10 x 8 = 80 x 3 sides LEAD WASHERS
= 240 / 6 meters 1. 704
=40 pieces 10 mm 2. 704 / 75 = 9.3 / 9.5 Kilograms
FOOTING
1. V = (1.5 x 1.5 x 0.3) 9
V = 6.075 Cubic Meters
CONCRETE WALLS
Side 1
V = 10 x 0.20 x 4.2
V = 8.4 x 3 faces walls
V = 25.2 cubic meters
Side 2
V = 6 x 0.20 x 4.2 x 0.30
V = 5.04 x 3 faces walls
V = 15.12 cubic meters
Exterior walls
V = 4.2 x 2.0 (2.5 + 1.5 + 2.5 + 1.5)
V = 4.2 x 0.20 (8)
V= 6.72 Cubic meters