Agile: 21 Future PMP Exam Questions


In this course, I have carefully prepared for you 21 PMP Exam Questions about Agile
environment.
These questions will ONLY be part of your PMP Exam after the exam changes in July
2020.
All of them are aligned with the last version of Agile Practice Guide 6th Edition.
I hope they can help you pass your PMP Exam in 2020.

Collected by engr. SALEH ELGEBALY PMI-PMP®


Contact me : +966500800794
Collected by engr. SALEH ELGEBALY PMI-PMP®

1. You, as project manager, are advising your customer to choose the right approach
for a project. In this case, the project has dynamic requirement but he would like to
allow feedback on partially completed work to improve and modify that work.
Which of the following approaches is most suitable?
Marked Answer :

B. Iterative life cycle.


Correct Answer :

B. Iterative life cycle.


Total Marks : 1MARKS OBTAINED 1

No life cycle can be perfect for all projects. Instead, each project finds a spot on the
continuum that provides an optimum balance of characteristics for its context. In this
case, an iterative life cycles would allow feedback on partially completed or
unfinished work to improve and modify that work. Therefore, the right choice for this
question is B. [Agile Practice Guide, Page 19] [Life Cycle Selection]
2. You are the project manager in the development of a new website. In this project,
the team does short iterations, daily stand-ups, retrospectives, cost estimations and
progress tracking. Which of the following approaches is the project using?
Marked Answer :

B. Combined agile and predictive approach.


Correct Answer :

B. Combined agile and predictive approach.


Total Marks : 1MARKS OBTAINED 1

3. As project manager, you decided to have multitask team members instead of a


dedicated team. Which of the following statements is true?
Marked Answer :

A. Multitasking slows the progress of the team.


Correct Answer :

A. Multitasking slows the progress of the team.


Total Marks : 1MARKS OBTAINED 1

Collected by engr. SALEH ELGEBALY PMI-PMP®


Contact me : +966500800794
Collected by engr. SALEH ELGEBALY PMI-PMP®

4. As part of your agile project, a project team member proposes using a kanban
board to visualize the flow of work in the project. What main benefit can a kanban
board bring about?
Marked Answer :

D. It helps the team to become more productive.


Correct Answer :

D. It helps the team to become more productive.


Total Marks : 1MARKS OBTAINED 1

5. In the development of a new website, you, the project manager, chose to use an
agile approach. However, many project team members are inexperienced in the use
of that approach. What should you do first?
Marked Answer :

C. You should make work visible using kanban boards.


Correct Answer :

C. You should make work visible using kanban boards.


Total Marks : 1MARKS OBTAINED 1

6. In a car design project, project sponsor can not wait for the project to be completed
and he is willing to receive first a subset of design. Which of the following life cycle
approachs would you propose him?
Marked Answer :

C. Incremental life cycle.


Correct Answer :

C. Incremental life cycle.


Total Marks : 1MARKS OBTAINED 1

7. In an agile project you manage, the quality of the product increments are poor.
What should you do?
Marked Answer :

A. I should use test-driven development practices.


Collected by engr. SALEH ELGEBALY PMI-PMP®
Contact me : +966500800794
Collected by engr. SALEH ELGEBALY PMI-PMP®

Correct Answer :

A. I should use test-driven development practices.


8. Your agile project team thinks about how to optimize the flow value. What benefits
will NOT that bring about?
Marked Answer :

D. It will allow the team to multitask efficiently.


Correct Answer :

D. It will allow the team to multitask efficiently.


Total Marks : 1MARKS OBTAINED 1

9. Simon, a project sponsor in an IT development project, would like to to have great


results in his project such as fast delivery of features with remarkable quality
standards. What type of team would you recommend him?
Marked Answer :

B. A small group with less specialist roles.


Correct Answer :

B. A small group with less specialist roles.


Total Marks : 1MARKS OBTAINED 1

10. You, as manager in an agile project, lack of guidelines to develop and set
the direction on the next functionality to be develop your project .Who is the agent
responsible of that in agile projects?
Marked Answer :

B. Product owner.
Correct Answer :

B. Product owner.
Total Marks : 1MARKS OBTAINED 1

11. In the construction of a new urban area, the project team expects the initial
requirements to change. On the other hand, you believe the adaptability of the
project to the changing customer needs is key to achieve project success. Which of
the following approach would you recommend?
Collected by engr. SALEH ELGEBALY PMI-PMP®
Contact me : +966500800794
Collected by engr. SALEH ELGEBALY PMI-PMP®

Marked Answer :

D. Agile life cycle.


D. Agile life cycle.
Total Marks : 1MARKS OBTAINED 1

12. In your agile project, you are afraid the team may be working in the
product in the wrong direction. As a general guideline, how often would you
recommend to demonstrate the working product?
Marked Answer :

B. Once every 2 weeks.


Correct Answer :

B. Once every 2 weeks.


Total Marks : 1MARKS OBTAINED 1

13. How should planning be in iteration-based agile projects?


Marked Answer :

D. Agile teams do not plan just once in one single chunk.


Correct Answer :

D. Agile teams do not plan just once in one single chunk.


Total Marks : 1MARKS OBTAINED 1

14. After several iterations, your team has unclear work assignments. How
would you tackle this problem?
Marked Answer :

A. Consider kanban boards to see the flow of work.


Correct Answer :

A. Consider kanban boards to see the flow of work.


Total Marks : 1MARKS OBTAINED 1

15. Which of the following is NOT a shared risk reward relationship in


procurement?
Collected by engr. SALEH ELGEBALY PMI-PMP®
Contact me : +966500800794
Collected by engr. SALEH ELGEBALY PMI-PMP®

Marked Answer :

C. Time and materials.


Correct Answer :

C. Time and materials.


Total Marks : 1MARKS OBTAINED 1

16. What is the most essential practice in agile to help the team learn from
previous work on the product and its process?
Marked Answer :

D. Retrospective.
Correct Answer :

D. Retrospective.
Total Marks : 1MARKS OBTAINED 1

17. Sam has just been hired as project manager of an IT development project.
The project will have dynamic requirements and the activities will be performed
once for a given increment with frequent smaller deliveries. He is discussing with
the project sponsor the most suitable type of life cycle on this case. What should
Sam recommend?
Marked Answer :

C. Incremental life cycle.


Correct Answer :

C. Incremental life cycle.


Total Marks : 1MARKS OBTAINED 1

18. Which of the following statements is NOT true related to agile teams?
Marked Answer :

C. Agile create the ability to do more work.


Correct Answer :

C. Agile create the ability to do more work.


Total Marks : 1MARKS OBTAINED 1
Collected by engr. SALEH ELGEBALY PMI-PMP®
Contact me : +966500800794
Collected by engr. SALEH ELGEBALY PMI-PMP®

19. Martin, as project manager, is worried about achieving a stable velocity


after two iterations. Is Martin right?
Marked Answer :

B. No, it usually takes four to eight iterations to achieve a stable velocity.


Correct Answer :

B. No, it usually takes four to eight iterations to achieve a stable velocity.


Total Marks : 1MARKS OBTAINED 1

20. A project manager focused on improving the teamwork process in previous


iterations. However, there is barely no improvement. How could you tackle that?
Marked Answer :

D. Capture no more than three items to improve at each retrospective.


Correct Answer :

D. Capture no more than three items to improve at each retrospective.


Total Marks : 1MARKS OBTAINED 1

21. What is the servant leadership about?


Marked Answer :

A. It is about the practice of leading through service to the team.


Correct Answer :

A. It is about the practice of leading through service to the team.