Professional Documents
Culture Documents
On January 21, 1988 defendant SAUDIA hired plaintiff as a Shortly afterwards, defendant SAUDIA summoned plaintiff to
Flight Attendant for its airlines based in Jeddah, Saudi Arabia. report to Jeddah once again and see Miniewy on June 27, 1993
... for further investigation. Plaintiff did so after receiving
assurance from SAUDIA's Manila manager, Aslam Saleemi,
On April 27, 1990, while on a lay-over in Jakarta, Indonesia, that the investigation was routinary and that it posed no danger
plaintiff went to a disco dance with fellow crew members to her.
Thamer Al-Gazzawi and Allah Al-Gazzawi, both Saudi
nationals. Because it was almost morning when they returned In Jeddah, a SAUDIA legal officer brought plaintiff to the
to their hotels, they agreed to have breakfast together at the same Saudi court on June 27, 1993. Nothing happened then
room of Thamer. When they were in te (sic) room, Allah left but on June 28, 1993, a Saudi judge interrogated plaintiff
on some pretext. Shortly after he did, Thamer attempted to through an interpreter about the Jakarta incident. After one
rape plaintiff. Fortunately, a roomboy and several security hour of interrogation, they let her go. At the airport, however,
personnel heard her cries for help and rescued her. Later, the just as her plane was about to take off, a SAUDIA officer told
Indonesian police came and arrested Thamer and Allah Al- her that the airline had forbidden her to take flight. At the
Gazzawi, the latter as an accomplice. Inflight Service Office where she was told to go, the secretary
of Mr. Yahya Saddick took away her passport and told her to
When plaintiff returned to Jeddah a few days later, several remain in Jeddah, at the crew quarters, until further orders.
SAUDIA officials interrogated her about the Jakarta incident.
They then requested her to go back to Jakarta to help arrange On July 3, 1993 a SAUDIA legal officer again escorted
the release of Thamer and Allah. In Jakarta, SAUDIA Legal plaintiff to the same court where the judge, to her
Officer Sirah Akkad and base manager Baharini negotiated astonishment and shock, rendered a decision, translated to her
with the police for the immediate release of the detained crew in English, sentencing her to five months imprisonment and to
members but did not succeed because plaintiff refused to 286 lashes. Only then did she realize that the Saudi court had
cooperate. She was afraid that she might be tricked into tried her, together with Thamer and Allah, for what happened
something she did not want because of her inability to in Jakarta. The court found plaintiff guilty of (1) adultery; (2)
understand the local dialect. She also declined to sign a blank going to a disco, dancing and listening to the music in
paper and a document written in the local dialect. Eventually, violation of Islamic laws; and (3) socializing with the male
SAUDIA allowed plaintiff to return to Jeddah but barred her crew, in contravention of Islamic tradition. 10
from the Jakarta flights.
Facing conviction, private respondent sought the help of her
Plaintiff learned that, through the intercession of the Saudi employer, petitioner SAUDIA. Unfortunately, she was denied
Arabian government, the Indonesian authorities agreed to any assistance. She then asked the Philippine Embassy in
deport Thamer and Allah after two weeks of detention. Jeddah to help her while her case is on appeal. Meanwhile, to
Eventually, they were again put in service by defendant pay for her upkeep, she worked on the domestic flight of
SAUDI (sic). In September 1990, defendant SAUDIA SAUDIA, while Thamer and Allah continued to serve in the
transferred plaintiff to Manila. international
flights. 11
Because she was wrongfully convicted, the Prince of Makkah Amended Complaint, which is one for the recovery of actual,
dismissed the case against her and allowed her to leave Saudi moral and exemplary damages plus attorney's fees, upon the
Arabia. Shortly before her return to Manila, 12 she was basis of the applicable Philippine law, Article 21 of the New
terminated from the service by SAUDIA, without her being Civil Code of the Philippines, is, clearly, within the
informed of the cause. jurisdiction of this Court as regards the subject matter, and
there being nothing new of substance which might cause the
On November 23, 1993, Morada filed a Complaint 13 for reversal or modification of the order sought to be
damages against SAUDIA, and Khaled Al-Balawi ("Al- reconsidered, the motion for reconsideration of the defendant,
Balawi"), its country manager. is DENIED.
On June 23, 1994, Morada filed an Amended In another Resolution 28 promulgated on September 27, 1995,
Complaint 17 wherein Al-Balawi was dropped as party now assailed, the appellate court denied SAUDIA's Petition
defendant. On August 11, 1994, Saudia filed its Manifestation for the Issuance of a Writ of Preliminary Injunction dated
and Motion to Dismiss Amended Complaint 18. February 18, 1995, to wit:
The trial court issued an Order 19 dated August 29, 1994 The Petition for the Issuance of a Writ of Preliminary
denying the Motion to Dismiss Amended Complaint filed by Injunction is hereby DENIED, after considering the Answer,
Saudia. with Prayer to Deny Writ of Preliminary Injunction (Rollo, p.
135) the Reply and Rejoinder, it appearing that herein
From the Order of respondent Judge 20 denying the Motion to petitioner is not clearly entitled thereto (Unciano Paramedical
Dismiss, SAUDIA filed on September 20, 1994, its Motion for College, et. Al., v. Court of Appeals, et. Al., 100335, April 7,
Reconsideration 21 of the Order dated August 29, 1994. It 1993, Second Division).
alleged that the trial court has no jurisdiction to hear and try
the case on the basis of Article 21 of the Civil Code, since the SO ORDERED.
proper law applicable is the law of the Kingdom of Saudi
Arabia. On October 14, 1994, Morada filed her On October 20, 1995, SAUDIA filed with this Honorable
Opposition 22 (To Defendant's Motion for Reconsideration). Court the instant Petition 29 for Review with Prayer for
Temporary Restraining Order dated October 13, 1995.
In the Reply 23 filed with the trial court on October 24, 1994,
SAUDIA alleged that since its Motion for Reconsideration However, during the pendency of the instant Petition,
raised lack of jurisdiction as its cause of action, the Omnibus respondent Court of Appeals rendered the Decision 30 dated
Motion Rule does not apply, even if that ground is raised for April 10, 1996, now also assailed. It ruled that the Philippines
the first time on appeal. Additionally, SAUDIA alleged that is an appropriate forum considering that the Amended
the Philippines does not have any substantial interest in the Complaint's basis for recovery of damages is Article 21 of the
prosecution of the instant case, and hence, without jurisdiction Civil Code, and thus, clearly within the jurisdiction of
to adjudicate the same. respondent Court. It further held that certiorari is not the
proper remedy in a denial of a Motion to Dismiss, inasmuch as
Respondent Judge subsequently issued another Order 24 dated the petitioner should have proceeded to trial, and in case of an
February 2, 1995, denying SAUDIA's Motion for adverse ruling, find recourse in an appeal.
Reconsideration. The pertinent portion of the assailed Order
reads as follows: On May 7, 1996, SAUDIA filed its Supplemental Petition for
Review with Prayer for Temporary Restraining Order 31 dated
Acting on the Motion for Reconsideration of defendant Saudi April 30, 1996, given due course by this Court. After both
Arabian Airlines filed, thru counsel, on September 20, 1994, parties submitted their Memoranda, 32 the instant case is now
and the Opposition thereto of the plaintiff filed, thru counsel, deemed submitted for decision.
on October 14, 1994, as well as the Reply therewith of
defendant Saudi Arabian Airlines filed, thru counsel, on Petitioner SAUDIA raised the following issues:
October 24, 1994, considering that a perusal of the plaintiffs
I On the other hand, private respondent contends that since her
Amended Complaint is based on Articles 19 35 and 21 36 of the
The trial court has no jurisdiction to hear and try Civil Case Civil Code, then the instant case is properly a matter of
No. Q-93-18394 based on Article 21 of the New Civil Code domestic law. 37
since the proper law applicable is the law of the Kingdom of
Saudi Arabia inasmuch as this case involves what is known in Under the factual antecedents obtaining in this case, there is
private international law as a "conflicts problem". Otherwise, no dispute that the interplay of events occurred in two states,
the Republic of the Philippines will sit in judgment of the acts the Philippines and Saudi Arabia.
done by another sovereign state which is abhorred.
As stated by private respondent in her Amended
II Complaint 38 dated June 23, 1994:
Leave of court before filing a supplemental pleading is not a 2. Defendant SAUDI ARABIAN AIRLINES or SAUDIA is a
jurisdictional requirement. Besides, the matter as to absence of foreign airlines corporation doing business in the Philippines.
leave of court is now moot and academic when this Honorable It may be served with summons and other court processes at
Court required the respondents to comment on petitioner's Travel Wide Associated Sales (Phils.). Inc., 3rd Floor, Cougar
April 30, 1996 Supplemental Petition For Review With Prayer Building, 114 Valero St., Salcedo Village, Makati, Metro
For A Temporary Restraining Order Within Ten (10) Days Manila.
From Notice Thereof. Further, the Revised Rules of Court
should be construed with liberality pursuant to Section 2, Rule xxx xxx xxx
1 thereof.
6. Plaintiff learned that, through the intercession of the Saudi
III Arabian government, the Indonesian authorities agreed to
deport Thamer and Allah after two weeks of detention.
