I. GENERAL SPECIFICATIONS

I.1. GENERAL DESCRIPTION OF WORK


The work to be done and executed shall
include the furnishing of labor and materials,
equipment and specialized work in the
construction of the house completely as shown in
the drawing and as specified herein. All
reference to details and plans in the
specifications, when not included in the set of
drawings, shall furnished later upon the request.

I.2. PROPORTION OF CONCRETE


All concrete work shall be done on strict
accordance with the Department of Public Works
specifications for concrete and revised
proportioning as follows:
Use Class A (1:2:4) concrete mixture, unless
otherwise for footing, beams, columns, steps and
floors. Use Class B (1:2.5:5) concrete wall,
concrete drainage and catch basin, and other
works of similar nature.

I.3. CONSISTENCY
It is being recognized that an excess of
water seriously reduces the strength of concrete,
the mixture shall be made as dry as possible to
produce of workable concrete.

1
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

I.4. REINFORCING STEEL BARS


Unless otherwise specified on plan,
reinforcing steel bars shall be deformed bars and
in accordance with the metal reinforcing
requirements of standard specifications on
highways and bridges as adopted by the
government. When placed in work, it shall be free
dirt, paints, spills of other foreign substance.

I.5. WOOD FORMS


Wood forms shall be sound, good quality, free
from large loose knots and otherwise suitable to
facilitate finishing exposed concrete as
specified.

I.6. CURING
Use water curing which shall be affected by
keeping the forms at all times sufficiently wet
with clean water to prevent the joints in the
forms of opening. Concrete surface not protected
by forms shall be protected from the loss of
surface moisture by covering with craft paper
quilts or burlaps. Protected material shall be
kept thoroughly wet for the duration of curing
period which shall not less than 7 days.

2
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

I.7. E X C A V A T I O N S FOOTING AND


FOUNDATIONS
The bottoms of all excavations for footing
and foundation which shall be undisturbed, earth
properly leveled off, tampered and approved by
the Architect. Excavations shall be entirely free
from water during the pouring of concrete.

I.8. CONCRETE FLOORS AND STEPS ON


FILL OR ON GROUND
Concrete from steps on fill shall be laid on
prepared foundation which shall be placed as
follow:

The earth or sand fill shall be laid to a uniform


grade below the excavation of the finished
floors, being placed in the layers not exceeding
15cm in thickness, its layer being thornily
wetted and tampered. The said fill shall be maid
as concrete walls and foundation shall have
sufficient strength. Concrete floor surface and
other surface exposed after removed of forms
shall be kept moist for a period of at least 7
days after being placed. All concrete placed
during hot weather shall be protected from the
rays of the sun and thoroughly wetted atlas three
times during the first 7 days.

3
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

I.9. FOUNDATIONS
All foundations shall be Class "A" (1:2:4)
concrete mixture with the necessary reinforcement
indicated in the plans. All zocalos shall be
0.15m thick concrete hollow blocks and shall be
filled with class “B" (1:3:5) mortar mixture with
the necessary reinforcement as indicated in the
plan.


I.10.FLOORINGS
Unless otherwise noted on the plan, all
flooring shall be 0.10m thick concrete slab on
fill on at 0.50m on center bothways.

I.11.WALLS
All exterior and interior walls shall be of
concrete hollow blocks with the necessary
reinforcement unless otherwise indicated in the
plans.


I.12.CEILING
All ceiling boards shall be of 6mm thick
ordinary plywoodnon 0.05x1.05m ceiling joist
spaced at 0.60m on center bothways.


I.13.DOORS AND WINDOWS


(See schedule on Plans)

4
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

I.14.CABINETS
All cabinets shall be of ordinary plywood.

All cabinet doors shall be a 12mm thick plywood
and louver as indicated in the follow-up design.


I.15.ROOFING
Unless otherwise noted on the plan, concrete
roofing shall be 0.15m thick and shall be applied
of water proofing. Temp bars spaced at 0.50m on
center bothways.


I.16.FINISHING HARDWARES
All finishing hardwares shall be of first
quality brand acceptable to the Architect and the
Owner(s).

I.17.PAINTINGS
All concrete walls shall received at least
two coats of approved cement paint. All exposed
lumber shall received at least three coats of
semi gloss paints or varnish as per
specifications of the Architects.

I.18.ELECTRICAL
(See Addt'l Specifications on Plans)

5
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

01.05 01.06
All electrical installations shall conform
with the latest National Electrical Code of the
Philippines and with the approval of local
Electrical Utility Company.
E - 02
All electrical wiring and fixtures shall be
of good quality brand approved by the Architect
and the Owner(s).

I.19.PLUMBING

All plumbing installation shall conform with
National Plumbing Code of the Philippines. All
pipings and fixtures shall be of good quality
brand approved by the Architect and the Owner(s).

01. All plumbing works included herein shall


be executed according to the requirements of the
philippine plumbing code and the rules and
regulations of the local government.

02. Coordinate the drawing with other related


drawings and specifications. The designer shall
be noticed immediately of any discrepancy found
therein.
03. Pipes shall be with prior approval of the
architect and engineer.
04. Proposed sanitary utilities shall conform
the actual location, depth and invert elevation
of all existing pipes and structures as verified
by the contractor.

6
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

05. The slopes for horizontal branches


(sewer) shall maintain 1% as minimum unless noted
otherwise.

06. All fixtures shall be vented, unless


otherwise indicated.

07. Air chamber: all individual branches to


fixture or group of fixtures and/or equipment
shall be provided with air chamber capped
vertical pipe extension of dimension as in
detail.

08. All sewer lines shall be sanimold extra


UPVC pipe (HD)

09. All main vents stacks shall be UPVC pipe


series 1,000

10. All circuit vent shall be UPVC pipe


series 1,000

11. All downspout (D.S.) shall be PVC pipe


series 1,000

12. All cold water lines shall be PVC pipe


schedule 40

I.20.LANDSCAPE AND INTERIOR DESIGN


Landscape and Interior designs shall be
approved by the Architects and the Owner(s).

