I. GENERAL SPECIFICATIONS
I.3. CONSISTENCY
It is being recognized that an excess of
water seriously reduces the strength of concrete,
the mixture shall be made as dry as possible to
produce of workable concrete.
1
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
I.6. CURING
Use water curing which shall be affected by
keeping the forms at all times sufficiently wet
with clean water to prevent the joints in the
forms of opening. Concrete surface not protected
by forms shall be protected from the loss of
surface moisture by covering with craft paper
quilts or burlaps. Protected material shall be
kept thoroughly wet for the duration of curing
period which shall not less than 7 days.
2
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
3
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
I.9. FOUNDATIONS
All foundations shall be Class "A" (1:2:4)
concrete mixture with the necessary reinforcement
indicated in the plans. All zocalos shall be
0.15m thick concrete hollow blocks and shall be
filled with class “B" (1:3:5) mortar mixture with
the necessary reinforcement as indicated in the
plan.
I.10.FLOORINGS
Unless otherwise noted on the plan, all
flooring shall be 0.10m thick concrete slab on
fill on at 0.50m on center bothways.
I.11.WALLS
All exterior and interior walls shall be of
concrete hollow blocks with the necessary
reinforcement unless otherwise indicated in the
plans.
I.12.CEILING
All ceiling boards shall be of 6mm thick
ordinary plywoodnon 0.05x1.05m ceiling joist
spaced at 0.60m on center bothways.
4
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
I.14.CABINETS
All cabinets shall be of ordinary plywood.
All cabinet doors shall be a 12mm thick plywood
and louver as indicated in the follow-up design.
I.15.ROOFING
Unless otherwise noted on the plan, concrete
roofing shall be 0.15m thick and shall be applied
of water proofing. Temp bars spaced at 0.50m on
center bothways.
I.16.FINISHING HARDWARES
All finishing hardwares shall be of first
quality brand acceptable to the Architect and the
Owner(s).
I.17.PAINTINGS
All concrete walls shall received at least
two coats of approved cement paint. All exposed
lumber shall received at least three coats of
semi gloss paints or varnish as per
specifications of the Architects.
I.18.ELECTRICAL
(See Addt'l Specifications on Plans)
5
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
01.05 01.06
All electrical installations shall conform
with the latest National Electrical Code of the
Philippines and with the approval of local
Electrical Utility Company.
E - 02
All electrical wiring and fixtures shall be
of good quality brand approved by the Architect
and the Owner(s).
I.19.PLUMBING
All plumbing installation shall conform with
National Plumbing Code of the Philippines. All
pipings and fixtures shall be of good quality
brand approved by the Architect and the Owner(s).
6
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
7
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
8
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
H. ROOFING WORKS
1. Rafter Angle Bars
1.1 1 1/2 x 1 1/2 x 4mm pc. 22.00 816.00 17,952.00
2.1 12mm diameter x 6m pc. 18.00 117.22 2,109.96
2. Purlins
2.1 2” x 6” C-Purlins pc. 2.00 1,100.00 2,200.00
3. GI Gutter
3.1 Plain pc. 4.00 900.00 3,600.00
3.2 Fascia flashing pc. 5.00 200.00 1,000.00
4. PRE PAINTED LONG SPAN ROOFING
4.1 11m x 0.76m colorbond trimdek hi-tenpc. 6.00 500.00 3,000.00
