1. 34 X 22 = 704 pieces
2. 704 / 180 3.9 / 4 Kilograms

CONSTRUCTION ESTIMATE G. I WASHERS


1. 704 X 2 = 1408
FOOTING
2. 1408 / 128 = 11 Kilograms
1. (1.3 x 10 x 2) 6
= 30 x 6 footing PLAIN G.I. STRAP ON 2” X 3” PURLINS
= 180 / 6 meters 1. 704
= 30 Pieces 10mm beams / footing tie beam 2. 704 / 384 = 1.83 / 2 Pieces Plain G. I Sheets

Side 1
10 x 8 = 80 x 3 sides LEAD WASHERS
= 240 / 6 meters 1. 704
=40 pieces 10 mm 2. 704 / 75 = 9.3 / 9.5 Kilograms

Multiplied by 2 for beams = 80 Pieces UMBRELLA NAILS


10 mm 1. 34 Pieces of 9 ft G.I Sheets x 22 = 748
2. 748 / 120 = 6.23 / 6.5 Kilograms
Side 2
6 x 8 = 48 x 3 sides SUMMARY OF MATERIALS
= 144 / 6 meters 34 pieces 32” x 9” Corrugated G.I Sheets
= 24 pieces 10 mm 4 Kilograms Rivets
11 Kilograms Washers
Multiplied by 2 for beams = 48 pieces 2 Pieces Plain G.I Sheets
1.5 kilograms Lead Washers
COLUMNS 6.5 kilograms Umbrella Nails

4 x 4.7 x 9 = 18.8 FOOTING TIE BEAMS AND BEAMS


Multiplied by 9 posts Side 1
= 169.2 / 6 meters 1. V= (3 x 0.3 x 0.3) x 6
= 28.210 by 10mm V = 1.62 Cubic Meters

4 x 4.7 x 9 = 18.8 Side 2


Multiplied by 9 posts
=169.2 / 6 meters 1. V= (5 x 0.3 x 0.3) x 6
=28.210 by 16mm V= 2.7 Cubic meters

SUMMARY Total Volume


1.62 + 2.7 = 4.32 x 2 for beams = 8.64 Cubic
28.2 / 29 Pieces 16mm 6 meters long meters
213.21 / 214 Pieces 10 mm 6 meters long
Cement: 8.64 x 9.0 = 77.76 bags
ROOFING Sand: 8.64 x 0.50 = 4.32 Cubic Meters
Gravel: 8.64 x 1.0 = 8.64 Cubic Meters
Corrugated G.I (Galvanized Iron) Sheets
1. 11.6 m / 0.70 m = 16.57 x 2 faces
= 33.1428 / 34 G.I. sheets by 9 meters
WALL FOOTING 23.52 = 18 +8.64 + 0.99 + 11.2 +47+0.4 = 85.87 /
Total length: 2.5 + 1.5 + 2.5 + 1.5 + 3 86 cubic meter gravel.
= 11 meters
REINFORCEMENTS
1. V = 11 + 0.3 + 0.3
V = 0.99 cubic meters Walls
Cement: 0.99 x 9.0 = 8.91 bags 1. A = 10 x 4.7
Sand: 0.99 x 0.50 = 0.495 Cubic meters A= 47 square meters
Gravel: 0.99 x 1.0 = 0.99 Cubic meters 47 x 1.60
= 75 meters long
POSTS 75 x 2.15
1. V = 4.2 x (0.400 x 0.350) x 9 posts = 161.25
V = 5.292 Cubic Meters

FOOTING
1. V = (1.5 x 1.5 x 0.3) 9
V = 6.075 Cubic Meters

Total Volume: 5.292 + 6.075 = 11.287

Cement: 11.287 x 90 = 101.5 bags


Sand: 11.287 x 0.50 = 5.6 Cubic meters
Gravel: 11.287 x 1.0 = 11.287 Cubic meters

CONCRETE WALLS
Side 1
V = 10 x 0.20 x 4.2
V = 8.4 x 3 faces walls
V = 25.2 cubic meters

Side 2
V = 6 x 0.20 x 4.2 x 0.30
V = 5.04 x 3 faces walls
V = 15.12 cubic meters

Exterior walls
V = 4.2 x 2.0 (2.5 + 1.5 + 2.5 + 1.5)
V = 4.2 x 0.20 (8)
V= 6.72 Cubic meters

Total: 25.2 + 15.12 + 6.72 = 47.04 Cubic Meters

Cement: 47.04 x 9.0 = 423.36 bags


Sand: 47.04 x 0.50 = 23.52 Cubic Meters
Gravel: 47.04 x 1.0 = 47.04 Cubic Meters

Summary

162 + 77.6 +8.91 + 101.5 +423.36 = 773.53 / 774


bags cement 9 + 4.32 + 0.495 + 5.6