7
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

II. BILL OF MATERIALS

DESCRIPTION UNIT QTY. UNIT COST TOTAL COST

A. TEMPORARY FACILITIES (TEMFACIL) WORKS L.S. 1.00 24,500.00 24,500.00


B. CLEARING & GRUBBING L.S. 1.00 4,320.00 4,320.00
C. EARTHWORKS
1. Excavation cu.m 55.11 210.00 11,573.10
2. Backfill cu.m 42.86 700.00 30,003.05
3. Embanckment cu.m 21.60 533.00 11,512.80
4. Gravel Bedding cu.m. 11.66 1,000.00 11,664.00
sub total 64,752.95
D. CONCRETE WORKS
1. Cement (Portland Type 1) bag 250.00 260.00 65,000.00
2. Washed Sand cu.m. 14.00 700.00 9,800.00
3. Gravel cu.m. 27.60 1,200.00 33,120.00
4. Lumber
4.1. 2" x 2”x 8m (Rough,Coco) pc. 334.00 60.00 20,040.00
5. Plywood
5.1 1 / 2" (Ordinary) sheet 31.00 560.00 17,360.00
6. Common Wire Nails (CWN)
6.1 1" (25 mm.) kilo 3.00 56.00 168.00
6.2 2“ (50 mm.) kilo 7.00 52.00 364.00
7 Water Proofing Cement bag 84.00 45.00 3,780.00
sub total 149,632.00
E. MASONRY WORKS
1. Concrete Hollow Blocks (CHBs)
1.1 4” (101.6mm) pc. 506.00 12.60 6,375.60
1.2 6” (150 mm.) pc. 2,625.00 15.50 40,687.50
2. Cement (Portland Type 1) pc. 468.00 265.00 124,020.00
3. Screened Sand cu.m. 18.80 640.00 12,032.00
4. Fine Sand cu. m. 7.90 640.00 5,056.00
5. Gravel cu.m. 53.40 800.00 42,720.00
sub total 230,891.10
F. SCAFFOLDINGS & STAGINGS
1. Lumber pc. 12.00 60.00 720.00
2. Common Wire Nail (CWN)
2.1 4” ( 100 mm) kilo 113.81 49.00 5,576.69
sub total 6,296.69
G. STEEL REINFORCEMENT WORKS
1. Reinforcing Bars
1.1. 10 mm. x 6 mtr. pc. 271.00 81.31 22,035.01
1.2. 10 mm. x 9 mtr. pc. 104.00 110.88 11,531.52
1.4. 12 mm. x 6 mtr. pc. 21.00 117.22 2,461.62
1.5. 16 mm. x 6 mtr. pc. 162.00 206.40 33,436.80
1.6. 16mm. x 7.5 mtr. pc. 31.00 236.70 7,337.70
1.7.16mm. x 9 mtr. pc. 26.00 258.90 6,731.40
2. G.I. Tie Wires #16 roll 2.00 2,100.00 4,200.00
sub total 87,734.05

8
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

H. ROOFING WORKS
1. Rafter Angle Bars
1.1 1 1/2 x 1 1/2 x 4mm pc. 22.00 816.00 17,952.00
2.1 12mm diameter x 6m pc. 18.00 117.22 2,109.96
2. Purlins
2.1 2” x 6” C-Purlins pc. 2.00 1,100.00 2,200.00
3. GI Gutter
3.1 Plain pc. 4.00 900.00 3,600.00
3.2 Fascia flashing pc. 5.00 200.00 1,000.00
4. PRE PAINTED LONG SPAN ROOFING
4.1 11m x 0.76m colorbond trimdek hi-tenpc. 6.00 500.00 3,000.00
5 Others L.S. 1.00 50,000.00 50,000.00
sub total 79,861.96
I. CARPENTRY WORKS
1. Doors
2.1 D1 Solid Core Panel Door pc. 5.00 4,284.00 21,420.00
2.2 D2 Solid Core Panel Type Door pc. 2.00 1,250.00 2,500.00
2.3 D3 Sliding Glass Door pc. 1.00 53,148.72 53,148.72
2.4 Door Knobs
2.4.1 D1 pc. 5.00 595.00 2,975.00
2.4.2 D2 pc. 2.00 235.00 470.00
2. Windows
3.1 Fix with Awning Window set 1.00 6,624.00 6,624.00
3.2 Fix with Awning Window set 1.00 6,624.00 6,624.00
3.3 Fix with Sliding Window set 3.00 3,930.00 11,790.00
3.4 Sliding Window set 1.00 3,500.00 3,500.00
3.5 Sliding Window set 2.00 3,368.00 6,736.00
3 Common Wire Nails (CWN)
3.1 3 1/2” (87.5 mm) kilo 2.76 50.00 138.00
3.2 4" (100 mm) kilo 4.42 49.00 216.58
3.3 4 1/2” (112.5 mm) kilo 5.53 49.00 270.97
3.4 5” (125 mm) kilo 7.46 49.00 365.54
sub total 116,778.81
J. PAINTING WORKS
1. Masonry Paint Gallon 15.00 450.00 6,750.00
2. Concrete Primer Gallon 14.00 500.00 7,000.00
4. 12" Roller Brush pc. 5.00 92.50 462.50
5. Baby Roller Brush pc. 5.00 63.00 315.00
6. 4" Paint Brush pc. 5.00 281.00 1,405.00
7. 3" Paint Brush pc. 5.00 104.75 523.75
8 2" Paint Brush pc. 5.00 52.75 263.75
sub total 16,720.00
K. TILE WORKS
1 16” x 16” pc. 101.00 53.00 5,353.00
2 12” x 12” pc. 739.00 37.00 27,343.00
3 8” x 8” pc. 788.00 29.50 23,246.00
4 Cement Mortar bag 10.00 265.00 2,650.00
5 White Cement bag 12.75 48.50 618.38
6 Adhesive bag 13.00 420.00 5,460.00
sub total 64,670.38

9
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

SUMMARY: (BILL OF MATERIALS)

A. TEMPORARY FACILITIES (TEMFACIL) WORKS 24,500.00

B. CLEARING & GRUBBING 4,320.00

C. EARTHWORKS 64,752.95

D. CONCRETE WORKS 149,632.00

E. MASONRY WORKS 230,891.10

F. SCAFFOLDINGS & STAGINGS 6,296.69

G. STEEL REINFORCEMENT WORKS 87,734.05

H. ROOFING WORKS 79,861.96

I. CARPENTRY WORKS 116,778.81

J. PAINTING WORKS 16,720.00

K. TILE WORKS 64,670.38

TOTAL MATERIAL COST 846,157.94


TOTAL LABOR COST 253,847.38

TOTAL DIRECT COST (EDC) 1,100,005.32

TOTAL INDIRECT COST 184,800.89


OVERHEAD / CONT. / MISC. 132,000.64
PROFIT 33,000.16
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 19,800.10

TOTAL PROJECT COST 1,284,806.21

Prepared by:

JOHN RUDSTER O. JAMOLO & AARAH DYNIELLE T. EOR


CIVIL ENGINEERS

10
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

III. BILL OF QUANTITIES

I.TEMPORARY FACILITIES (TEMFACIL) WORKS


TOTAL MATERIAL COST 24,500.00

TOTAL LABOR COST 7,350.00

TOTAL DIRECT COST (EDC) 31,850.00

TOTAL INDIRECT COST 5,350.80

OVERHEAD / CONT. / MISC. 3,822.00

PROFIT 955.50

TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 573.30

TOTAL PROJECT COST 37,200.80

II.CLEARING & GRUBBING


TOTAL MATERIAL COST 4,320.00

TOTAL LABOR COST 1,296.00

TOTAL DIRECT COST (EDC) 5,616.00

TOTAL INDIRECT COST 943.49

OVERHEAD / CONT. / MISC. 673.92

PROFIT 168.48

TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 101.09

TOTAL PROJECT COST 6,559.49

III. EATRHWORKS
TOTAL MATERIAL COST 98,320.88

TOTAL LABOR COST 29,496.26

TOTAL DIRECT COST (EDC) 127,817.14

TOTAL INDIRECT COST 21,473.28

OVERHEAD / CONT. / MISC. 15,338.06

PROFIT 3,834.51

TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 2,300.71

TOTAL PROJECT COST 149,290.42

11
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

A. EXCAVATION
TOTAL MATERIAL COST 11,573.10
TOTAL LABOR COST 3,471.93
TOTAL DIRECT COST (EDC) 15,045.03
TOTAL INDIRECT COST 2,527.57
OVERHEAD / CONT. / MISC. 1,805.40
PROFIT 451.35
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 270.81
TOTAL PROJECT COST 17,572.60