5 Others L.S. 1.00 50,000.00 50,000.00
sub total 79,861.96
I. CARPENTRY WORKS
1. Doors
2.1 D1 Solid Core Panel Door pc. 5.00 4,284.00 21,420.00
2.2 D2 Solid Core Panel Type Door pc. 2.00 1,250.00 2,500.00
2.3 D3 Sliding Glass Door pc. 1.00 53,148.72 53,148.72
2.4 Door Knobs
2.4.1 D1 pc. 5.00 595.00 2,975.00
2.4.2 D2 pc. 2.00 235.00 470.00
2. Windows
3.1 Fix with Awning Window set 1.00 6,624.00 6,624.00
3.2 Fix with Awning Window set 1.00 6,624.00 6,624.00
3.3 Fix with Sliding Window set 3.00 3,930.00 11,790.00
3.4 Sliding Window set 1.00 3,500.00 3,500.00
3.5 Sliding Window set 2.00 3,368.00 6,736.00
3 Common Wire Nails (CWN)
3.1 3 1/2” (87.5 mm) kilo 2.76 50.00 138.00
3.2 4" (100 mm) kilo 4.42 49.00 216.58
3.3 4 1/2” (112.5 mm) kilo 5.53 49.00 270.97
3.4 5” (125 mm) kilo 7.46 49.00 365.54
sub total 116,778.81
J. PAINTING WORKS
1. Masonry Paint Gallon 15.00 450.00 6,750.00
2. Concrete Primer Gallon 14.00 500.00 7,000.00
4. 12" Roller Brush pc. 5.00 92.50 462.50
5. Baby Roller Brush pc. 5.00 63.00 315.00
6. 4" Paint Brush pc. 5.00 281.00 1,405.00
7. 3" Paint Brush pc. 5.00 104.75 523.75
8 2" Paint Brush pc. 5.00 52.75 263.75
sub total 16,720.00
K. TILE WORKS
1 16” x 16” pc. 101.00 53.00 5,353.00
2 12” x 12” pc. 739.00 37.00 27,343.00
3 8” x 8” pc. 788.00 29.50 23,246.00
4 Cement Mortar bag 10.00 265.00 2,650.00
5 White Cement bag 12.75 48.50 618.38
6 Adhesive bag 13.00 420.00 5,460.00
sub total 64,670.38
9
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
C. EARTHWORKS 64,752.95
Prepared by:
10
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
PROFIT 955.50
PROFIT 168.48
III. EATRHWORKS
TOTAL MATERIAL COST 98,320.88
PROFIT 3,834.51
11
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
A. EXCAVATION
TOTAL MATERIAL COST 11,573.10
TOTAL LABOR COST 3,471.93
TOTAL DIRECT COST (EDC) 15,045.03
TOTAL INDIRECT COST 2,527.57
OVERHEAD / CONT. / MISC. 1,805.40
PROFIT 451.35
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 270.81
TOTAL PROJECT COST 17,572.60
B. BACKFILL
TOTAL MATERIAL COST 30,003.05
TOTAL LABOR COST 9,000.92
TOTAL DIRECT COST (EDC) 39,003.97
TOTAL INDIRECT COST 6,552.67
OVERHEAD / CONT. / MISC. 4,680.48
PROFIT 1,170.12
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 702.07
TOTAL PROJECT COST 45,556.63
C. EMBANCKMENT
TOTAL MATERIAL COST 11,512.80
TOTAL LABOR COST 3,453.84
TOTAL DIRECT COST (EDC) 14,966.64
TOTAL INDIRECT COST 2,514.40
OVERHEAD / CONT. / MISC. 1,796.00
PROFIT 449.00
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 269.40
TOTAL PROJECT COST 17,481.04
D. GRAVEL BEDDING
TOTAL MATERIAL COST 11,664.00
TOTAL LABOR COST 3,499.20
TOTAL DIRECT COST (EDC) 15,163.20
TOTAL INDIRECT COST 2,547.42
OVERHEAD / CONT. / MISC. 1,819.58
PROFIT 454.90
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 272.94
TOTAL PROJECT COST 17,710.62
12
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
IV. CONCRETE
TOTAL MATERIAL COST 149,632.00
TOTAL LABOR COST 44,889.60
TOTAL DIRECT COST (EDC) 194,521.60
TOTAL INDIRECT COST 32,679.63
OVERHEAD / CONT. / MISC. 23,342.59
PROFIT 5,835.65
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 3,501.39
TOTAL PROJECT COST 227,201.23
V. MASONRY
TOTAL MATERIAL COST 230,891.10
TOTAL LABOR COST 69,267.33
TOTAL DIRECT COST (EDC) 300,158.43
TOTAL INDIRECT COST 50,426.62
OVERHEAD / CONT. / MISC. 36,019.01
PROFIT 9,004.75
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 5,402.85
