Project Name:-Construction of Major bridges, Limited Height Subways in connection with Doubling of track between Rajpura - Bhatinda from

Km 0.00 to Km 172.64
in Ambala Division of Northern Railway, Punjab, india
Dist. in Height in b/w Proposed R.L & Prop. Face Distance
Details of Abutment Details of Pier Proposed
Schedule b/w Exst. Pilecap PCC Bottom in b/w Exst. &
Sl. MJB Span Total Abutment Face
Chainage and Prop. Proposed Pile Prop. Remarks
No No (Mtr) No. of No. of piles Proposed distance from Ext.
(Km) Dimension Dimension C/L Cap PCC Diff. Abutment
Piles Piles R.L Track C/L
(In Mtr.) Bottom RL (In Mtr.)

1 17-A 8+200 45.7 X 1 24 (L)10.4*(W)9.125 - - 24 7.500 265.106 260.813 4.293 0.365


4.385 (A2) & 4.385 Retaining Wall in
2 26 14+9-10 9.15 X 3 12 (L)7.4*(W)7.340 8 (L) 4.4*(W) 4.4 20 7.500 259.931 253.661 6.270 0.400 (A1) Existing Abutment
4.125 (A2) & Retaining Wall in
3 35 21+230 12.2 X 5 12 (L)8.8*(W)7.60 20 (L)7.6*(W)5.64 32 7.500 254.309 246.022 8.287 0.975 4.125 (A1) Existing Abutment
4.125 (A2) & Retaining Wall in
4 36 21+390 12.2 X 4 16 (L)12.4*(W)7.6 15 (L)7.6*(W)5.64 31 7.500 254.309 245.312 8.997 0.810 4.125 (A1) Existing Abutment
3.350 (A2) &
5 40 23+450 12.2 X 3 12 (L)7.4*(W)6.975 12 (L)7.4*(W)5.64 24 6.100 253.177 247.867 5.310 0.283 3.350 (A1)
3.795 (A2) &
6 60-A 30+653 9.15 X 3 12 (L)7.4*(W)7.930 8 (L)4.4*(W)4.4 20 7.500 253.985 246.586 7.399 0.445 3.795 (A1)
3.375 (A2) &
7 62-A 31+170 61 X 1 24 (L)10.4*(W)9.125 - - 24 7.500 255.016 250.141 4.875 0.617 3.375 (A1)
3.576 (A2) &
8 70 34+980 12.2 X 4 12 (L)7.4*(W)8.15 18 (L)7.4*(W)5.64 30 7.500 251.551 245.959 5.592 0.325 3.576 (A1)
3.795 (A2) & Retaining Wall in
9 100 48+185 9.15 X 3 12 (L)7.4*(W)7.930 8 (L)4.4*(W)4.4 20 7.500 250.949 244.77 6.179 0.400 3.795 (A1) Existing Abutment
10 102 48+935 45.7 X 1 24 (L)10.4*(W)9.125 - - 24 7.500 252.569 248.276 4.293 0.595
3.875 (A2) &
11 114 54+535 6.1 X 4 12 (L)7.4*(W)7.85 12 (L)4.4*(W)4.4 24 7.500 249.727 242.847 6.880 0.825 3.875 (A1)
3.575 (A2) &
12 129 63+077 12.2 X 14 12 (L)7.4*(W)8.15 78 (L)7.4*(W)5.64 90 7.500 244.948 239.127 5.821 0.250 3.578 (A1)
3.875 (A2) &
13 140 70+075 6.1 X 4 12 (L)7.4*(W)7.85 12 (L)4.4*(W)4.4 24 7.500 244.700 238.777 5.923 0.795 3.875 (A1)
3.875 (A2) &
14 166 83+523 6.1 X 4 12 (L)7.4*(W)7.85 12 (L)4.4*(W)4.4 24 7.500 240.525 234.555 5.970 0.825 3.875 (A1)

15 172 85+397 61 X 1 24 (L)10.4*(W)9.125 - - 24 7.500 241.673 236.958 4.715 0.480


4.700 (A2) &
16 197 103+027 6.1 X 12 12 (L)7.4*(W)7.025 44 (L)4.4*(W)4.4 56 7.500 232.32 227.094 5.226 0.335 4.700 (A1)
4.700 (A2) &
17 198 104+119 6.1 X 3 12 (L)7.4*(W)7.025 8 (L)4.4*(W)4.4 20 7.500 232.093 227.249 4.844 0.325 4.700 (A1)
3.576 (A2) & Retaining Wall in
18 206 112+753 12.2 X 2 12 (L)7.4*(W)8.15 6 (L)7.4*(W)5.64 18 7.500 230.502 224.389 6.113 0.525 3.576 (A1) Existing Abutment
3.5765(A2) &
19 216 120+023 12.2 X 3 12 (L)7.4*(W)8.15 12 (L)7.4*(W)5.64 24 7.500 225.75 221.203 4.547 0.885 3.575 (A1)
4.700 (A2) &
20 218 121+089 6.1 X 6 12 (L)7.4*(W)7.025 20 (L)4.4*(W)4.4 32 7.500 224.4 219.392 5.008 0.540 4.700 (A1)
3.795 (A2) &
21 221 123+076 9.15 X 2 12 (L)7.4*(W)7.930 4 (L)4.4*(W)4.4 16 7.500 223.124 217.893 5.231 0.720 3.795 (A1)
3.575 (A2) &
22 231 130+390 12.2 X 3 12 (L)7.4*(W)8.150 12 (L)7.4*(W)5.640 24 7.500 221.566 215.381 6.185 0.505 3.578 (A1)

23 292 167+200 30.5 X 1 18 (L)7.4*(W)9.125 - - 18 7.500 210.529 206.318 4.211 0.100


Total Number of Pile:- 334 309 643