B. BACKFILL
TOTAL MATERIAL COST 30,003.05
TOTAL LABOR COST 9,000.92
TOTAL DIRECT COST (EDC) 39,003.97
TOTAL INDIRECT COST 6,552.67
OVERHEAD / CONT. / MISC. 4,680.48
PROFIT 1,170.12
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 702.07
TOTAL PROJECT COST 45,556.63

C. EMBANCKMENT
TOTAL MATERIAL COST 11,512.80
TOTAL LABOR COST 3,453.84
TOTAL DIRECT COST (EDC) 14,966.64
TOTAL INDIRECT COST 2,514.40
OVERHEAD / CONT. / MISC. 1,796.00
PROFIT 449.00
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 269.40
TOTAL PROJECT COST 17,481.04

D. GRAVEL BEDDING
TOTAL MATERIAL COST 11,664.00
TOTAL LABOR COST 3,499.20
TOTAL DIRECT COST (EDC) 15,163.20
TOTAL INDIRECT COST 2,547.42
OVERHEAD / CONT. / MISC. 1,819.58
PROFIT 454.90
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 272.94
TOTAL PROJECT COST 17,710.62

12
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

IV. CONCRETE
TOTAL MATERIAL COST 149,632.00
TOTAL LABOR COST 44,889.60
TOTAL DIRECT COST (EDC) 194,521.60
TOTAL INDIRECT COST 32,679.63
OVERHEAD / CONT. / MISC. 23,342.59
PROFIT 5,835.65
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 3,501.39
TOTAL PROJECT COST 227,201.23

V. MASONRY
TOTAL MATERIAL COST 230,891.10
TOTAL LABOR COST 69,267.33
TOTAL DIRECT COST (EDC) 300,158.43
TOTAL INDIRECT COST 50,426.62
OVERHEAD / CONT. / MISC. 36,019.01
PROFIT 9,004.75
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 5,402.85
TOTAL PROJECT COST 350,585.05

VI. SCAFFOLDINGS & STAGINGS


TOTAL MATERIAL COST 6,296.69
TOTAL LABOR COST 1,889.01
TOTAL DIRECT COST (EDC) 8,185.70
TOTAL INDIRECT COST 1,375.20
OVERHEAD / CONT. / MISC. 982.28
PROFIT 245.57
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 147.34
TOTAL PROJECT COST 9,560.89

VII. STEEL AND REINFORCEMENT WORKS


TOTAL MATERIAL COST 87,734.05
TOTAL LABOR COST 26,320.22
TOTAL DIRECT COST (EDC) 114,054.27
TOTAL INDIRECT COST 19,161.12
OVERHEAD / CONT. / MISC. 13,686.51
PROFIT 3,421.63
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 2,052.98
TOTAL PROJECT COST 133,215.38

13
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

VIII. ROOFING WORKS


TOTAL MATERIAL COST 79,861.96
TOTAL LABOR COST 23,958.59
TOTAL DIRECT COST (EDC) 103,820.55
TOTAL INDIRECT COST 17,441.85
OVERHEAD / CONT. / MISC. 12,458.47
PROFIT 3,114.62
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 1,868.77
TOTAL PROJECT COST 121,262.40

IX. CARPENTRY WORKS


TOTAL MATERIAL COST 116,778.81
TOTAL LABOR COST 35,033.64
TOTAL DIRECT COST (EDC) 151,812.45
TOTAL INDIRECT COST 25,504.49
OVERHEAD / CONT. / MISC. 18,217.49
PROFIT 4,554.37
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 2,732.62
TOTAL PROJECT COST 177,316.95

X. PAINTING WORKS
TOTAL MATERIAL COST 16,720.00
TOTAL LABOR COST 5,016.00
TOTAL DIRECT COST (EDC) 21,736.00
TOTAL INDIRECT COST 3,651.65
OVERHEAD / CONT. / MISC. 2,608.32
PROFIT 652.08
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 391.25
TOTAL PROJECT COST 25,387.65

XI. TILE WORKS


TOTAL MATERIAL COST 64,670.38
TOTAL LABOR COST 19,401.11
TOTAL DIRECT COST (EDC) 84,071.49
TOTAL INDIRECT COST 14,124.01
OVERHEAD / CONT. / MISC. 10,088.58
PROFIT 2,522.14
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 1,513.29
TOTAL PROJECT COST 98,195.50

14
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

IV. CONSTRUCTION SCHEDULE

15
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

16
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

17
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V. COMPUTATIONS

V.1. TEMFACIL

TEMPORARY FACILITIES (TEMFACIL) WORKS

COST

1. STORAGE HOUSE 4,500.00

2. ELECTRICITY 5,000.00

3. BUNKHOUSE 15,000.00

Total Cost 24,500.00

V.2. CLEARING AND GRUBBING

CLEARING & GRUBBING

RATE

2 LABORER 600.00/day

600.00 /day
RATE
=
10 sq.m./day
CAPABILITY

Peso = 60.00 /sq. m.

LOT AREA = 72 m2

PAYMENT =
4,320.00

18
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.3. EARTHWORKS

V.3.1. EXCAVATION

EXCAVATIONS
REQUIRED AREA NO. OF TOTAL VOLUME
DIMENSION PCS TO BE EXCAVATED
ALLOWANCE
Length Width Depth Length Width
F1 1.5 1.5 1.2 0.25 1.75 1.75 3 11.025 m3
F2 1.5 1.5 1.2 0.25 1.75 1.75 8 29.4 m3
40.425 m3

EXCAVATIONS
REQUIRED AREA TOTAL VOLUME TO BE
DIMENSION
ALLOWANCE EXCAVATED
Length Width Depth Length Width
WF1 5.6 0.3 1 0.25 5.85 0.55 6.435 m3
WF2 4.8 0.3 1 0.25 5.05 0.55 2.7775 m3
WF3 5.4 0.3 1 0.25 5.65 0.55 3.1075 m3
WF4 2.6 0.3 1 0.25 2.85 0.55 1.5675 m3
WF5 1.2 0.3 1 0.25 1.45 0.55 0.7975 m3
14.685 m3

Total
55.11 m3
Volume

V.3.2. BACKFILL

BACKFILLING
REQUIRED AREA NO. OF TOTAL VOLUME
DIMENSION PCS TO BE BACKFILL
ALLOWANCE
Length Width Depth Length Width
F1 1.5 1.5 1 0.25 1.75 1.75 3 9.1875 m3
F2 1.5 1.5 1 0.25 1.75 1.75 8 24.5 m3
33.6875 m3

BACKFILLING
REQUIRED AREA TOTAL VOLUME TO BE
DIMENSION BACKFILL
ALLOWANCE
Length Width Depth Length Width
WF1 5.6 0.3 0.4 0.25 5.85 0.55 2.574 m3
WF2 4.8 0.3 0.4 0.25 5.05 0.55 2.222 m3
WF3 5.4 0.3 0.4 0.25 5.65 0.55 2.486 m3
WF4 2.6 0.3 0.4 0.25 2.85 0.55 1.254 m3
WF5 1.2 0.3 0.4 0.25 1.45 0.55 0.638 m3
9.174 m3