Petitioner received on April 22, 1996 the April 10, 1996 Eventually, they were again put in service by defendant
decision in CA-G.R. SP NO. 36533 entitled "Saudi Arabian SAUDIA. In September 1990, defendant SAUDIA transferred
Airlines v. Hon. Rodolfo A. Ortiz, et al." and filed its April plaintiff to Manila.
30, 1996 Supplemental Petition For Review With Prayer For
A Temporary Restraining Order on May 7, 1996 at 10:29 a.m. 7. On January 14, 1992, just when plaintiff thought that the
or within the 15-day reglementary period as provided for Jakarta incident was already behind her, her superiors
under Section 1, Rule 45 of the Revised Rules of Court. reauested her to see MR. Ali Meniewy, Chief Legal Officer of
Therefore, the decision in CA-G.R. SP NO. 36533 has not yet SAUDIA in Jeddah, Saudi Arabia. When she saw him, he
become final and executory and this Honorable Court can take brought her to the police station where the police took her
cognizance of this case. 33 passport and questioned her about the Jakarta incident.
Miniewy simply stood by as the police put pressure on her to
From the foregoing factual and procedural antecedents, the make a statement dropping the case against Thamer and Allah.
following issues emerge for our resolution: Not until she agreed to do so did the police return her passport
and allowed her to catch the afternoon flight out of Jeddah.
I.
8. One year and a half later or on June 16, 1993, in Riyadh,
WHETHER RESPONDENT APPELLATE COURT ERRED Saudi Arabia, a few minutes before the departure of her flight
IN HOLDING THAT THE REGIONAL TRIAL COURT OF to Manila, plaintiff was not allowed to board the plane and
QUEZON CITY HAS JURISDICTION TO HEAR AND TRY instead ordered to take a later flight to Jeddah to see Mr.
CIVIL CASE NO. Q-93-18394 ENTITLED "MILAGROS P. Meniewy, the Chief Legal Officer of SAUDIA. When she did,
MORADA V. SAUDI ARABIAN AIRLINES". a certain Khalid of the SAUDIA office brought her to a Saudi
court where she was asked to sigh a document written in
II. Arabic. They told her that this was necessary to close the case
against Thamer and Allah. As it turned out, plaintiff signed a
notice to her to appear before the court on June 27,
WHETHER RESPONDENT APPELLATE COURT ERRED 1993. Plaintiff then returned to Manila.
IN RULING THAT IN THIS CASE PHILIPPINE LAW
SHOULD GOVERN.
9. Shortly afterwards, defendant SAUDIA summoned plaintiff
to report to Jeddah once again and see Miniewy on June 27,
Petitioner SAUDIA claims that before us is a conflict of laws 1993 for further investigation. Plaintiff did so after receiving
that must be settled at the outset. It maintains that private assurance from SAUDIA's Manila manger, Aslam Saleemi,
respondent's claim for alleged abuse of rights occurred in the that the investigation was routinary and that it posed no
Kingdom of Saudi Arabia. It alleges that the existence of a danger to her.
foreign element qualifies the instant case for the application of
the law of the Kingdom of Saudi Arabia, by virtue of the lex
loci delicti commissi rule. 34 10. In Jeddah, a SAUDIA legal officer brought plaintiff to the
same Saudi court on June 27, 1993. Nothing happened then
but on June 28, 1993, a Saudi judge interrogated plaintiff After a careful study of the private respondent's Amended
through an interpreter about the Jakarta incident. After one Complaint, 44 and the Comment thereon, we note that she aptly
hour of interrogation, they let her go. At the airport, however, predicated her cause of action on Articles 19 and 21 of the
just as her plane was about to take off, a SAUDIA officer told New Civil Code.
her that the airline had forbidden her to take that flight. At the
Inflight Service Office where she was told to go, the secretary On one hand, Article 19 of the New Civil Code provides:
of Mr. Yahya Saddick took away her passport and told her to
remain in Jeddah, at the crew quarters, until further orders. Art. 19. Every person must, in the exercise of his rights and in
the performance of his duties, act with justice give everyone
11. On July 3, 1993 a SAUDIA legal officer again escorted his due and observe honesty and good faith.
plaintiff to the same court where the judge, to her
astonishment and shock, rendered a decision, translated to her On the other hand, Article 21 of the New Civil Code provides:
in English, sentencing her to five months imprisonment and to
286 lashes. Only then did she realize that the Saudi court had
tried her, together with Thamer and Allah, for what happened Art. 21. Any person who willfully causes loss or injury to
in Jakarta. The court found plaintiff guilty of (1) adultery; (2) another in a manner that is contrary to morals, good customs
going to a disco, dancing, and listening to the music in or public policy shall compensate the latter for damages.
violation of Islamic laws; (3) socializing with the male crew,
in contravention of Islamic tradition. Thus, in Philippine National Bank (PNB) vs. Court of
Appeals, 45 this Court held that:
12. Because SAUDIA refused to lend her a hand in the case,
plaintiff sought the help of the Philippines Embassy in Jeddah. The aforecited provisions on human relations were intended to
The latter helped her pursue an appeal from the decision of the expand the concept of torts in this jurisdiction by granting
court. To pay for her upkeep, she worked on the domestic adequate legal remedy for the untold number of moral wrongs
flights of defendant SAUDIA while, ironically, Thamer and which is impossible for human foresight to specifically
Allah freely served the international flights. 39 provide in the statutes.
Where the factual antecedents satisfactorily establish the Although Article 19 merely declares a principle of law, Article
existence of a foreign element, we agree with petitioner that 21 gives flesh to its provisions. Thus, we agree with private
the problem herein could present a "conflicts" case. respondent's assertion that violations of Articles 19 and 21 are
actionable, with judicially enforceable remedies in the
A factual situation that cuts across territorial lines and is municipal forum.
affected by the diverse laws of two or more states is said to
contain a "foreign element". The presence of a foreign element Based on the allegations 46 in the Amended Complaint, read in
is inevitable since social and economic affairs of individuals the light of the Rules of Court on jurisdiction 47 we find that
and associations are rarely confined to the geographic limits of the Regional Trial Court (RTC) of Quezon City possesses
their birth or conception. 40 jurisdiction over the subject matter of the suit. 48 Its authority
to try and hear the case is provided for under Section 1 of
The forms in which this foreign element may appear are Republic Act No. 7691, to wit:
many. 41 The foreign element may simply consist in the fact
that one of the parties to a contract is an alien or has a foreign Sec. 1. Section 19 of Batas Pambansa Blg. 129, otherwise
domicile, or that a contract between nationals of one State known as the "Judiciary Reorganization Act of 1980", is
involves properties situated in another State. In other cases, hereby amended to read as follows:
the foreign element may assume a complex form. 42
Sec. 19. Jurisdiction in Civil Cases. - Regional Trial Courts
In the instant case, the foreign element consisted in the fact shall exercise exclusive jurisdiction:
that private respondent Morada is a resident Philippine
national, and that petitioner SAUDIA is a resident foreign xxx xxx xxx
corporation. Also, by virtue of the employment of Morada
with the petitioner Saudia as a flight stewardess, events did (8) In all other cases in which demand, exclusive of interest,
transpire during her many occasions of travel across national damages of whatever kind, attorney's fees, litigation expenses,
borders, particularly from Manila, Philippines to Jeddah, and cots or the value of the property in controversy exceeds
Saudi Arabia, and vice versa, that caused a "conflicts" One hundred thousand pesos (P100,000.00) or, in such other
situation to arise. cases in Metro Manila, where the demand, exclusive of the
above-mentioned items exceeds Two hundred Thousand pesos
We thus find private respondent's assertion that the case is (P200,000.00). (Emphasis ours)
purely domestic, imprecise. A conflicts problem presents itself
here, and the question of jurisdiction 43 confronts the court a xxx xxx xxx
quo.
And following Section 2 (b), Rule 4 of the Revised Rules of interposing such second ground in its motion to dismiss, Ker
Court - the venue, Quezon City, is appropriate: and Co., Ltd. availed of an affirmative defense on the basis of
which it prayed the court to resolve controversy in its favor.
Sec. 2 Venue in Courts of First Instance. - [Now Regional For the court to validly decide the said plea of defendant Ker
Trial Court] & Co., Ltd., it necessarily had to acquire jurisdiction upon the
latter's person, who, being the proponent of the affirmative
(a) xxx xxx xxx defense, should be deemed to have abandoned its special
appearance and voluntarily submitted itself to the jurisdiction
of the court.
(b) Personal actions. - All other actions may be commenced
and tried where the defendant or any of the defendants resides
or may be found, or where the plaintiff or any of the plaintiff Similarly, the case of De Midgely vs. Ferandos, held that;
resides, at the election of the plaintiff.