TOTAL PROJECT COST 350,585.05
13
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
X. PAINTING WORKS
TOTAL MATERIAL COST 16,720.00
TOTAL LABOR COST 5,016.00
TOTAL DIRECT COST (EDC) 21,736.00
TOTAL INDIRECT COST 3,651.65
OVERHEAD / CONT. / MISC. 2,608.32
PROFIT 652.08
TAX (12 % of OCM + PROFIT + LABOR COST + RENTAL COST) 391.25
TOTAL PROJECT COST 25,387.65
14
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
15
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
16
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
17
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V. COMPUTATIONS
V.1. TEMFACIL
COST
2. ELECTRICITY 5,000.00
3. BUNKHOUSE 15,000.00
RATE
2 LABORER 600.00/day
600.00 /day
RATE
=
10 sq.m./day
CAPABILITY
LOT AREA = 72 m2
PAYMENT =
4,320.00
18
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.3. EARTHWORKS
V.3.1. EXCAVATION
EXCAVATIONS
REQUIRED AREA NO. OF TOTAL VOLUME
DIMENSION PCS TO BE EXCAVATED
ALLOWANCE
Length Width Depth Length Width
F1 1.5 1.5 1.2 0.25 1.75 1.75 3 11.025 m3
F2 1.5 1.5 1.2 0.25 1.75 1.75 8 29.4 m3
40.425 m3
EXCAVATIONS
REQUIRED AREA TOTAL VOLUME TO BE
DIMENSION
ALLOWANCE EXCAVATED
Length Width Depth Length Width
WF1 5.6 0.3 1 0.25 5.85 0.55 6.435 m3
WF2 4.8 0.3 1 0.25 5.05 0.55 2.7775 m3
WF3 5.4 0.3 1 0.25 5.65 0.55 3.1075 m3
WF4 2.6 0.3 1 0.25 2.85 0.55 1.5675 m3
WF5 1.2 0.3 1 0.25 1.45 0.55 0.7975 m3
14.685 m3
Total
55.11 m3
Volume
V.3.2. BACKFILL
BACKFILLING
REQUIRED AREA NO. OF TOTAL VOLUME
DIMENSION PCS TO BE BACKFILL
ALLOWANCE
Length Width Depth Length Width
F1 1.5 1.5 1 0.25 1.75 1.75 3 9.1875 m3
F2 1.5 1.5 1 0.25 1.75 1.75 8 24.5 m3
33.6875 m3
BACKFILLING
REQUIRED AREA TOTAL VOLUME TO BE
DIMENSION BACKFILL
ALLOWANCE
Length Width Depth Length Width
WF1 5.6 0.3 0.4 0.25 5.85 0.55 2.574 m3
WF2 4.8 0.3 0.4 0.25 5.05 0.55 2.222 m3
WF3 5.4 0.3 0.4 0.25 5.65 0.55 2.486 m3
WF4 2.6 0.3 0.4 0.25 2.85 0.55 1.254 m3
WF5 1.2 0.3 0.4 0.25 1.45 0.55 0.638 m3
9.174 m3
Total m3
42.8615
Volume
19
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.3.3. EMBANKMENT
Total Volume
TOTAL FLOOR AREA LENGTH
EMBANKMENT
21.6 m3
72 0.3
Gravel Bedding
9.9 m3
Gravel Bedding
1.764 m3
20
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.4.1.FOOTING
WALL FOOTING
FORMULA: VOLUME = L * W * T
CLASS A CONCRETE MIX
Enter Length (M) 19.6 M
Enter Width W (M) 0.4 M
Enter Thickness T (M) 0.3 M
TOTAL VOLUME OF CONCRETE: 2.352 CU.M.
# OF CEMENT BAGS 22 BAGS
VOL. OF SAND CU.M. 1.2 CU.M.
VOL. OF GRAVEL CU.M. 2.4 CU.M.
21
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.4.3. COLUMN
Width 1 0.4 M
Width 2 0.2 M
FORMULA: VOLUME = H * W1 * W2
CLASS A CONCRETE MIX
Enter Height L (M) 1.2 M
VOLUME OF CONCRETE FOR EACH COLUME: 0.096 CU.M.
Number of Columns Units 11 Units
TOTAL VOLUME OF CONCRETE: 1.056 CU.M.
# OF CEMENT BAGS 10 BAGS
VOL. OF SAND CU.M. 0.6 CU.M.
VOL. OF GRAVEL CU.M. 1.1 CU.M.
22
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.4.4. BEAM
CONCRETE BEAMS
2ND FLOOR
FORMULA: VOLUME = * W * D
CLASS A CONCRETE MIX
EnterTotal Length (M) 41.452 M
Enter Width W (M) 0.2 M
BEAM DIMENSIONS: Enter Depth D (M) 0.4 M
TOTAL VOLUME OF CONCRETE: 3.31616 CU.M.
# OF CEMENT BAGS 30 BAGS
VOL. OF SAND CU.M. 1.7 CU.M.
VOL. OF GRAVEL CU.M. 3.4 CU.M.
CONCRETE BEAMS
ROOF BEAM
FORMULA: VOLUME = * W * D
CLASS A CONCRETE MIX
EnterTotal Length (M) 34.85 M
Enter Width W (M) 0.2 M
BEAM DIMENSIONS: Enter Depth D (M) 0.4 M
TOTAL VOLUME OF CONCRETE: 2.788 CU.M.