Total m3
42.8615
Volume

19
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.3.3. EMBANKMENT

Total Volume
TOTAL FLOOR AREA LENGTH
EMBANKMENT
21.6 m3
72 0.3

V.3.4. GRAVEL BEDDING

Gravel Bedding

DIMENSION NO. OF PCS TOTAL VOLUME

Length Width Depth


F1 1.5 1.5 0.4 3 2.7 m3
F2 1.5 1.5 0.4 8 7.2 m3

9.9 m3

Gravel Bedding

DIMENSION TOTAL VOLUME

Length Width Depth

WF1 5.6 0.3 0.3 0.504 m3

WF2 4.8 0.3 0.3 0.432 m3

WF3 5.4 0.3 0.3 0.486 m3

WF4 2.6 0.3 0.3 0.234 m3

WF5 1.2 0.3 0.3 0.108 m3

1.764 m3

Total Volume 11.664 m3

20
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.4. CONCRETE WORKS

V.4.1.FOOTING

FOOTING C1 FORMULA: VOLUME = L * W * T


CLASS A CONCRETE MIX
Enter Length L (M) 1.5 M
Enter Width W (M) 1.5 M
Enter Thickness T (M) 0.3 M
TOTAL VOLUME OF CONCRETE: 0.675 CU.M.
Number of Footing Units 3 Units
TOTAL VOLUME OF CONCRETE: 2.187 CU.M.
# OF CEMENT BAGS 20 BAGS
VOL. OF SAND CU.M. 1.1 CU.M.
VOL. OF GRAVEL CU.M. 2.2 CU.M.

FOOTING C2 FORMULA: VOLUME = L * W * T


CLASS A CONCRETE MIX
Enter Length L (M) 1.5 M
Enter Width W (M) 1.5 M
Enter Thickness T (M) 0.3 M
TOTAL VOLUME OF CONCRETE: 0.675 CU.M.
Number of Footing Units 8 Units
TOTAL VOLUME OF CONCRETE: 5.562 CU.M.
# OF CEMENT BAGS 51 BAGS
VOL. OF SAND CU.M. 2.8 CU.M.
VOL. OF GRAVEL CU.M. 5.6 CU.M.

WALL FOOTING

FORMULA: VOLUME = L * W * T
CLASS A CONCRETE MIX
Enter Length (M) 19.6 M
Enter Width W (M) 0.4 M
Enter Thickness T (M) 0.3 M
TOTAL VOLUME OF CONCRETE: 2.352 CU.M.
# OF CEMENT BAGS 22 BAGS
VOL. OF SAND CU.M. 1.2 CU.M.
VOL. OF GRAVEL CU.M. 2.4 CU.M.

21
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.4.2. FLOOR SLAB

FLOOR SLAB - BY AREA


Ground Floor FORMULA: VOLUME = Floor Area* T
CLASS A CONCRETE MIX
Enter Floor Area A (SQ.M) 51 SQ.M
Enter Thickness T (M) 0.1 M
Enter Concrete Mix Design (CLASS) AA, A,or B A 1:2:4
TOTAL VOLUME OF CONCRETE: 5.1 CU.M.
# OF CEMENT BAGS 46 BAGS
VOL. OF SAND CU.M. 2.6 CU.M.
9 0.5 1 VOL. OF GRAVEL CU.M. 5.1 CU.M.

FLOOR SLAB - BY AREA


2ND FLOOR + Canopy FORMULA: VOLUME = Floor Area* T
CLASS A CONCRETE MIX
Enter Floor Area A (SQ.M) 40.41 SQ.M
Enter Thickness T (M) 0.1 M
Enter Concrete Mix Design (CLASS) AA, A,or B A 1:2:4
TOTAL VOLUME OF CONCRETE: 4.041 CU.M.
# OF CEMENT BAGS 37 BAGS
VOL. OF SAND CU.M. 2.1 CU.M.
9 0.5 1 VOL. OF GRAVEL CU.M. 4.1 CU.M.

V.4.3. COLUMN

CONCRETE COLUMNS COLUMN DIMENSIONS:

Width 1 0.4 M
Width 2 0.2 M

FORMULA: VOLUME = H * W1 * W2
CLASS A CONCRETE MIX
Enter Height L (M) 1.2 M
VOLUME OF CONCRETE FOR EACH COLUME: 0.096 CU.M.
Number of Columns Units 11 Units
TOTAL VOLUME OF CONCRETE: 1.056 CU.M.
# OF CEMENT BAGS 10 BAGS
VOL. OF SAND CU.M. 0.6 CU.M.
VOL. OF GRAVEL CU.M. 1.1 CU.M.

22
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.4.4. BEAM

CONCRETE BEAMS
2ND FLOOR
FORMULA: VOLUME = * W * D
CLASS A CONCRETE MIX
EnterTotal Length (M) 41.452 M
Enter Width W (M) 0.2 M
BEAM DIMENSIONS: Enter Depth D (M) 0.4 M
TOTAL VOLUME OF CONCRETE: 3.31616 CU.M.
# OF CEMENT BAGS 30 BAGS
VOL. OF SAND CU.M. 1.7 CU.M.
VOL. OF GRAVEL CU.M. 3.4 CU.M.

CONCRETE BEAMS
ROOF BEAM
FORMULA: VOLUME = * W * D
CLASS A CONCRETE MIX
EnterTotal Length (M) 34.85 M
Enter Width W (M) 0.2 M
BEAM DIMENSIONS: Enter Depth D (M) 0.4 M
TOTAL VOLUME OF CONCRETE: 2.788 CU.M.
# OF CEMENT BAGS 26 BAGS
VOL. OF SAND CU.M. 1.4 CU.M.
VOL. OF GRAVEL CU.M. 2.8 CU.M.

V.4.5. STAIR

CONCRETE STAIR

Enter Riser Height (M) 0.0875 M


Enter Tread Run (M) 0.3 M
Enter Stair Width W (M) 0.85 M
Enter # of Steps N 16 Steps
Enter Stringer Thickness (M) 0.15 M
0.18 0.64 0.82
TOTAL VOLUME OF CONCRETE: 0.82 CU.M.
# OF CEMENT BAGS 8.00 BAGS
VOL. OF SAND CU.M. 0.50 CU.M.
VOL. OF GRAVEL CU.M. 0.90 CU.M.

23
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.4.6. WATER PROOFING CEMENT

CONCRETE WATER PROFFING - BY AREA

FORMULA: VOLUME = Floor Area* T

CLASS A CONCRETE MIX


A (SQ.M)
Enter Floor Area 93 SQ.M
T (M)
Enter Thickness 0.1 M
TOTAL VOLUME OF CONCRETE:
9.3 CU.M.
# OF CEMENT BAGS BAGS
83.7

V.4.7. FORMS

FORMS

DETERMINING THE TOTAL MATERIALS USED FOR SQUARES & RECTANGULAR COLUMN FORMS

Enter Column Height M 6

Column Dimension A M 0.4

Column Dimension B M 0.2

Enter Number of Columns Units 11

1.40 36.96
Note: One form per column - (Resusable form)

Total # of Bd.ft of frame required: 385.71 Bd.ft

Enter desired lumber dimension : W1 (in) W2 (in) L (ft)

2 2 8

Total Number of Lumber: 145 PCS

Total Number of Plywood required: 13.00 Sheet(s)

Total Number of #2 CWNails: 3.00 KGS

Total Number of #1 Finishing Nails: 1.30 Kgs

24
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

DETERMINING THE TOTAL MATERIALS USED FOR BEAMS & GIRDER FORMS

Enter Beam Length M 45.15


Beam Dimension D M 0.4
Beam Dimension B M 0.2
Enter Number of Beams Units 1
1.10 49.67

Total # of Bd.ft of frame required: 504.00 Bd.ft


W1 (in) W2 (in) L (ft)
2 2 8
Total Number of Lumber: 189 PCS
Total Number of Plywood required: 18.00 Sheet(s)
Total Number of #2 CWNails: 4.00 KGS
Total Number of #1 Finishing Nails: 1.70 Kgs

V.5. MASONRY WORKS

MASONRY WORKS
6” CHB (FRONT)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 6.7 M
Enter Wall Length L (M) 6 M
Enter Area of Window W (SQ.M.) 7.276 SQ.M
Enter Area of Door D (SQ.M) 3.36 SQ.M.
Area of Wall Openings D (SQ.M) 9.876 SQ.M.
Breakage Allowance % 5 %

TOTAL WALL AREA: 19.688 SQ.M.