When the appearance is by motion for the purpose of
Pragmatic considerations, including the convenience of the objecting to the jurisdiction of the court over the person, it
parties, also weigh heavily in favor of the RTC Quezon City must be for the sole and separate purpose of objecting to the
assuming jurisdiction. Paramount is the private interest of the jurisdiction of the court. If his motion is for any other purpose
litigant. Enforceability of a judgment if one is obtained is quite than to object to the jurisdiction of the court over his person,
obvious. Relative advantages and obstacles to a fair trial are he thereby submits himself to the jurisdiction of the court. A
equally important. Plaintiff may not, by choice of an special appearance by motion made for the purpose of
inconvenient forum, "vex", "harass", or "oppress" the objecting to the jurisdiction of the court over the person will
defendant, e.g. by inflicting upon him needless expense or be held to be a general appearance, if the party in said motion
disturbance. But unless the balance is strongly in favor of the should, for example, ask for a dismissal of the action upon the
defendant, the plaintiffs choice of forum should rarely be further ground that the court had no jurisdiction over the
disturbed. 49 subject matter. 52
Weighing the relative claims of the parties, the court a Clearly, petitioner had submitted to the jurisdiction of the
quo found it best to hear the case in the Philippines. Had it Regional Trial Court of Quezon City. Thus, we find that the
refused to take cognizance of the case, it would be forcing trial court has jurisdiction over the case and that its exercise
plaintiff (private respondent now) to seek remedial action thereof, justified.
elsewhere, i.e. in the Kingdom of Saudi Arabia where she no
longer maintains substantial connections. That would have As to the choice of applicable law, we note that choice-of-law
caused a fundamental unfairness to her. problems seek to answer two important questions: (1) What
legal system should control a given situation where some of
Moreover, by hearing the case in the Philippines no the significant facts occurred in two or more states; and (2) to
unnecessary difficulties and inconvenience have been shown what extent should the chosen legal system regulate the
by either of the parties. The choice of forum of the plaintiff situation. 53
(now private respondent) should be upheld.
Several theories have been propounded in order to identify the
Similarly, the trial court also possesses jurisdiction over the legal system that should ultimately control. Although ideally,
persons of the parties herein. By filing her Complaint and all choice-of-law theories should intrinsically advance both
Amended Complaint with the trial court, private respondent notions of justice and predictability, they do not always do so.
has voluntary submitted herself to the jurisdiction of the court. The forum is then faced with the problem of deciding which of
these two important values should be stressed. 54
The records show that petitioner SAUDIA has filed several
motions 50 praying for the dismissal of Morada's Amended Before a choice can be made, it is necessary for us to
Complaint. SAUDIA also filed an Answer In Ex Abundante determine under what category a certain set of facts or rules
Cautelam dated February 20, 1995. What is very patent and fall. This process is known as "characterization", or the
explicit from the motions filed, is that SAUDIA prayed for "doctrine of qualification". It is the "process of deciding
other reliefs under the premises. Undeniably, petitioner whether or not the facts relate to the kind of question specified
SAUDIA has effectively submitted to the trial court's in a conflicts rule." 55 The purpose of "characterization" is to
jurisdiction by praying for the dismissal of the Amended enable the forum to select the proper law. 56
Complaint on grounds other than lack of jurisdiction.
Our starting point of analysis here is not a legal relation, but a
As held by this Court in Republic vs. Ker and Company, factual situation, event, or operative fact. 57 An essential
Ltd.: 51 element of conflict rules is the indication of a "test" or
"connecting factor" or "point of contact". Choice-of-law rules
invariably consist of a factual relationship (such as property
We observe that the motion to dismiss filed on April 14, 1962, right, contract claim) and a connecting factor or point of
aside from disputing the lower court's jurisdiction over contact, such as the situs of the res, the place of celebration,
defendant's person, prayed for dismissal of the complaint on the place of performance, or the place of wrongdoing. 58
the ground that plaintiff's cause of action has prescribed. By
Note that one or more circumstances may be present to serve respondent. Petitioner thereby allegedly facilitated the arrest,
as the possible test for the determination of the applicable detention and prosecution of private respondent under the
law. 59 These "test factors" or "points of contact" or guise of petitioner's authority as employer, taking advantage
"connecting factors" could be any of the following: of the trust, confidence and faith she reposed upon it. As
purportedly found by the Prince of Makkah, the alleged
(1) The nationality of a person, his domicile, his residence, his conviction and imprisonment of private respondent was
place of sojourn, or his origin; wrongful. But these capped the injury or harm allegedly
inflicted upon her person and reputation, for which petitioner
(2) the seat of a legal or juridical person, such as a could be liable as claimed, to provide compensation or redress
corporation; for the wrongs done, once duly proven.
(3) the situs of a thing, that is, the place where a thing is, or is Considering that the complaint in the court a quo is one
deemed to be situated. In particular, the lex situs is decisive involving torts, the "connecting factor" or "point of contact"
when real rights are involved; could be the place or places where the tortious conduct or lex
loci actus occurred. And applying the torts principle in a
conflicts case, we find that the Philippines could be said as a
(4) the place where an act has been done, the locus actus, situs of the tort (the place where the alleged tortious conduct
such as the place where a contract has been made, a marriage took place). This is because it is in the Philippines where
celebrated, a will signed or a tort committed. The lex loci petitioner allegedly deceived private respondent, a Filipina
actus is particularly important in contracts and torts; residing and working here. According to her, she had honestly
believed that petitioner would, in the exercise of its rights and
(5) the place where an act is intended to come into effect, e.g., in the performance of its duties, "act with justice, give her due
the place of performance of contractual duties, or the place and observe honesty and good faith." Instead, petitioner failed
where a power of attorney is to be exercised; to protect her, she claimed. That certain acts or parts of the
injury allegedly occurred in another country is of no moment.
(6) the intention of the contracting parties as to the law that For in our view what is important here is the place where the
should govern their agreement, the lex loci intentionis; over-all harm or the totality of the alleged injury to the person,
reputation, social standing and human rights of complainant,
(7) the place where judicial or administrative proceedings are had lodged, according to the plaintiff below (herein private
instituted or done. The lex fori - the law of the forum - is respondent). All told, it is not without basis to identify the
particularly important because, as we have seen earlier, Philippines as the situs of the alleged tort.
matters of "procedure" not going to the substance of the claim
involved are governed by it; and because the lex fori applies Moreover, with the widespread criticism of the traditional rule
whenever the content of the otherwise applicable foreign law of lex loci delicti commissi, modern theories and rules on tort
is excluded from application in a given case for the reason that liability 61 have been advanced to offer fresh judicial
it falls under one of the exceptions to the applications of approaches to arrive at just results. In keeping abreast with the
foreign law; and modern theories on tort liability, we find here an occasion to
apply the "State of the most significant relationship" rule,
(8) the flag of a ship, which in many cases is decisive of which in our view should be appropriate to apply now, given
practically all legal relationships of the ship and of its master the factual context of this case.
or owner as such. It also covers contractual relationships
particularly contracts of affreightment. 60 (Emphasis ours.) In applying said principle to determine the State which has the
most significant relationship, the following contacts are to be
After a careful study of the pleadings on record, including taken into account and evaluated according to their relative
allegations in the Amended Complaint deemed admitted for importance with respect to the particular issue: (a) the place
purposes of the motion to dismiss, we are convinced that there where the injury occurred; (b) the place where the conduct
is reasonable basis for private respondent's assertion that causing the injury occurred; (c) the domicile, residence,
although she was already working in Manila, petitioner nationality, place of incorporation and place of business of the
brought her to Jeddah on the pretense that she would merely parties, and (d) the place where the relationship, if any,
testify in an investigation of the charges she made against the between the parties is centered. 62
two SAUDIA crew members for the attack on her person
while they were in Jakarta. As it turned out, she was the one As already discussed, there is basis for the claim that over-all
made to face trial for very serious charges, including adultery injury occurred and lodged in the Philippines. There is
and violation of Islamic laws and tradition. likewise no question that private respondent is a resident
Filipina national, working with petitioner, a resident foreign
There is likewise logical basis on record for the claim that the corporation engaged here in the business of international air
"handing over" or "turning over" of the person of private carriage. Thus, the "relationship" between the parties was
respondent to Jeddah officials, petitioner may have acted centered here, although it should be stressed that this suit is
beyond its duties as employer. Petitioner's purported act not based on mere labor law violations. From the record, the
contributed to and amplified or even proximately caused claim that the Philippines has the most significant contact with
additional humiliation, misery and suffering of private the matter in this dispute, 63 raised by private respondent as
plaintiff below against defendant (herein petitioner), in our
view, has been properly established.
SO ORDERED.
5,079-square meter property with a 4,032-square meter
warehouse building to house the LPG manufacturing plant.
The monthly rental was PhP 322,560 commencing on January
1, 1998 with a 10% annual increment clause. Subsequently,
the machineries, equipment, and facilities for the manufacture
of LPG cylinders were shipped, delivered, and installed in the
Republic of the Philippines Carmona plant. PGSMC paid KOGIES USD 1,224,000.
SUPREME COURT
Manila However, gleaned from the Certificate 4 executed by the parties
on January 22, 1998, after the installation of the plant, the
SECOND DIVISION initial operation could not be conducted as PGSMC
encountered financial difficulties affecting the supply of
materials, thus forcing the parties to agree that KOGIES
G.R. No. 143581 January 7, 2008 would be deemed to have completely complied with the terms
and conditions of the March 5, 1997 contract.
