scheduled for the duration that resulted in the minimum direct cost in
this way, the time to complete the entire project might be too long and substantial
penalties associated with the late project completion might be incurred. Thus, planners
Exercise 1
(b) After receiving the estimated time to complete the road, the client has asked
. ABC Construction Ltd to reduce the completion time by 7 months. What
would be the minimum extra cost to meet this revised deadline?
(c) The client has now requested a further five months reduction in the project
duration. Comment on this request.