TOTAL NUMBER OF CHB: 259 PCS

MORTAR USING 6" CHB


# OF CEMENT BAGS 31 BAGS
VOL. OF SCREENED SAND CU.M. 1.7 CU.M.
VOL. OF GRAVEL CU.M. 3.4 CU.M.

PLASTER : 16mm thk Mix: 1:2


Two faces of the wall
# OF CEMENT BAGS 12 BAGS
VOL. OF FINE SAND CU.M. 0.7 CU.M.
VOL. OF GRAVEL CU.M 1.4 CU.M.

25
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

MASONRY WORKS
6” CHB (RIGHT ELEVATION)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 8.6 M
Enter Wall Length L (M) 8.2 M
Enter Area of Window W (SQ.M.) 0 SQ.M
Enter Area of Door D (SQ.M) 0 SQ.M.
Area of Wall Openings D (SQ.M) 0 SQ.M.
Breakage Allowance % 5 %

TOTAL WALL AREA: 70.52 SQ.M.


TOTAL NUMBER OF CHB: 926 PCS

MORTAR USING 6" CHB


# OF CEMENT BAGS 108 BAGS
VOL. OF SCREENED SAND CU.M. 6 CU.M.
VOL. OF GRAVEL CU.M. 12 CU.M.

PLASTER : 16mm thk Mix: 1:2


Two faces of the wall
# OF CEMENT BAGS 41 BAGS
VOL. OF FINE SAND CU.M. 2.3 CU.M.
VOL. OF GRAVEL CU.M 4.6 CU.M.

MASONRY WORKS
6” CHB (LEFT ELEVATION)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 8.6 M
Enter Wall Length L (M) 9.2 M
Enter Area of Window W (SQ.M.) 0 SQ.M
Enter Area of Door D (SQ.M) 0 SQ.M.
Area of Wall Openings D (SQ.M) 0 SQ.M.
Breakage Allowance % 5 %

TOTAL WALL AREA: 79.12 SQ.M.


TOTAL NUMBER OF CHB: 1039 PCS

MORTAR USING 6" CHB


# OF CEMENT BAGS 121 BAGS
VOL. OF SCREENED SAND CU.M. 6.7 CU.M.
VOL. OF GRAVEL CU.M. 13.4 CU.M.

PLASTER : 16mm thk Mix: 1:2


Two faces of the wall
# OF CEMENT BAGS 46 BAGS
VOL. OF FINE SAND CU.M. 2.6 CU.M.
VOL. OF GRAVEL CU.M 5.2 CU.M.

26
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

MASONRY WORKS
6” CHB (BACK)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 6.7 M
Enter Wall Length L (M) 6 M
Enter Area of Window W (SQ.M.) 4.68 SQ.M
Enter Area of Door D (SQ.M) 5.04 SQ.M.
Area of Wall Openings D (SQ.M) 0 SQ.M.
Breakage Allowance % 5 %

TOTAL WALL AREA: 30.48 SQ.M.


TOTAL NUMBER OF CHB: 401 PCS

MORTAR USING 6" CHB


# OF CEMENT BAGS 47 BAGS
VOL. OF SCREENED SAND CU.M. 2.6 CU.M.
VOL. OF GRAVEL CU.M. 5.2 CU.M.

PLASTER : 16mm thk Mix: 1:2


Two faces of the wall
# OF CEMENT BAGS 18 BAGS
VOL. OF FINE SAND CU.M. 1 CU.M.
VOL. OF GRAVEL CU.M 2 CU.M.

MASONRY WORKS
4” CHB (INSIDE - GF)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 3.5 M
Enter Wall Length L (M) 5.75 M

Breakage Allowance % 5 %

TOTAL WALL AREA: 20.125 SQ.M.


TOTAL NUMBER OF CHB: 265 PCS

MORTAR USING 6" CHB


# OF CEMENT BAGS 11 BAGS
VOL. OF SCREENED SAND CU.M. 0.9 CU.M.
VOL. OF GRAVEL CU.M. 1.8 CU.M.

PLASTER : 16mm thk Mix: 1:2


Two faces of the wall
# OF CEMENT BAGS 12 BAGS
VOL. OF FINE SAND CU.M. 0.7 CU.M.
VOL. OF GRAVEL CU.M 1.4 CU.M.

27
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

MASONRY WORKS
4” CHB (INSIDE - 2ND FLOOR)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 3 M
Enter Wall Length L (M) 6.1 M

Breakage Allowance % 5 %

TOTAL WALL AREA: 18.3 SQ.M.


TOTAL NUMBER OF CHB: 241 PCS

MORTAR USING 6" CHB


# OF CEMENT BAGS 10 BAGS
VOL. OF SCREENED SAND CU.M. 0.9 CU.M.
VOL. OF GRAVEL CU.M. 1.8 CU.M.

PLASTER : 16mm thk Mix: 1:2


Two faces of the wall
# OF CEMENT BAGS 11 BAGS
VOL. OF FINE SAND CU.M. 0.6 CU.M.
VOL. OF GRAVEL CU.M 1.2 CU.M.

V.6. SCAFFOLDING AND STAGING

QUANTITY OF LUMBER FOR SCAFFOLDING OR STAGING


LUMBER COLUMN BEAMS FLOORING

Bd. Ft. Per M.


Size Bd. Ft. Per M. Ht. Bd. Ft. Per M. Ht.
Ht.
Vertical Horizontal Brace Vertical Horizontal
2"x2" 4.70 21.00 11.70 4.00 4.70 6.10
2"x3" 7.00 31.67 17.50 6.00 7.00 9.10
2"x4" 9.35 42.25 23.35 8.00 9.35 12.10

W1 (in) W2 (in) L (ft)


Enter desired lumber dimension :
2 2 8

28
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

COLUMN
MEMBER NO. OF TOTAL
MEMBER LOCATION CLEAR VERTICAL HORIZONTAL BRACE
MARK PCS HEIGHT HEIGHT

FTG TO
2ND
C1 6 3.75 22.5 105.75 472.50 263.25
COLUMN
2ND TO RB
SC1 20 2.64 52.8 248.16 1108.80 617.76

353.91 1581.30 881.01

TOTAL = 2816.22 Bd. Ft. (2"x 2")

TOTAL = 8 PCS.

MEMBER LOCATION MEMBER MARK TOTAL LENGTH VERTICAL HORIZONTAL

2ND LEVEL
B1 17.4 69.60 81.78
BEAM
ROOF
RB1 63.2 252.80 297.04

322.40 378.82

TOTAL = 701.22 Bd. Ft. (2"x 2")

TOTAL = 2 PCS.