KOREA TECHNOLOGIES CO., LTD., petitioner,
vs. For the remaining balance of USD306,000 for the installation
HON. ALBERTO A. LERMA, in his capacity as Presiding and initial operation of the plant, PGSMC issued two
Judge of Branch 256 of Regional Trial Court of postdated checks: (1) BPI Check No. 0316412 dated January
Muntinlupa City, and PACIFIC GENERAL STEEL 30, 1998 for PhP 4,500,000; and (2) BPI Check No. 0316413
MANUFACTURING CORPORATION, respondents. dated March 30, 1998 for PhP 4,500,000.5
After the parties submitted their Memoranda, on July 23, On September 21, 1998, the trial court issued an Order (1)
1998, the RTC issued an Order denying the application for a granting PGSMC’s motion for inspection; (2) denying
writ of preliminary injunction, reasoning that PGSMC had KOGIES’ motion for reconsideration of the July 23, 1998
paid KOGIES USD 1,224,000, the value of the machineries RTC Order; and (3) denying KOGIES’ motion to dismiss
and equipment as shown in the contract such that KOGIES no PGSMC’s compulsory counterclaims as these counterclaims
longer had proprietary rights over them. And finally, the RTC fell within the requisites of compulsory counterclaims.
held that Art. 15 of the Contract as amended was invalid as it
tended to oust the trial court or any other court jurisdiction On October 2, 1998, KOGIES filed an Urgent Motion for
over any dispute that may arise between the parties. KOGIES’ Reconsideration17 of the September 21, 1998 RTC Order
prayer for an injunctive writ was denied. 10 The dispositive granting inspection of the plant and denying dismissal of
portion of the Order stated: PGSMC’s compulsory counterclaims.
WHEREFORE, in view of the foregoing Ten days after, on October 12, 1998, without waiting for the
consideration, this Court believes and so holds that resolution of its October 2, 1998 urgent motion for
no cogent reason exists for this Court to grant the reconsideration, KOGIES filed before the Court of Appeals
(CA) a petition for certiorari 18 docketed as CA-G.R. SP No. September 21, 1998 RTC Order which was the plain, speedy,
49249, seeking annulment of the July 23, 1998 and September and adequate remedy available. According to the CA, the RTC
21, 1998 RTC Orders and praying for the issuance of writs of must be given the opportunity to correct any alleged error it
prohibition, mandamus, and preliminary injunction to enjoin has committed, and that since the assailed orders were
the RTC and PGSMC from inspecting, dismantling, and interlocutory, these cannot be the subject of a petition for
transferring the machineries and equipment in the Carmona certiorari.
plant, and to direct the RTC to enforce the specific agreement
on arbitration to resolve the dispute. Hence, we have this Petition for Review on Certiorari under
Rule 45.
In the meantime, on October 19, 1998, the RTC denied
KOGIES’ urgent motion for reconsideration and directed the The Issues
Branch Sheriff to proceed with the inspection of the
machineries and equipment in the plant on October 28, 1998.19 Petitioner posits that the appellate court committed the
following errors:
Thereafter, KOGIES filed a Supplement to the Petition 20 in
CA-G.R. SP No. 49249 informing the CA about the October a. PRONOUNCING THE QUESTION OF
19, 1998 RTC Order. It also reiterated its prayer for the OWNERSHIP OVER THE MACHINERY AND
issuance of the writs of prohibition, mandamus and FACILITIES AS "A QUESTION OF FACT"
preliminary injunction which was not acted upon by the CA. "BEYOND THE AMBIT OF A PETITION FOR
KOGIES asserted that the Branch Sheriff did not have the CERTIORARI" INTENDED ONLY FOR
technical expertise to ascertain whether or not the machineries CORRECTION OF ERRORS OF JURISDICTION
and equipment conformed to the specifications in the contract OR GRAVE ABUSE OF DISCRETION
and were properly installed. AMOUNTING TO LACK OF (SIC) EXCESS OF
JURISDICTION, AND CONCLUDING THAT THE
On November 11, 1998, the Branch Sheriff filed his Sheriff’s TRIAL COURT’S FINDING ON THE SAME
Report21 finding that the enumerated machineries and QUESTION WAS IMPROPERLY RAISED IN THE
equipment were not fully and properly installed. PETITION BELOW;
The Court of Appeals affirmed the trial court and declared b. DECLARING AS NULL AND VOID THE
the arbitration clause against public policy ARBITRATION CLAUSE IN ARTICLE 15 OF
THE CONTRACT BETWEEN THE PARTIES FOR
On May 30, 2000, the CA rendered the assailed BEING "CONTRARY TO PUBLIC POLICY" AND
Decision22 affirming the RTC Orders and dismissing the FOR OUSTING THE COURTS OF
petition for certiorari filed by KOGIES. The CA found that the JURISDICTION;
RTC did not gravely abuse its discretion in issuing the assailed
July 23, 1998 and September 21, 1998 Orders. Moreover, the c. DECREEING PRIVATE RESPONDENT’S
CA reasoned that KOGIES’ contention that the total contract COUNTERCLAIMS TO BE ALL COMPULSORY
price for USD 1,530,000 was for the whole plant and had not NOT NECESSITATING PAYMENT OF DOCKET
been fully paid was contrary to the finding of the RTC that FEES AND CERTIFICATION OF NON-FORUM
PGSMC fully paid the price of USD 1,224,000, which was for SHOPPING;
all the machineries and equipment. According to the CA, this
determination by the RTC was a factual finding beyond the d. RULING THAT THE PETITION WAS FILED
ambit of a petition for certiorari. PREMATURELY WITHOUT WAITING FOR THE
RESOLUTION OF THE MOTION FOR
On the issue of the validity of the arbitration clause, the CA RECONSIDERATION OF THE ORDER DATED
agreed with the lower court that an arbitration clause which SEPTEMBER 21, 1998 OR WITHOUT GIVING
provided for a final determination of the legal rights of the THE TRIAL COURT AN OPPORTUNITY TO
parties to the contract by arbitration was against public policy. CORRECT ITSELF;
On the issue of nonpayment of docket fees and non- e. PROCLAIMING THE TWO ORDERS DATED
attachment of a certificate of non-forum shopping by PGSMC, JULY 23 AND SEPTEMBER 21, 1998 NOT TO BE
the CA held that the counterclaims of PGSMC were PROPER SUBJECTS OF CERTIORARI AND
compulsory ones and payment of docket fees was not required PROHIBITION FOR BEING "INTERLOCUTORY
since the Answer with counterclaim was not an initiatory IN NATURE;"
pleading. For the same reason, the CA said a certificate of
non-forum shopping was also not required. f. NOT GRANTING THE RELIEFS AND
REMEDIES PRAYED FOR IN HE (SIC) PETITION
Furthermore, the CA held that the petition for certiorari had AND, INSTEAD, DISMISSING THE SAME FOR
been filed prematurely since KOGIES did not wait for the ALLEGEDLY "WITHOUT MERIT."23
resolution of its urgent motion for reconsideration of the
The Court’s Ruling The proper remedy in such cases is an ordinary
appeal from an adverse judgment on the merits,
The petition is partly meritorious. incorporating in said appeal the grounds for assailing
the interlocutory orders. Allowing appeals from
Before we delve into the substantive issues, we shall first interlocutory orders would result in the ‘sorry
tackle the procedural issues. spectacle’ of a case being subject of a
counterproductive ping-pong to and from the
appellate court as often as a trial court is perceived to
The rules on the payment of docket fees for counterclaims have made an error in any of its interlocutory rulings.
and cross claims were amended effective August 16, 2004 However, where the assailed interlocutory order was
issued with grave abuse of discretion or patently
KOGIES strongly argues that when PGSMC filed the erroneous and the remedy of appeal would not afford
counterclaims, it should have paid docket fees and filed a adequate and expeditious relief, the Court allows
certificate of non-forum shopping, and that its failure to do so certiorari as a mode of redress.28
was a fatal defect.
Also, appeals from interlocutory orders would open the
We disagree with KOGIES. floodgates to endless occasions for dilatory motions. Thus,
where the interlocutory order was issued without or in excess
As aptly ruled by the CA, the counterclaims of PGSMC were of jurisdiction or with grave abuse of discretion, the remedy is
incorporated in its Answer with Compulsory Counterclaim certiorari.29
dated July 17, 1998 in accordance with Section 8 of Rule 11,
1997 Revised Rules of Civil Procedure, the rule that was The alleged grave abuse of discretion of the respondent court
effective at the time the Answer with Counterclaim was filed. equivalent to lack of jurisdiction in the issuance of the two
Sec. 8 on existing counterclaim or cross-claim states, "A assailed orders coupled with the fact that there is no plain,
compulsory counterclaim or a cross-claim that a defending speedy, and adequate remedy in the ordinary course of law
party has at the time he files his answer shall be contained amply provides the basis for allowing the resort to a petition
therein." for certiorari under Rule 65.
On July 17, 1998, at the time PGSMC filed its Answer Prematurity of the petition before the CA
incorporating its counterclaims against KOGIES, it was not
liable to pay filing fees for said counterclaims being Neither do we think that KOGIES was guilty of forum
compulsory in nature. We stress, however, that effective shopping in filing the petition for certiorari. Note that
August 16, 2004 under Sec. 7, Rule 141, as amended by A.M. KOGIES’ motion for reconsideration of the July 23, 1998
No. 04-2-04-SC, docket fees are now required to be paid in RTC Order which denied the issuance of the injunctive writ
compulsory counterclaim or cross-claims. had already been denied. Thus, KOGIES’ only remedy was to
assail the RTC’s interlocutory order via a petition for certiorari
As to the failure to submit a certificate of forum shopping, under Rule 65.