# OF CEMENT BAGS 26 BAGS
VOL. OF SAND CU.M. 1.4 CU.M.
VOL. OF GRAVEL CU.M. 2.8 CU.M.
V.4.5. STAIR
CONCRETE STAIR
23
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.4.7. FORMS
FORMS
DETERMINING THE TOTAL MATERIALS USED FOR SQUARES & RECTANGULAR COLUMN FORMS
1.40 36.96
Note: One form per column - (Resusable form)
2 2 8
24
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
DETERMINING THE TOTAL MATERIALS USED FOR BEAMS & GIRDER FORMS
MASONRY WORKS
6” CHB (FRONT)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 6.7 M
Enter Wall Length L (M) 6 M
Enter Area of Window W (SQ.M.) 7.276 SQ.M
Enter Area of Door D (SQ.M) 3.36 SQ.M.
Area of Wall Openings D (SQ.M) 9.876 SQ.M.
Breakage Allowance % 5 %
25
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
MASONRY WORKS
6” CHB (RIGHT ELEVATION)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 8.6 M
Enter Wall Length L (M) 8.2 M
Enter Area of Window W (SQ.M.) 0 SQ.M
Enter Area of Door D (SQ.M) 0 SQ.M.
Area of Wall Openings D (SQ.M) 0 SQ.M.
Breakage Allowance % 5 %
MASONRY WORKS
6” CHB (LEFT ELEVATION)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 8.6 M
Enter Wall Length L (M) 9.2 M
Enter Area of Window W (SQ.M.) 0 SQ.M
Enter Area of Door D (SQ.M) 0 SQ.M.
Area of Wall Openings D (SQ.M) 0 SQ.M.
Breakage Allowance % 5 %
26
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
MASONRY WORKS
6” CHB (BACK)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 6.7 M
Enter Wall Length L (M) 6 M
Enter Area of Window W (SQ.M.) 4.68 SQ.M
Enter Area of Door D (SQ.M) 5.04 SQ.M.
Area of Wall Openings D (SQ.M) 0 SQ.M.
Breakage Allowance % 5 %
MASONRY WORKS
4” CHB (INSIDE - GF)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 3.5 M
Enter Wall Length L (M) 5.75 M
Breakage Allowance % 5 %
27
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
MASONRY WORKS
4” CHB (INSIDE - 2ND FLOOR)
A. DETERMINING THE NUMBER OF CONCRETE HOLLOW BLOCKS USED
B. DETERMINING THE NUMBER OF CEMENT & VOLUME OF SAND FOR MORTAR & PLASTERING
Enter Wall Height H (M) 3 M
Enter Wall Length L (M) 6.1 M
Breakage Allowance % 5 %
28
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
COLUMN
MEMBER NO. OF TOTAL
MEMBER LOCATION CLEAR VERTICAL HORIZONTAL BRACE
MARK PCS HEIGHT HEIGHT
FTG TO
2ND
C1 6 3.75 22.5 105.75 472.50 263.25
COLUMN
2ND TO RB
SC1 20 2.64 52.8 248.16 1108.80 617.76
TOTAL = 8 PCS.
2ND LEVEL
B1 17.4 69.60 81.78
BEAM
ROOF
RB1 63.2 252.80 297.04
322.40 378.82
TOTAL = 2 PCS.