MEMBER LOCATION MEMBER MARK AREA Bd.ft

SLAB 2ND FLOOR


135.06 823.87

823.87

TOTAL = 823.87 Bd. Ft. (2"x 2”)

TOTAL = 2 PCS

29
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.7. REINFORCEMENT BARS

V.7.1.WALL BARS

Wall Bars (10mm)


Ground to Roof (Left & Right Elevation)
Enter Wall Height H (M) 8.6 M
Enter Wall Length L (M) 17.2 M
Enter wall openings SQ.M 0 SQ.M.
Enter Constant Factor VERTICAL 2.93 40cm
Enter Constant Factor HORIZONTAL 3.3 2 layers
TOTAL WALL AREA: 147.92 SQ.M.
# OF VERTICAL BARS USED: 73 PCS @ 6M
# OF HORIZONTAL BARS USED: 82 PCS @ 6M
#16 TIE WIRE USED: 7 Kgs

Wall bars (10mm)


Ground to 2nd Floor(Back)
Enter Wall Height H (M) 6.7 M
Enter Wall Length L (M) 6 M
Enter wall openings SQ.M 9.72 SQ.M.
Enter Constant Factor VERTICAL 2.93 40cm
Enter Constant Factor HORIZONTAL 3.3 2 layers
TOTAL WALL AREA: 30.48 SQ.M.
# OF VERTICAL BARS USED: 15 PCS @ 6M
# OF HORIZONTAL BARS USED: 17 PCS @ 6M
#16 TIE WIRE USED: 1.5 Kgs

Wall bars (10mm)


Ground to 2nd Floor (Front)
Enter Wall Height H (M) 6.7 M
Enter Wall Length L (M) 6 M
Enter wall openings SQ.M 18.832 SQ.M.
Enter Constant Factor VERTICAL 2.93 40cm
Enter Constant Factor HORIZONTAL 3.3 2 layers
TOTAL WALL AREA: 21.368 SQ.M.
# OF VERTICAL BARS USED: 11 PCS @ 6M
# OF HORIZONTAL BARS USED: 12 PCS @ 6M
#16 TIE WIRE USED: 1.1 Kgs

30
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

Wall bars (10mm)


Ground to 2nd Floor (Inside GF)
Enter Wall Height H (M) 3 M
Enter Wall Length L (M) 7.25 M
Enter wall openings SQ.M 1.5 SQ.M.
Enter Constant Factor VERTICAL 2.93 40cm
Enter Constant Factor HORIZONTAL 3.3 2 layers
TOTAL WALL AREA: 20.25 SQ.M.
# OF VERTICAL BARS USED: 10 PCS @ 6M
# OF HORIZONTAL BARS USED: 12 PCS @ 6M
#16 TIE WIRE USED: 1 Kgs

Wall bars (10mm)


Ground to 2nd Floor (Inside 2nd)
Enter Wall Height H (M) 3 M
Enter Wall Length L (M) 13.28 M
Enter wall openings SQ.M 3.1 SQ.M.
Enter Constant Factor VERTICAL 2.93 40cm
Enter Constant Factor HORIZONTAL 3.3 2 layers
TOTAL WALL AREA: 36.74 SQ.M.
# OF VERTICAL BARS USED: 18 PCS @ 6M
# OF HORIZONTAL BARS USED: 21 PCS @ 6M
#16 TIE WIRE USED: 1.8 Kgs

V.7.2.FOOTING MATTING

FOOTING MATTING(F1) (16mm)


Enter Footing Length L (M) 1.5 M
Enter Footing Width W (M) 1.5 M
Enter # of Bars along X # 6 Pcs
Enter Number of Bars along Y # 8 Pcs
Enter Number of Footing # 3 Units
Enter Clear Cover Cc (M) 0.050 M
Note: Standard Clear Cover for footing =0.05m to 0.075m

Net. Length along L 1.4 M


Net. Length along W 1.4 M
# OF REIN. BARS USED: 8.4 LHS
#16 TIE WIRE USED: 1.1 Kgs

31
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

FOOTING MATTING F2 (16mm)


Enter Footing Length L (M) 1.5 M
Enter Footing Width W (M) 1.5 M
Enter # of Bars along X # 6 Pcs
Enter Number of Bars along Y # 8 Pcs
Enter Number of Footing # 8 Units
Enter Clear Cover Cc (M) 0.050 M
Note: Standard Clear Cover for footing =0.05m to 0.075m

Net. Length along L 1.4 M


Net. Length along W 1.4 M
# OF REIN. BARS USED: 22.4 LHS
#16 TIE WIRE USED: 2.9 Kgs

V.7.3.WALL FOOTING

WALL FOOTING REINFORCEMENT (10mm)


Enter Wall Footing Width W (M) 0.30 M

Enter Wall Footing Total Length (M) 25.4 M

Enter Spacing of Tie Bars for Wall footing (M) 0.30 M

Total # of Ties: 86 PCS


Total # of Horizontal Bars Used: 10 LHS
Overall Total # of Bars used: 15 LHS
#16 TIE WIRE USED: 1.3 Kgs

WALL FOOTING REINFORCEMENT (12mm)

Enter Wall Footing Total Length (M) 25.4 M

Number of continuous bars (PCS) 3 PCS

Overall Total # of Bars used: 12.7 LHS


#16 TIE WIRE USED: 0 Kgs

32
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.7.4.COLUMN

COLUMN REINFORCEMENT PLANTED COLUMN

Enter Column Height H (M) 1.2 M


Enter Number of Columns # 11 Units
Enter Reinforcement Bar Diameter required Ø 12 mm
Enter Column Dimension D1 (M) 0.4 M
Enter Column Dimension D2 (M) 0.2 M

Enter Number of Vertical Bars (M) 6 PCS


Enter Lateral Ties diameter required Ø 10 mm
Enter Lateral Ties Spacing (M) 0.25 M

0.5 0.2
Use End Hook: 0.200 M
Total length of each bars should be more than or equal to: 1.90 M
Total Number of Vertical Bars @ 6M: 33 LHS
3
Cut Length of each stirrups: 1.1 M
Number of Lateral Stirrups per Column: 16 PCS
Total Number of Bars used for stirrups @ 6M : 33 LHS

#16 TIE WIRE USED: 4 Kgs

COLUMN REINFORCEMENT C1

Enter Column Height H (M) 3.7 M


Enter Number of Columns # 8 Units
Enter Reinforcement Bar Diameter required Ø 16 mm
Enter Column Dimension D1 (M) 0.4 M
Enter Column Dimension D2 (M) 0.2 M

Enter Number of Vertical Bars (M) 6 PCS


Enter Lateral Ties diameter required Ø 10 mm
Enter Lateral Ties Spacing (M) 0.25 M

1 0.25
Use End Hook: 0.250 M
Total length of each bars should be more than or equal to: 4.60 M
Total Number of Vertical Bars @ 6M: 48 LHS
6
Cut Length of each stirrups: 1.1 M
Number of Lateral Stirrups per Column: 26 PCS
Total Number of Bars used for stirrups @ 9M : 26 LHS