PGSMC’s Answer is not an initiatory pleading which requires
a certification against forum shopping under Sec. 524 of Rule While the October 2, 1998 motion for reconsideration of
7, 1997 Revised Rules of Civil Procedure. It is a responsive KOGIES of the September 21, 1998 RTC Order relating to the
pleading, hence, the courts a quo did not commit reversible inspection of things, and the allowance of the compulsory
error in denying KOGIES’ motion to dismiss PGSMC’s counterclaims has not yet been resolved, the circumstances in
compulsory counterclaims. this case would allow an exception to the rule that before
certiorari may be availed of, the petitioner must have filed a
Interlocutory orders proper subject of certiorari motion for reconsideration and said motion should have been
first resolved by the court a quo. The reason behind the rule is
Citing Gamboa v. Cruz,25 the CA also pronounced that "to enable the lower court, in the first instance, to pass upon
"certiorari and Prohibition are neither the remedies to question and correct its mistakes without the intervention of the higher
the propriety of an interlocutory order of the trial court." 26 The court."30
CA erred on its reliance on Gamboa. Gamboa involved the
denial of a motion to acquit in a criminal case which was not The September 21, 1998 RTC Order directing the branch
assailable in an action for certiorari since the denial of a sheriff to inspect the plant, equipment, and facilities when he
motion to quash required the accused to plead and to continue is not competent and knowledgeable on said matters is
with the trial, and whatever objections the accused had in his evidently flawed and devoid of any legal support. Moreover,
motion to quash can then be used as part of his defense and there is an urgent necessity to resolve the issue on the
subsequently can be raised as errors on his appeal if the dismantling of the facilities and any further delay would
judgment of the trial court is adverse to him. The general rule prejudice the interests of KOGIES. Indeed, there is real and
is that interlocutory orders cannot be challenged by an imminent threat of irreparable destruction or substantial
appeal.27 Thus, in Yamaoka v. Pescarich Manufacturing damage to KOGIES’ equipment and machineries. We find the
Corporation, we held: resort to certiorari based on the gravely abusive orders of the
trial court sans the ruling on the October 2, 1998 motion for Commercial Arbitration Rules of the KCAB, and that the
reconsideration to be proper. arbitral award is final and binding, is not contrary to public
policy. This Court has sanctioned the validity of arbitration
The Core Issue: Article 15 of the Contract clauses in a catena of cases. In the 1957 case of Eastboard
Navigation Ltd. v. Juan Ysmael and Co., Inc.,38 this Court had
We now go to the core issue of the validity of Art. 15 of the occasion to rule that an arbitration clause to resolve
Contract, the arbitration clause. It provides: differences and breaches of mutually agreed contractual terms
is valid. In BF Corporation v. Court of Appeals, we held that
"[i]n this jurisdiction, arbitration has been held valid and
Article 15. Arbitration.—All disputes, controversies, constitutional. Even before the approval on June 19, 1953 of
or differences which may arise between the parties, Republic Act No. 876, this Court has countenanced the
out of or in relation to or in connection with this settlement of disputes through arbitration. Republic Act No.
Contract or for the breach thereof, shall finally be 876 was adopted to supplement the New Civil Code’s
settled by arbitration in Seoul, Korea in accordance provisions on arbitration."39 And in LM Power Engineering
with the Commercial Arbitration Rules of the Korean Corporation v. Capitol Industrial Construction Groups, Inc.,
Commercial Arbitration Board. The award we declared that:
rendered by the arbitration(s) shall be final and
binding upon both parties concerned. (Emphasis
supplied.) Being an inexpensive, speedy and amicable method
of settling disputes, arbitration––along with
mediation, conciliation and negotiation––is
Petitioner claims the RTC and the CA erred in ruling that the encouraged by the Supreme Court. Aside from
arbitration clause is null and void. unclogging judicial dockets, arbitration also hastens
the resolution of disputes, especially of the
Petitioner is correct. commercial kind. It is thus regarded as the "wave of
the future" in international civil and commercial
Established in this jurisdiction is the rule that the law of the disputes. Brushing aside a contractual agreement
place where the contract is made governs. Lex loci contractus. calling for arbitration between the parties would be a
The contract in this case was perfected here in the Philippines. step backward.
Therefore, our laws ought to govern. Nonetheless, Art. 2044
of the Civil Code sanctions the validity of mutually agreed Consistent with the above-mentioned policy of
arbitral clause or the finality and binding effect of an arbitral encouraging alternative dispute resolution methods,
award. Art. 2044 provides, "Any stipulation that the courts should liberally construe arbitration clauses.
arbitrators’ award or decision shall be final, is valid, Provided such clause is susceptible of an
without prejudice to Articles 2038, 2039 and 2040." interpretation that covers the asserted dispute, an
(Emphasis supplied.) order to arbitrate should be granted. Any doubt
should be resolved in favor of arbitration.40
Arts. 2038,31 2039,32 and 204033 abovecited refer to instances
where a compromise or an arbitral award, as applied to Art. Having said that the instant arbitration clause is not against
2044 pursuant to Art. 2043,34 may be voided, rescinded, or public policy, we come to the question on what governs an
annulled, but these would not denigrate the finality of the arbitration clause specifying that in case of any dispute arising
arbitral award. from the contract, an arbitral panel will be constituted in a
foreign country and the arbitration rules of the foreign country
The arbitration clause was mutually and voluntarily agreed would govern and its award shall be final and binding.
upon by the parties. It has not been shown to be contrary to
any law, or against morals, good customs, public order, or RA 9285 incorporated the UNCITRAL Model law
public policy. There has been no showing that the parties have to which we are a signatory
not dealt with each other on equal footing. We find no reason
why the arbitration clause should not be respected and For domestic arbitration proceedings, we have particular
complied with by both parties. In Gonzales v. Climax Mining agencies to arbitrate disputes arising from contractual
Ltd.,35 we held that submission to arbitration is a contract and relations. In case a foreign arbitral body is chosen by the
that a clause in a contract providing that all matters in dispute parties, the arbitration rules of our domestic arbitration bodies
between the parties shall be referred to arbitration is a would not be applied. As signatory to the Arbitration Rules of
contract.36 Again in Del Monte Corporation-USA v. Court of the UNCITRAL Model Law on International Commercial
Appeals, we likewise ruled that "[t]he provision to submit to Arbitration41 of the United Nations Commission on
arbitration any dispute arising therefrom and the relationship International Trade Law (UNCITRAL) in the New York
of the parties is part of that contract and is itself a contract." 37 Convention on June 21, 1985, the Philippines committed itself
to be bound by the Model Law. We have even incorporated
Arbitration clause not contrary to public policy the Model Law in Republic Act No. (RA) 9285, otherwise
known as the Alternative Dispute Resolution Act of 2004
The arbitration clause which stipulates that the arbitration entitled An Act to Institutionalize the Use of an Alternative
must be done in Seoul, Korea in accordance with the Dispute Resolution System in the Philippines and to Establish
the Office for Alternative Dispute Resolution, and for Other finds that the arbitration agreement is null and void,
Purposes, promulgated on April 2, 2004. Secs. 19 and 20 of inoperative or incapable of being performed.
Chapter 4 of the Model Law are the pertinent provisions:
(2) Foreign arbitral awards must be confirmed by the RTC
CHAPTER 4 - INTERNATIONAL COMMERCIAL
ARBITRATION Foreign arbitral awards while mutually stipulated by the
parties in the arbitration clause to be final and binding are not
SEC. 19. Adoption of the Model Law on immediately enforceable or cannot be implemented
International Commercial Arbitration.––International immediately. Sec. 3543 of the UNCITRAL Model Law
commercial arbitration shall be governed by the stipulates the requirement for the arbitral award to be
Model Law on International Commercial Arbitration recognized by a competent court for enforcement, which court
(the "Model Law") adopted by the United Nations under Sec. 36 of the UNCITRAL Model Law may refuse
Commission on International Trade Law on June 21, recognition or enforcement on the grounds provided for. RA
1985 (United Nations Document A/40/17) and 9285 incorporated these provisos to Secs. 42, 43, and 44
recommended for enactment by the General relative to Secs. 47 and 48, thus:
Assembly in Resolution No. 40/72 approved on
December 11, 1985, copy of which is hereto attached SEC. 42. Application of the New York Convention.––
as Appendix "A". The New York Convention shall govern the
recognition and enforcement of arbitral awards
SEC. 20. Interpretation of Model Law.––In covered by said Convention.
interpreting the Model Law, regard shall be had to its
international origin and to the need for uniformity in The recognition and enforcement of such arbitral
its interpretation and resort may be made to awards shall be filed with the Regional Trial
the travaux preparatories and the report of the Court in accordance with the rules of procedure to be
Secretary General of the United Nations Commission promulgated by the Supreme Court. Said procedural
on International Trade Law dated March 25, 1985 rules shall provide that the party relying on the award
entitled, "International Commercial Arbitration: or applying for its enforcement shall file with the
Analytical Commentary on Draft Trade identified by court the original or authenticated copy of the award
reference number A/CN. 9/264." and the arbitration agreement. If the award or
agreement is not made in any of the official
While RA 9285 was passed only in 2004, it nonetheless languages, the party shall supply a duly certified
applies in the instant case since it is a procedural law which translation thereof into any of such languages.
has a retroactive effect. Likewise, KOGIES filed its
application for arbitration before the KCAB on July 1, 1998 The applicant shall establish that the country in
and it is still pending because no arbitral award has yet been which foreign arbitration award was made in party to
rendered. Thus, RA 9285 is applicable to the instant case. the New York Convention.