823.87
TOTAL = 2 PCS
29
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.7.1.WALL BARS
30
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.7.2.FOOTING MATTING
31
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.7.3.WALL FOOTING
32
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
V.7.4.COLUMN
0.5 0.2
Use End Hook: 0.200 M
Total length of each bars should be more than or equal to: 1.90 M
Total Number of Vertical Bars @ 6M: 33 LHS
3
Cut Length of each stirrups: 1.1 M
Number of Lateral Stirrups per Column: 16 PCS
Total Number of Bars used for stirrups @ 6M : 33 LHS
COLUMN REINFORCEMENT C1
1 0.25
Use End Hook: 0.250 M
Total length of each bars should be more than or equal to: 4.60 M
Total Number of Vertical Bars @ 6M: 48 LHS
6
Cut Length of each stirrups: 1.1 M
Number of Lateral Stirrups per Column: 26 PCS
Total Number of Bars used for stirrups @ 9M : 26 LHS
33
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
COLUMN REINFORCEMENT C2
Enter Column Height H (M) 3.7 M
Enter Number of Columns # 3 Units
Enter Reinforcement Bar Diameter required Ø 16 mm
Enter Column Dimension D1 (M) 0.4 M
Enter Column Dimension D2 (M) 0.2 M
1 0.25
Use End Hook: 0.250 M
Total length of each bars should be more than or equal to: 4.60 M
Total Number of Vertical Bars @ 6M: 48 LHS
6
Cut Length of each stirrups: 1.1 M
Number of Lateral Stirrups per Column: 26 PCS
Total Number of Bars used for stirrups @ 6M : 15 LHS
#16 TIE WIRE USED: 1.8 Kgs
V.7.5.BEAM
BEAM REINFORCEMENT (BEAM TO BEAM = LESS THAN 6.0 METERS) ONE BAY
2nd Floor
Enter Beam to Beam Length L (M) 41.452 M
Enter Beam Width W (M) 0.2 M
Enter Beam Depth D (M) 0.4 M
Enter Column Width Cw(M) 0.2 M
# of Bars # of Non-
Continuo Continuo Size of Bars Units
us us Bars
Top Bars 2 - 16 mm
Web Bars - - - mm
Note: put "0" zero if web bars not applicable
Bottom Bars 2 - 16 mm
Enter Stirrup Bars Diameter required: 10 mm
Enter Stirrup Spacing: 0.1 M
TOP BARS
# of 6m Length Deformed Bars required as Continuous Bars 15 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS
WEB BARS
# of 6m Length Deformed Bars required as Web Bars 0 PCS
BOTTOM BARS
# of 6m Length Deformed Bars required as Continuous Bars 15 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS
34
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
ROOF BEAM REINFORCEMENT (BEAM TO BEAM = LESS THAN 6.0 METERS) ONE BAY
ROOF BEAM
Enter Beam to Beam Length L (M) 34.85 M
Enter Beam Width W (M) 0.2 M
Enter Beam Depth D (M) 0.4 M
Enter Column Width Cw(M) 0.2 M
# of
# of Bars Non-
Continuo Continuo Size of Bars Units
us us Bars
Top Bars 2 - 16 mm
Web Bars - - - mm
Note: put "0" zero if web bars not applicable
Bottom Bars 2 - 16 mm
Enter Stirrup Bars Diameter required: 10 mm
Enter Stirrup Spacing: 0.1 M
TOP BARS
# of 6m Length Deformed Bars required as Continuous Bars 12 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS
WEB BARS
# of 6m Length Deformed Bars required as Web Bars 0 PCS
BOTTOM BARS
# of 6m Length Deformed Bars required as Continuous Bars 12 PCS
# of 6m Length Deformed Bars required as Non-Continuous Bars 0 PCS
V.7.6.SLAB
Ground Floor
QUANTITY OF REINFORCING STEEL BARS IN A TWO WAY REINFORCED CONCRETE SLAB
35
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
2nd Floor
V.7.7.STAIRS
CONCRETE STAIRS
Enter Riser Height (M) 0.1875 M
Enter Tread Run (M) 0.25 M
Enter Stair Width W (M) 0.85 M
Enter # of Steps N 9 Steps
Enter Stringer Thickness (M) 0.15 M
0.18 0.31 0.49
Enter Spacing (M) Enter Spacing (M)
0.7 0.7
Enter Stringer Lateral Bar diameter (mm) Enter Steps Lateral Bar diameter (mm)
12 10
36
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
37
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
38
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
RAFTER
53.70 6 22 pcs
GI GUTTER
effective lt.
Of ready
TOTAL Lt. OF made gutter pcs plain GI GUTTER
GUTTER(m) No. of required pcs
9 2.25 4
PLAIN GI FLASHNG
effective lt.
Of each pcs 2.4(8') plain
TOTAL Lt. OF
accesory GI fascia flashing
GUTTER(m) No. of required pcs
9 2.1 5
39
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
40
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
For furniture,
cabinets, doors,
1 Hour. Allow 4
4. Latex Hi-Gloss windows, tools,
Usse as is hrs before 30 to 40 sq.m.
Enamel toys, wrought
recoating
iron, & primed
metals
Enter Wall Area 27.324 SQ.M. Enter Wall Area 66.42 SQ.M.
Coverag Coverag
e/Gal e/Gal
Coats Coats
Gals Gals
41
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
Enter Wall Area 66.42 SQ.M. Enter Wall Area 37.2 SQ.M.