#16 TIE WIRE USED: 4.8 Kgs

33
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

COLUMN REINFORCEMENT C2
Enter Column Height H (M) 3.7 M
Enter Number of Columns # 3 Units
Enter Reinforcement Bar Diameter required Ø 16 mm
Enter Column Dimension D1 (M) 0.4 M
Enter Column Dimension D2 (M) 0.2 M

Enter Number of Vertical Bars (M) 16 PCS


Enter Lateral Ties diameter required Ø 10 mm
Enter Lateral Ties Spacing (M) 0.25 M

1 0.25
Use End Hook: 0.250 M
Total length of each bars should be more than or equal to: 4.60 M
Total Number of Vertical Bars @ 6M: 48 LHS
6
Cut Length of each stirrups: 1.1 M
Number of Lateral Stirrups per Column: 26 PCS
Total Number of Bars used for stirrups @ 6M : 15 LHS
#16 TIE WIRE USED: 1.8 Kgs

V.7.5.BEAM

BEAM REINFORCEMENT (BEAM TO BEAM = LESS THAN 6.0 METERS) ONE BAY
2nd Floor
Enter Beam to Beam Length L (M) 41.452 M
Enter Beam Width W (M) 0.2 M
Enter Beam Depth D (M) 0.4 M
Enter Column Width Cw(M) 0.2 M
# of Bars # of Non-
Continuo Continuo Size of Bars Units
us us Bars
Top Bars 2 - 16 mm
Web Bars - - - mm
Note: put "0" zero if web bars not applicable
Bottom Bars 2 - 16 mm
Enter Stirrup Bars Diameter required: 10 mm
Enter Stirrup Spacing: 0.1 M
TOP BARS
# of 6m Length Deformed Bars required as Continuous Bars 15 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS
WEB BARS
# of 6m Length Deformed Bars required as Web Bars 0 PCS
BOTTOM BARS
# of 6m Length Deformed Bars required as Continuous Bars 15 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS

Number of 16mm bars used as main bars 30.00 PCS


Number of - mm bars used as web bars - PCS
Number of 10mm bars used as stirrups 39 PCS
#16 TIE WIRE USED: 5 Kgs

34
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

ROOF BEAM REINFORCEMENT (BEAM TO BEAM = LESS THAN 6.0 METERS) ONE BAY
ROOF BEAM
Enter Beam to Beam Length L (M) 34.85 M
Enter Beam Width W (M) 0.2 M
Enter Beam Depth D (M) 0.4 M
Enter Column Width Cw(M) 0.2 M
# of
# of Bars Non-
Continuo Continuo Size of Bars Units
us us Bars
Top Bars 2 - 16 mm
Web Bars - - - mm
Note: put "0" zero if web bars not applicable
Bottom Bars 2 - 16 mm
Enter Stirrup Bars Diameter required: 10 mm
Enter Stirrup Spacing: 0.1 M
TOP BARS
# of 6m Length Deformed Bars required as Continuous Bars 12 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS
WEB BARS
# of 6m Length Deformed Bars required as Web Bars 0 PCS
BOTTOM BARS
# of 6m Length Deformed Bars required as Continuous Bars 12 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS

Number of 16mm bars used as main bars 24.00 PCS


Number of - mm bars used as web bars - PCS
Number of 10mm bars used as stirrups 33 PCS
#16 TIE WIRE USED: 4.2 Kgs

V.7.6.SLAB

Ground Floor
QUANTITY OF REINFORCING STEEL BARS IN A TWO WAY REINFORCED CONCRETE SLAB

NUMBER OF STEEL BARS PER SQUARE


BAR SPACING IN CM. METER
TIES (KGS)

10.000 2.772 0.648


12.500 2.245 0.431
15.000 1.921 0.343
17.500 1.650 0.298
20.000 1.461 0.231
22.200 1.312 0.198
25.000 1.217 0.152

Enter Length (M) 7 M


Enter Width W (M) 6 M
Enter Bar Spacing cm 25 CM
# of Steel Bar Constant factor c 1.217
# of Ties #16 Constant factor c 0.152
# OF STEEL BARS required PCS @ 9M 52 PCS
# OF #16 TIE WIRE required KGS 7 KGS

35
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

2nd Floor

QUANTITY OF REINFORCING STEEL BARS IN A TWO WAY REINFORCED CONCRETE SLAB

NUMBER OF STEEL BARS PER SQUARE


BAR SPACING IN CM. METER
TIES (KGS)

10.000 2.772 0.648


12.500 2.245 0.431
15.000 1.921 0.343
17.500 1.650 0.298
20.000 1.461 0.231
22.200 1.312 0.198
25.000 1.217 0.152

Enter Length (M) 7 M


Enter Width W (M) 6 M
Enter Bar Spacing cm 25 CM

# of Steel Bar Constant factor c 1.217


# of Ties #16 Constant factor c 0.152
# OF STEEL BARS required PCS @ 9M 52 PCS
# OF #16 TIE WIRE required KGS 7 KGS

V.7.7.STAIRS

CONCRETE STAIRS
Enter Riser Height (M) 0.1875 M
Enter Tread Run (M) 0.25 M
Enter Stair Width W (M) 0.85 M
Enter # of Steps N 9 Steps
Enter Stringer Thickness (M) 0.15 M
0.18 0.31 0.49
Enter Spacing (M) Enter Spacing (M)
0.7 0.7
Enter Stringer Lateral Bar diameter (mm) Enter Steps Lateral Bar diameter (mm)
12 10

Enter Spacing (M) Enter Spacing (M)


0.2 0.2
Enter Stringer Horizontal Bar diameter (mm) Enter Steps Lateral Bar diameter (mm)
12 12

Number of 10 mm Lateral Bars required @ Steps PCS @ 6M 3 PCS


Number of 12 mm Horizontal Bars required @ Steps PCS @ 6M 4 PCS
Number of 12 mm Lateral Bars required @ Stringer PCS @ 6M 2 PCS
Number of 12 mm Horizontal Bars required @ Stringer PCS @ 6M 2 PCS
# OF #16 TIE WIRE USED KGS 1 KGS

36
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.8. BAR BENDING SCHEDULE

37
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.9. CUTTING LIST

38
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.10. ROOFING WORKS

RAFTER

TOTAL LT. (m) Commerial Lt.(m) No. of Angle Bars

53.70 6 22 pcs

DEFORMED BARS WEB MEMBERS

TOTAL Lt. OF Lt. per


RAFTER(m) 1m commercial lt. total lt. no. of Bars

53.70 1.94 6 104.18 18.00 12mm Ø bar x 6m

GI GUTTER
effective lt.
Of ready
TOTAL Lt. OF made gutter pcs plain GI GUTTER
GUTTER(m) No. of required pcs

9 2.25 4

PLAIN GI FLASHNG
effective lt.
Of each pcs 2.4(8') plain
TOTAL Lt. OF
accesory GI fascia flashing
GUTTER(m) No. of required pcs
9 2.1 5

PRE PAINTED LONG SPAN ROOFING

Total area ofArea


roofof color bond trimdek hi-ten no. Of pcs pcs of 11m x .76m
of colorbond trimdek hi-ten
47.275 8.36 6

39
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.11. CARPENTRY WORKS

40
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.12. PAINTING WORKS

WATER BASE MASONRY PAINT


KIND OF PAINT USES THINING DRYING TIME COVERAGE/Gal

Exterior & 30 minutes


1/2 lts/ 4 lts
1. Acrylic Latex Paint Interior masonry allow 6 hrs b4 30 to 40 sq.m.
water
surfaces recoat

Exterior & 30 minutes


2. Acrylic Semi-Gloss
Interior masonry Water allow 6 hrs b4 30 to 40 sq.m.
Latex
surfaces recoat

Exterior & 30 minutes


3. Acrylic Gloss Latex Interior masonry Water allow 6 hrs b4 30 to 40 sq.m.
surfaces recoat

For furniture,
cabinets, doors,
1 Hour. Allow 4
4. Latex Hi-Gloss windows, tools,
Usse as is hrs before 30 to 40 sq.m.
Enamel toys, wrought
recoating
iron, & primed
metals

5. Tinting Colors Acrylic colors water

Front Left Elevation

Enter Wall Area 27.324 SQ.M. Enter Wall Area 66.42 SQ.M.