Well-settled is the rule that procedural laws are construed to
be applicable to actions pending and undetermined at the time xxxx
of their passage, and are deemed retroactive in that sense and
to that extent. As a general rule, the retroactive application of
procedural laws does not violate any personal rights because SEC. 43. Recognition and Enforcement of Foreign
no vested right has yet attached nor arisen from them.42 Arbitral Awards Not Covered by the New York
Convention.––The recognition and enforcement of
foreign arbitral awards not covered by the New York
Among the pertinent features of RA 9285 applying and Convention shall be done in accordance with
incorporating the UNCITRAL Model Law are the following: procedural rules to be promulgated by the Supreme
Court. The Court may, on grounds of comity and
(1) The RTC must refer to arbitration in proper cases reciprocity, recognize and enforce a non-convention
award as a convention award.
Under Sec. 24, the RTC does not have jurisdiction over
disputes that are properly the subject of arbitration pursuant to SEC. 44. Foreign Arbitral Award Not Foreign
an arbitration clause, and mandates the referral to arbitration Judgment.––A foreign arbitral award when
in such cases, thus: confirmed by a court of a foreign country, shall be
recognized and enforced as a foreign arbitral award
SEC. 24. Referral to Arbitration.––A court before and not as a judgment of a foreign court.
which an action is brought in a matter which is the
subject matter of an arbitration agreement shall, if at A foreign arbitral award, when confirmed by the
least one party so requests not later than the pre-trial Regional Trial Court, shall be enforced in the same
conference, or upon the request of both parties manner as final and executory decisions of courts of
thereafter, refer the parties to arbitration unless it law of the Philippines
xxxx court the original or authenticated copy of the award
and the arbitration agreement. If the award or
SEC. 47. Venue and Jurisdiction.––Proceedings for agreement is not made in any of the official
recognition and enforcement of an arbitration languages, the party shall supply a duly certified
agreement or for vacations, setting aside, correction translation thereof into any of such languages.
or modification of an arbitral award, and any
application with a court for arbitration assistance and The applicant shall establish that the country in
supervision shall be deemed as special proceedings which foreign arbitration award was made is party to
and shall be filed with the Regional Trial Court (i) the New York Convention.
where arbitration proceedings are conducted; (ii)
where the asset to be attached or levied upon, or the If the application for rejection or suspension of
act to be enjoined is located; (iii) where any of the enforcement of an award has been made, the
parties to the dispute resides or has his place of Regional Trial Court may, if it considers it proper,
business; or (iv) in the National Judicial Capital vacate its decision and may also, on the application
Region, at the option of the applicant. of the party claiming recognition or enforcement of
the award, order the party to provide appropriate
SEC. 48. Notice of Proceeding to Parties.––In a security.
special proceeding for recognition and enforcement
of an arbitral award, the Court shall send notice to the xxxx
parties at their address of record in the arbitration, or
if any part cannot be served notice at such address, at SEC. 45. Rejection of a Foreign Arbitral Award.––A
such party’s last known address. The notice shall be party to a foreign arbitration proceeding may oppose
sent al least fifteen (15) days before the date set for an application for recognition and enforcement of the
the initial hearing of the application. arbitral award in accordance with the procedures and
rules to be promulgated by the Supreme Court only
It is now clear that foreign arbitral awards when confirmed by on those grounds enumerated under Article V of the
the RTC are deemed not as a judgment of a foreign court but New York Convention. Any other ground raised shall
as a foreign arbitral award, and when confirmed, are enforced be disregarded by the Regional Trial Court.
as final and executory decisions of our courts of law.
Thus, while the RTC does not have jurisdiction over disputes
Thus, it can be gleaned that the concept of a final and binding governed by arbitration mutually agreed upon by the parties,
arbitral award is similar to judgments or awards given by still the foreign arbitral award is subject to judicial review by
some of our quasi-judicial bodies, like the National Labor the RTC which can set aside, reject, or vacate it. In this sense,
Relations Commission and Mines Adjudication Board, whose what this Court held in Chung Fu Industries (Phils.), Inc.
final judgments are stipulated to be final and binding, but not relied upon by KOGIES is applicable insofar as the foreign
immediately executory in the sense that they may still be arbitral awards, while final and binding, do not oust courts of
judicially reviewed, upon the instance of any party. Therefore, jurisdiction since these arbitral awards are not absolute and
the final foreign arbitral awards are similarly situated in that without exceptions as they are still judicially reviewable.
they need first to be confirmed by the RTC. Chapter 7 of RA 9285 has made it clear that all arbitral
awards, whether domestic or foreign, are subject to judicial
(3) The RTC has jurisdiction to review foreign arbitral review on specific grounds provided for.
awards
(4) Grounds for judicial review different in domestic and
Sec. 42 in relation to Sec. 45 of RA 9285 designated and foreign arbitral awards
vested the RTC with specific authority and jurisdiction to set
aside, reject, or vacate a foreign arbitral award on grounds The differences between a final arbitral award from an
provided under Art. 34(2) of the UNCITRAL Model Law. international or foreign arbitral tribunal and an award given by
Secs. 42 and 45 provide: a local arbitral tribunal are the specific grounds or conditions
that vest jurisdiction over our courts to review the awards.
SEC. 42. Application of the New York Convention.––
The New York Convention shall govern the For foreign or international arbitral awards which must first be
recognition and enforcement of arbitral awards confirmed by the RTC, the grounds for setting aside, rejecting
covered by said Convention. or vacating the award by the RTC are provided under Art.
34(2) of the UNCITRAL Model Law.
The recognition and enforcement of such arbitral
awards shall be filed with the Regional Trial For final domestic arbitral awards, which also need
Court in accordance with the rules of procedure to be confirmation by the RTC pursuant to Sec. 23 of RA 876 44 and
promulgated by the Supreme Court. Said procedural shall be recognized as final and executory decisions of the
rules shall provide that the party relying on the award RTC,45 they may only be assailed before the RTC and vacated
or applying for its enforcement shall file with the on the grounds provided under Sec. 25 of RA 876.46
(5) RTC decision of assailed foreign arbitral award What this Court held in University of the Philippines v. De
appealable Los Angeles47 and reiterated in succeeding cases, 48 that the act
of treating a contract as rescinded on account of infractions by
Sec. 46 of RA 9285 provides for an appeal before the CA as the other contracting party is valid albeit provisional as it can
the remedy of an aggrieved party in cases where the RTC sets be judicially assailed, is not applicable to the instant case on
aside, rejects, vacates, modifies, or corrects an arbitral award, account of a valid stipulation on arbitration. Where an
thus: arbitration clause in a contract is availing, neither of the
parties can unilaterally treat the contract as rescinded since
SEC. 46. Appeal from Court Decision or Arbitral whatever infractions or breaches by a party or differences
Awards.—A decision of the Regional Trial Court arising from the contract must be brought first and resolved by
confirming, vacating, setting aside, modifying or arbitration, and not through an extrajudicial rescission or
correcting an arbitral award may be appealed to the judicial action.
Court of Appeals in accordance with the rules and
procedure to be promulgated by the Supreme Court. The issues arising from the contract between PGSMC and
KOGIES on whether the equipment and machineries delivered
The losing party who appeals from the judgment of and installed were properly installed and operational in the
the court confirming an arbitral award shall be plant in Carmona, Cavite; the ownership of equipment and
required by the appellate court to post a counterbond payment of the contract price; and whether there was
executed in favor of the prevailing party equal to the substantial compliance by KOGIES in the production of the
amount of the award in accordance with the rules to samples, given the alleged fact that PGSMC could not supply
be promulgated by the Supreme Court. the raw materials required to produce the sample LPG
cylinders, are matters proper for arbitration. Indeed, we note
that on July 1, 1998, KOGIES instituted an Application for
Thereafter, the CA decision may further be appealed or Arbitration before the KCAB in Seoul, Korea pursuant to Art.
reviewed before this Court through a petition for review under 15 of the Contract as amended. Thus, it is incumbent upon
Rule 45 of the Rules of Court. PGSMC to abide by its commitment to arbitrate.
PGSMC has remedies to protect its interests Corollarily, the trial court gravely abused its discretion in
granting PGSMC’s Motion for Inspection of Things on
Thus, based on the foregoing features of RA 9285, PGSMC September 21, 1998, as the subject matter of the motion is
must submit to the foreign arbitration as it bound itself under the primary jurisdiction of the mutually agreed arbitral
through the subject contract. While it may have misgivings on body, the KCAB in Korea.
the foreign arbitration done in Korea by the KCAB, it has
available remedies under RA 9285. Its interests are duly In addition, whatever findings and conclusions made by the
protected by the law which requires that the arbitral award that RTC Branch Sheriff from the inspection made on October 28,
may be rendered by KCAB must be confirmed here by the 1998, as ordered by the trial court on October 19, 1998, is of
RTC before it can be enforced. no worth as said Sheriff is not technically competent to
ascertain the actual status of the equipment and machineries as
With our disquisition above, petitioner is correct in its installed in the plant.
contention that an arbitration clause, stipulating that the
arbitral award is final and binding, does not oust our courts of For these reasons, the September 21, 1998 and October 19,
jurisdiction as the international arbitral award, the award of 1998 RTC Orders pertaining to the grant of the inspection of
which is not absolute and without exceptions, is still judicially the equipment and machineries have to be recalled and
reviewable under certain conditions provided for by the nullified.