Coverage Coverage
/Gal /Gal
Enter Coverage 30 Enter Coverage 30
Coats Coats
Gals Gals
PRIMERS
KIND OF PAINT USES THINING DRYING TIME COVERAGE/Gal
2 hrs, allow
1. Interior Primer & For interior
Paint Thinner overnight b4 25 to 30 sq.m.
Sealer wood surfaces
recoating
6 hrs, allow
2. Exterior Wood For exterior
Paint Thinner overnight b4 30 to 40 sq.m.
Primer wood surfaces
recoating
Primer for
ferrous and non-
3. Red Oxide Primer Paint Thinner 3 Hours 35 to 40 sq.m.
ferrous
materials
Rust preventive
4. Red Lead Primer primer for Paint Thinner 3 Hours 30 to 40 sq.m.
ferrous surfaces
Coverage/Gal
Enter Coverage 30
Coats
Enter # of Coats 2
Gals
Number of Gallons 14
42
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
31.49 SQ.M.
Enter Ground Floor Area
7 %
Enter Breakage Allowance (5 - 10%)
4x4 10 x 10 3,370.00
4x8 10 x 20 1,685.00
6x6 15 x 15 1,498.00
6x8 15 x 20 1,124.00
6 x 12 15 x 30 749.00
8x8 20 x 20 843.00
8 x 12 20 x 30 562.00
8 x 16 20 x 40 422.00
10 x 16 25 x 25 540.00
12 x 12 30 x 30 375.00
12 x 24 30 x 60 188.00
16 x 16 40 x 40 211.00
20 x 20 50 x 50 135.00
24 x 24 60 x 60 94.00
43
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
30.57 SQ.M.
Enter 2nd Floor Area
7 %
Enter Breakage Allowance (5 - 10%)
4x4 10 x 10 3,271.00
4x8 10 x 20 1,636.00
6x6 15 x 15 1,454.00
6x8 15 x 20 1,091.00
6 x 12 15 x 30 727.00
8x8 20 x 20 818.00
8 x 12 20 x 30 545.00
8 x 16 20 x 40 409.00
10 x 16 25 x 25 524.00
12 x 12 30 x 30 364.00
12 x 24 30 x 60 182.00
16 x 16 40 x 40 205.00
20 x 20 50 x 50 131.00
24 x 24 60 x 60 91.00
44
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
21.944 SQ.M.
Enter Wall Area for CR
7 %
Enter Breakage Allowance (5 - 10%)
4x4 10 x 10 2,349.00
4x8 10 x 20 1,175.00
6x6 15 x 15 1,044.00
6x8 15 x 20 783.00
6 x 12 15 x 30 522.00
8x8 20 x 20 588.00
8 x 12 20 x 30 392.00
8 x 16 20 x 40 294.00
10 x 16 25 x 25 376.00
12 x 12 30 x 30 261.00
12 x 24 30 x 60 131.00
16 x 16 40 x 40 147.00
20 x 20 50 x 50 94.00
24 x 24 60 x 60 66.00
45
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
7.474 SQ.M.
Enter Floor Area for CR (GF-2nd)
7 %
Enter Breakage Allowance (5 - 10%)
4x4 10 x 10 800.00
4x8 10 x 20 400.00
6x6 15 x 15 356.00
6x8 15 x 20 267.00
6 x 12 15 x 30 178.00
8x8 20 x 20 200.00
8 x 12 20 x 30 134.00
8 x 16 20 x 40 100.00
10 x 16 25 x 25 128.00
12 x 12 30 x 30 89.00
12 x 24 30 x 60 45.00
16 x 16 40 x 40 50.00
20 x 20 50 x 50 32.00
24 x 24 60 x 60 23.00
46
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
15 SQ.M.
Enter Garage Floor Area
7 %
Enter Breakage Allowance (5 - 10%)
4x4 10 x 10 1,605.00
4x8 10 x 20 803.00
6x6 15 x 15 714.00
6x8 15 x 20 535.00
6 x 12 15 x 30 357.00
8x8 20 x 20 402.00
8 x 12 20 x 30 268.00
8 x 16 20 x 40 201.00
10 x 16 25 x 25 257.00
12 x 12 30 x 30 179.00
12 x 24 30 x 60 90.00
16 x 16 40 x 40 101.00
20 x 20 50 x 50 65.00
24 x 24 60 x 60 45.00
47
University of San Agustin
COLLEGE OF TECHNOLOGY
Gen. Luna Street, Iloilo City
VI. PLAN
48