Coverag Coverag
e/Gal e/Gal

Enter Coverage 30 Enter Coverage 30

Coats Coats

Enter # of Coats 2 Enter # of Coats 2

Gals Gals

Number of Gallons 2 Number of Gallons 5

41
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

Right Elevation Back

Enter Wall Area 66.42 SQ.M. Enter Wall Area 37.2 SQ.M.

Coverage Coverage
/Gal /Gal
Enter Coverage 30 Enter Coverage 30

Coats Coats

Enter # of Coats 2 Enter # of Coats 2

Gals Gals

Number of Gallons 5 Number of Gallons 3

PRIMERS
KIND OF PAINT USES THINING DRYING TIME COVERAGE/Gal

2 hrs, allow
1. Interior Primer & For interior
Paint Thinner overnight b4 25 to 30 sq.m.
Sealer wood surfaces
recoating

6 hrs, allow
2. Exterior Wood For exterior
Paint Thinner overnight b4 30 to 40 sq.m.
Primer wood surfaces
recoating

Primer for
ferrous and non-
3. Red Oxide Primer Paint Thinner 3 Hours 35 to 40 sq.m.
ferrous
materials

Rust preventive
4. Red Lead Primer primer for Paint Thinner 3 Hours 30 to 40 sq.m.
ferrous surfaces

For Steel, 6 hrs, allow


5. Epoxy Primer Aluminum, Epoxy Reducer overnight b4 30 to 40 sq.m.
Galvanized iron recoating

Enter Wall Area 197.364 SQ.M.

Coverage/Gal
Enter Coverage 30

Coats
Enter # of Coats 2

Gals

Number of Gallons 14

42
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

V.13. TILING WORKS

31.49 SQ.M.
Enter Ground Floor Area
7 %
Enter Breakage Allowance (5 - 10%)

Tile Size # of PCS

Inches cm per Sq.m.

3x3 7.5 x 7.5 5,991.00

4x4 10 x 10 3,370.00

4 1/4 x 4 1/4 10.6 x 10.6 2,979.00

4x8 10 x 20 1,685.00

6x6 15 x 15 1,498.00

6x8 15 x 20 1,124.00

6 x 12 15 x 30 749.00

8x8 20 x 20 843.00

8 x 12 20 x 30 562.00

8 x 16 20 x 40 422.00

10 x 16 25 x 25 540.00

12 x 12 30 x 30 375.00

12 x 24 30 x 60 188.00

16 x 16 40 x 40 211.00

20 x 20 50 x 50 135.00

24 x 24 60 x 60 94.00

Cement Mortar 3.00 BAGS

White Cement 16.00 KGS

Adhesive 4.00 BAGS

43
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

30.57 SQ.M.
Enter 2nd Floor Area
7 %
Enter Breakage Allowance (5 - 10%)

Tile Size # of PCS

Inches cm per Sq.m.

3x3 7.5 x 7.5 5,816.00

4x4 10 x 10 3,271.00

4 1/4 x 4 1/4 10.6 x 10.6 2,892.00

4x8 10 x 20 1,636.00

6x6 15 x 15 1,454.00

6x8 15 x 20 1,091.00

6 x 12 15 x 30 727.00

8x8 20 x 20 818.00

8 x 12 20 x 30 545.00

8 x 16 20 x 40 409.00

10 x 16 25 x 25 524.00

12 x 12 30 x 30 364.00

12 x 24 30 x 60 182.00

16 x 16 40 x 40 205.00

20 x 20 50 x 50 131.00

24 x 24 60 x 60 91.00

Cement Mortar 3.00 BAGS

White Cement 16.00 KGS

Adhesive 4.00 BAGS

44
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

21.944 SQ.M.
Enter Wall Area for CR
7 %
Enter Breakage Allowance (5 - 10%)

Tile Size # of PCS

Inches cm per Sq.m.

3x3 7.5 x 7.5 4,175.00

4x4 10 x 10 2,349.00

4 1/4 x 4 1/4 10.6 x 10.6 2,076.00

4x8 10 x 20 1,175.00

6x6 15 x 15 1,044.00

6x8 15 x 20 783.00

6 x 12 15 x 30 522.00

8x8 20 x 20 588.00

8 x 12 20 x 30 392.00

8 x 16 20 x 40 294.00

10 x 16 25 x 25 376.00

12 x 12 30 x 30 261.00

12 x 24 30 x 60 131.00

16 x 16 40 x 40 147.00

20 x 20 50 x 50 94.00

24 x 24 60 x 60 66.00

Cement Mortar 2.00 BAGS

White Cement 11.00 KGS

Adhesive 3.00 BAGS

45
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

7.474 SQ.M.
Enter Floor Area for CR (GF-2nd)
7 %
Enter Breakage Allowance (5 - 10%)

Tile Size # of PCS

Inches cm per Sq.m.

3x3 7.5 x 7.5 1,422.00

4x4 10 x 10 800.00

4 1/4 x 4 1/4 10.6 x 10.6 707.00

4x8 10 x 20 400.00

6x6 15 x 15 356.00

6x8 15 x 20 267.00

6 x 12 15 x 30 178.00

8x8 20 x 20 200.00

8 x 12 20 x 30 134.00

8 x 16 20 x 40 100.00

10 x 16 25 x 25 128.00

12 x 12 30 x 30 89.00

12 x 24 30 x 60 45.00

16 x 16 40 x 40 50.00

20 x 20 50 x 50 32.00

24 x 24 60 x 60 23.00

Cement Mortar 1.00 BAGS

White Cement 4.00 KGS

Adhesive 1.00 BAGS

46
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City

15 SQ.M.
Enter Garage Floor Area
7 %
Enter Breakage Allowance (5 - 10%)

Tile Size # of PCS

Inches cm per Sq.m.

3x3 7.5 x 7.5 2,854.00

4x4 10 x 10 1,605.00

4 1/4 x 4 1/4 10.6 x 10.6 1,419.00

4x8 10 x 20 803.00

6x6 15 x 15 714.00

6x8 15 x 20 535.00

6 x 12 15 x 30 357.00

8x8 20 x 20 402.00

8 x 12 20 x 30 268.00

8 x 16 20 x 40 201.00

10 x 16 25 x 25 257.00

12 x 12 30 x 30 179.00

12 x 24 30 x 60 90.00

16 x 16 40 x 40 101.00

20 x 20 50 x 50 65.00

24 x 24 60 x 60 45.00

Cement Mortar 2.00 BAGS

White Cement 8.00 KGS

Adhesive 2.00 BAGS

47