UNCITRAL Model Law on ICA as applied and incorporated
in RA 9285.
Issue on ownership of plant proper for arbitration
Finally, it must be noted that there is nothing in the subject
Contract which provides that the parties may dispense with the Petitioner assails the CA ruling that the issue petitioner raised
arbitration clause. on whether the total contract price of USD 1,530,000 was for
the whole plant and its installation is beyond the ambit of a
Petition for Certiorari.
Unilateral rescission improper and illegal
Petitioner’s position is untenable.
Having ruled that the arbitration clause of the subject contract
is valid and binding on the parties, and not contrary to public
policy; consequently, being bound to the contract of It is settled that questions of fact cannot be raised in an
arbitration, a party may not unilaterally rescind or terminate original action for certiorari.49 Whether or not there was full
the contract for whatever cause without first resorting to payment for the machineries and equipment and installation is
arbitration. indeed a factual issue prohibited by Rule 65.
However, what appears to constitute a grave abuse of (c) The order granting provisional relief may be
discretion is the order of the RTC in resolving the issue on the conditioned upon the provision of security or any act
ownership of the plant when it is the arbitral body (KCAB) or omission specified in the order.
and not the RTC which has jurisdiction and authority over the
said issue. The RTC’s determination of such factual issue (d) Interim or provisional relief is requested by
constitutes grave abuse of discretion and must be reversed and written application transmitted by reasonable means
set aside. to the Court or arbitral tribunal as the case may be
and the party against whom the relief is sought,
RTC has interim jurisdiction to protect the rights of the describing in appropriate detail the precise relief, the
parties party against whom the relief is requested, the
grounds for the relief, and the evidence supporting
Anent the July 23, 1998 Order denying the issuance of the the request.
injunctive writ paving the way for PGSMC to dismantle and
transfer the equipment and machineries, we find it to be in (e) The order shall be binding upon the parties.
order considering the factual milieu of the instant case.
(f) Either party may apply with the Court for
Firstly, while the issue of the proper installation of the assistance in implementing or enforcing an interim
equipment and machineries might well be under the primary measure ordered by an arbitral tribunal.
jurisdiction of the arbitral body to decide, yet the RTC under
Sec. 28 of RA 9285 has jurisdiction to hear and grant interim (g) A party who does not comply with the order shall
measures to protect vested rights of the parties. Sec. 28 be liable for all damages resulting from
pertinently provides: noncompliance, including all expenses, and
reasonable attorney's fees, paid in obtaining the
SEC. 28. Grant of interim Measure of Protection.— order’s judicial enforcement. (Emphasis ours.)
(a) It is not incompatible with an arbitration
agreement for a party to request, before Art. 17(2) of the UNCITRAL Model Law on ICA defines an
constitution of the tribunal, from a Court to grant "interim measure" of protection as:
such measure. After constitution of the arbitral
tribunal and during arbitral proceedings, a request for Article 17. Power of arbitral tribunal to order
an interim measure of protection, or modification interim measures
thereof, may be made with the arbitral or to the
extent that the arbitral tribunal has no power to
act or is unable to act effectivity, the request may xxx xxx xxx
be made with the Court. The arbitral tribunal is
deemed constituted when the sole arbitrator or the (2) An interim measure is any temporary measure,
third arbitrator, who has been nominated, has whether in the form of an award or in another form,
accepted the nomination and written communication by which, at any time prior to the issuance of the
of said nomination and acceptance has been received award by which the dispute is finally decided, the
by the party making the request. arbitral tribunal orders a party to:
(b) The following rules on interim or provisional (a) Maintain or restore the status quo pending
relief shall be observed: determination of the dispute;
Any party may request that provisional relief be (b) Take action that would prevent, or refrain from
granted against the adverse party. taking action that is likely to cause, current or
imminent harm or prejudice to the arbitral process
Such relief may be granted: itself;
(i) to prevent irreparable loss or injury; (c) Provide a means of preserving assets out of which
a subsequent award may be satisfied; or
(ii) to provide security for the performance
of any obligation; (d) Preserve evidence that may be relevant and
material to the resolution of the dispute.
(iii) to produce or preserve any evidence; or
Art. 17 J of UNCITRAL Model Law on ICA also grants
courts power and jurisdiction to issue interim measures:
(iv) to compel any other appropriate act or
omission.
Article 17 J. Court-ordered interim measures
A court shall have the same power of issuing an Moreover, KOGIES is amply protected by the arbitral action it
interim measure in relation to arbitration proceedings, has instituted before the KCAB, the award of which can be
irrespective of whether their place is in the territory enforced in our jurisdiction through the RTC. Besides, by our
of this State, as it has in relation to proceedings in decision, PGSMC is compelled to submit to arbitration
courts. The court shall exercise such power in pursuant to the valid arbitration clause of its contract with
accordance with its own procedures in consideration KOGIES.
of the specific features of international arbitration.
PGSMC to preserve the subject equipment and
In the recent 2006 case of Transfield Philippines, Inc. v. machineries
Luzon Hydro Corporation, we were explicit that even "the
pendency of an arbitral proceeding does not foreclose resort to Finally, while PGSMC may have been granted the right to
the courts for provisional reliefs." We explicated this way: dismantle and transfer the subject equipment and machineries,
it does not have the right to convey or dispose of the same
As a fundamental point, the pendency of arbitral considering the pending arbitral proceedings to settle the
proceedings does not foreclose resort to the courts for differences of the parties. PGSMC therefore must preserve and
provisional reliefs. The Rules of the ICC, which maintain the subject equipment and machineries with the
governs the parties’ arbitral dispute, allows the diligence of a good father of a family51 until final resolution of
application of a party to a judicial authority for the arbitral proceedings and enforcement of the award, if any.
interim or conservatory measures. Likewise, Section
14 of Republic Act (R.A.) No. 876 (The Arbitration WHEREFORE, this petition is PARTLY GRANTED, in
Law) recognizes the rights of any party to petition the that:
court to take measures to safeguard and/or conserve
any matter which is the subject of the dispute in (1) The May 30, 2000 CA Decision in CA-G.R. SP No. 49249
arbitration. In addition, R.A. 9285, otherwise known is REVERSED and SET ASIDE;
as the "Alternative Dispute Resolution Act of 2004,"
allows the filing of provisional or interim measures
with the regular courts whenever the arbitral tribunal (2) The September 21, 1998 and October 19, 1998 RTC
has no power to act or to act effectively.50 Orders in Civil Case No. 98-117 are REVERSED and SET
ASIDE;
It is thus beyond cavil that the RTC has authority and
jurisdiction to grant interim measures of protection. (3) The parties are hereby ORDERED to submit themselves
to the arbitration of their dispute and differences arising from
the subject Contract before the KCAB; and
Secondly, considering that the equipment and machineries are
in the possession of PGSMC, it has the right to protect and
preserve the equipment and machineries in the best way it can. (4) PGSMC is hereby ALLOWED to dismantle and transfer
Considering that the LPG plant was non-operational, PGSMC the equipment and machineries, if it had not done so,
has the right to dismantle and transfer the equipment and and ORDERED to preserve and maintain them until the
machineries either for their protection and preservation or for finality of whatever arbitral award is given in the arbitration
the better way to make good use of them which is ineluctably proceedings.
within the management discretion of PGSMC.
No pronouncement as to costs.
Thirdly, and of greater import is the reason that maintaining
the equipment and machineries in Worth’s property is not to SO ORDERED.
the best interest of PGSMC due to the prohibitive rent while
the LPG plant as set-up is not operational. PGSMC was losing
PhP322,560 as monthly rentals or PhP3.87M for 1998 alone
without considering the 10% annual rent increment in
maintaining the plant.
Upon the application of respondents 3-Plex and VPECI, Upon receiving a copy of that telex message on 27 October
petitioner Philguarantee issued in favor of Al Ahli Bank of 1986, respondent VPECI requested Iraq Trade and Economic
Kuwait Letter of Guarantee No. 81-194-F 10 (Performance Development Minister Mohammad Fadhi Hussein to recall the
Bond Guarantee) in the amount of ID271,808/610 and Letter telex call on the performance guarantee for being a drastic
of Guarantee No. 81-195-F11 (Advance Payment Guarantee) in action in contravention of its mutual agreement with the latter
the amount of ID541,608/901, both for a term of eighteen that (1) the imposition of penalty would be held in abeyance
months from 25 May 1981. These letters of guarantee were until the completion of the project; and (2) the time extension
secured by (1) a Deed of Undertaking 12 executed by would be open, depending on the developments on the
respondents VPECI, Spouses Vicente P. Eusebio and Soledad negotiations for a foreign loan to finance the completion of the
C. Eusebio, 3-Plex, and Spouses Eduardo E. Santos and project.23 It also wrote SOB protesting the call for lack of
Iluminada Santos; and (2) a surety bond13 issued by respondent factual or legal basis, since the failure to complete the Project
First Integrated Bonding and Insurance Company, Inc. was due to (1) the Iraqi government's lack of foreign exchange
(FIBICI). The Surety Bond was later amended on 23 June with which to pay its (VPECI's) accomplishments and (2)
1981 to increase the amount of coverage from P6.4 million SOB's noncompliance for the past several years with the
to P6.967 million and to change the bank in whose favor the provision in the contract that 75% of the billings would be
petitioner's guarantee was issued, from Rafidain Bank to Al paid in US dollars.24 Subsequently, or on 19 November 1986,
Ahli Bank of Kuwait.14 respondent VPECI advised the petitioner not to pay yet Al
Ahli Bank because efforts were being exerted for the amicable
On 11 June 1981, SOB and the joint venture VPECI and Ajyal settlement of the Project.25
executed the service contract 15 for the construction of the
Institute of Physical Therapy – Medical Rehabilitation Center, On 14 April 1987, the petitioner received another telex
Phase II, in Baghdad, Iraq, wherein the joint venture message from Al Ahli Bank stating that it had already paid to
contractor undertook to complete the Project within a period Rafidain Bank the sum of US$876,564 under its letter of
of 547 days or 18 months. Under the Contract, the Joint guarantee, and demanding reimbursement by the petitioner of
Venture would supply manpower and materials, and SOB what it paid to the latter bank plus interest thereon and related
would refund to the former 25% of the project cost in Iraqi expenses.26
Dinar and the 75% in US dollars at the exchange rate of 1
Dinar to 3.37777 US Dollars.16 Both petitioner Philguarantee and respondent VPECI sought
the assistance of some government agencies of the Philippines.
