1. You, as project manager, are advising your customer to choose the right approach
for a project. In this case, the project has dynamic requirement but he would like to
allow feedback on partially completed work to improve and modify that work.
Which of the following approaches is most suitable?
Marked Answer :
No life cycle can be perfect for all projects. Instead, each project finds a spot on the
continuum that provides an optimum balance of characteristics for its context. In this
case, an iterative life cycles would allow feedback on partially completed or
unfinished work to improve and modify that work. Therefore, the right choice for this
question is B. [Agile Practice Guide, Page 19] [Life Cycle Selection]
2. You are the project manager in the development of a new website. In this project,
the team does short iterations, daily stand-ups, retrospectives, cost estimations and
progress tracking. Which of the following approaches is the project using?
Marked Answer :
4. As part of your agile project, a project team member proposes using a kanban
board to visualize the flow of work in the project. What main benefit can a kanban
board bring about?
Marked Answer :
5. In the development of a new website, you, the project manager, chose to use an
agile approach. However, many project team members are inexperienced in the use
of that approach. What should you do first?
Marked Answer :
6. In a car design project, project sponsor can not wait for the project to be completed
and he is willing to receive first a subset of design. Which of the following life cycle
approachs would you propose him?
Marked Answer :
7. In an agile project you manage, the quality of the product increments are poor.
What should you do?
Marked Answer :
Correct Answer :
10. You, as manager in an agile project, lack of guidelines to develop and set
the direction on the next functionality to be develop your project .Who is the agent
responsible of that in agile projects?
Marked Answer :
B. Product owner.
Correct Answer :
B. Product owner.
Total Marks : 1MARKS OBTAINED 1
11. In the construction of a new urban area, the project team expects the initial
requirements to change. On the other hand, you believe the adaptability of the
project to the changing customer needs is key to achieve project success. Which of
the following approach would you recommend?
Collected by engr. SALEH ELGEBALY PMI-PMP®
Contact me : +966500800794
Collected by engr. SALEH ELGEBALY PMI-PMP®
Marked Answer :
12. In your agile project, you are afraid the team may be working in the
product in the wrong direction. As a general guideline, how often would you
recommend to demonstrate the working product?
Marked Answer :
14. After several iterations, your team has unclear work assignments. How
would you tackle this problem?
Marked Answer :
Marked Answer :
16. What is the most essential practice in agile to help the team learn from
previous work on the product and its process?
Marked Answer :
D. Retrospective.
Correct Answer :
D. Retrospective.
Total Marks : 1MARKS OBTAINED 1
17. Sam has just been hired as project manager of an IT development project.
The project will have dynamic requirements and the activities will be performed
once for a given increment with frequent smaller deliveries. He is discussing with
the project sponsor the most suitable type of life cycle on this case. What should
Sam recommend?
Marked Answer :
18. Which of the following statements is NOT true related to agile teams?
Marked Answer :