The construction, which was supposed to start on 2 June 1981, On 10 August 1987, VPECI requested the Central Bank to
commenced only on the last week of August 1981. Because of hold in abeyance the payment by the petitioner "to allow the
this delay and the slow progress of the construction work due diplomatic machinery to take its course, for otherwise, the
to some setbacks and difficulties, the Project was not Philippine government , through the Philguarantee and the
completed on 15 November 1982 as scheduled. But in October Central Bank, would become instruments of the Iraqi
1982, upon foreseeing the impossibility of meeting the Government in consummating a clear act of injustice and
deadline and upon the request of Al Ahli Bank, the joint inequity committed against a Filipino contractor."27
venture contractor worked for the renewal or extension of the
Performance Bond and Advance Payment Guarantee. On 27 August 1987, the Central Bank authorized the
Petitioner's Letters of Guarantee Nos. 81-194-F (Performance remittance for its account of the amount of US$876,564
Bond) and 81-195-F (Advance Payment Bond) with expiry (equivalent to ID271, 808/610) to Al Ahli Bank representing
date of 25 November 1982 were then renewed or extended to full payment of the performance counter-guarantee for
9 February 1983 and 9 March 1983, respectively.17 The surety VPECI's project in Iraq. 28
bond was also extended for another period of one year, from
12 May 1982 to 12 May 1983.18 The Performance Bond was On 6 November 1987, Philguarantee informed VPECI that it
further extended twelve times with validity of up to 8 would remit US$876,564 to Al Ahli Bank, and reiterated the
December 1986,19 while the Advance Payment Guarantee was joint and solidary obligation of the respondents to reimburse
extended three times more up to 24 May 1984 when the latter the petitioner for the advances made on its counter-
was cancelled after full refund or reimbursement by the joint guarantee.29
venture contractor.20 The surety bond was likewise extended to
8 May 1987.21
The petitioner thus paid the amount of US$876,564 to Al Ahli
Bank of Kuwait on 21 January 1988. 30 Then, on 6 May 1988,
As of March 1986, the status of the Project was 51% the petitioner paid to Al Ahli Bank of Kuwait US$59,129.83
accomplished, meaning the structures were already finished. representing interest and penalty charges demanded by the
The remaining 47% consisted in electro-mechanical works and latter bank.31
the 2%, sanitary works, which both required importation of
equipment and materials.22
On 19 June 1991, the petitioner sent to the respondents an amount collectible from and still being retained by
separate letters demanding full payment of the amount the project owner, which amount can be set-off with
of P47,872,373.98 plus accruing interest, penalty charges, and the sum covered by the performance guarantee.
10% attorney's fees pursuant to their joint and solidary
obligations under the deed of undertaking and surety …
bond.32 When the respondents failed to pay, the petitioner filed
on 9 July 1991 a civil case for collection of a sum of money Fourth, well-apprised of the above conditions
against the respondents before the RTC of Makati City. obtaining at the Project site and cognizant of the war
situation at the time in Iraq, appellant, though earlier
After due trial, the trial court ruled against Philguarantee and has made representations with the SOB regarding a
held that the latter had no valid cause of action against the possible amicable termination of the Project as
respondents. It opined that at the time the call was made on the suggested by VPECI, made a complete turn-around
guarantee which was executed for a specific period, the and insisted on acting in favor of the unjustified
guarantee had already lapsed or expired. There was no valid "call" by the foreign banks.35
renewal or extension of the guarantee for failure of the
petitioner to secure respondents' express consent thereto. The The petitioner then came to this Court via Rule 45 of the Rules
trial court also found that the joint venture contractor incurred of Court claiming that the Court of Appeals erred in affirming
no delay in the execution of the Project. Considering the the trial court's ruling that
Project owner's violations of the contract which rendered
impossible the joint venture contractor's performance of its
undertaking, no valid call on the guarantee could be made. I
Furthermore, the trial court held that no valid notice was first
made by the Project owner SOB to the joint venture contractor …RESPONDENTS ARE NOT LIABLE UNDER
before the call on the guarantee. Accordingly, it dismissed the THE DEED OF UNDERTAKING THEY
complaint, as well as the counterclaims and cross-claim, and EXECUTED IN FAVOR OF PETITIONER IN
ordered the petitioner to pay attorney's fees of P100,000 to CONSIDERATION FOR THE ISSUANCE OF ITS
respondents VPECI and Eusebio Spouses and P100,000 to 3- COUNTER-GUARANTEE AND THAT
Plex and the Santos Spouses, plus costs. 33 PETITIONER CANNOT PASS ON TO
RESPONDENTS WHAT IT HAD PAID UNDER
In its 14 June 1999 Decision, 34 the Court of Appeals affirmed THE SAID COUNTER-GUARANTEE.
the trial court's decision, ratiocinating as follows:
II
First, appellant cannot deny the fact that it was fully
aware of the status of project implementation as well …PETITIONER CANNOT CLAIM
as the problems besetting the contractors, between SUBROGATION.
1982 to 1985, having sent some of its people to
Baghdad during that period. The successive III
renewals/extensions of the guarantees in fact, was
prompted by delays, not solely attributable to the …IT IS INIQUITOUS AND UNJUST FOR
contractors, and such extension understandably PETITIONER TO HOLD RESPONDENTS LIABLE
allowed by the SOB (project owner) which had not UNDER THEIR DEED OF UNDERTAKING.36
anyway complied with its contractual commitment to
tender 75% of payment in US Dollars, and which still
The main issue in this case is whether the petitioner is entitled
retained overdue amounts collectible by VPECI.
to reimbursement of what it paid under Letter of Guarantee
No. 81-194-F it issued to Al Ahli Bank of Kuwait based on the
… deed of undertaking and surety bond from the respondents.
Second, appellant was very much aware of the The petitioner asserts that since the guarantee it issued was
violations committed by the SOB of its contractual absolute, unconditional, and irrevocable the nature and extent
undertakings with VPECI, principally, the payment of its liability are analogous to those of suretyship. Its liability
of foreign currency (US$) for 75% of the total accrued upon the failure of the respondents to finish the
contract price, as well as of the complications and construction of the Institute of Physical Therapy Buildings in
injustice that will result from its payment of the full Baghdad.
amount of the performance guarantee, as evident in
PHILGUARANTEE's letter dated 13 May 1987 ….
By guaranty a person, called the guarantor, binds himself to
the creditor to fulfill the obligation of the principal debtor in
… case the latter should fail to do so. If a person binds himself
solidarily with the principal debtor, the contract is called
Third, appellant was fully aware that SOB was in fact suretyship. 37
still obligated to the Joint Venture and there was still
Strictly speaking, guaranty and surety are nearly related, and Guided by the abovementioned distinctions between a surety
many of the principles are common to both. In both contracts, and a guaranty, as well as the factual milieu of this case, we
there is a promise to answer for the debt or default of another. find that the Court of Appeals and the trial court were correct
However, in this jurisdiction, they may be distinguished thus: in ruling that the petitioner is a guarantor and not a surety.
That the guarantee issued by the petitioner is unconditional
1. A surety is usually bound with his principal by the and irrevocable does not make the petitioner a surety. As a
same instrument executed at the same time and on the guaranty, it is still characterized by its subsidiary and
same consideration. On the other hand, the contract conditional quality because it does not take effect until the
of guaranty is the guarantor's own separate fulfillment of the condition, namely, that the principal obligor
undertaking often supported by a consideration should fail in his obligation at the time and in the form he
separate from that supporting the contract of the bound himself.40 In other words, an unconditional guarantee is
principal; the original contract of his principal is not still subject to the condition that the principal debtor should
his contract. default in his obligation first before resort to the guarantor
could be had. A conditional guaranty, as opposed to an
2. A surety assumes liability as a regular party to the unconditional guaranty, is one which depends upon some
undertaking; while the liability of a guarantor is extraneous event, beyond the mere default of the principal,
conditional depending on the failure of the primary and generally upon notice of the principal's default and
debtor to pay the obligation. reasonable diligence in exhausting proper remedies against the
principal.41
3. The obligation of a surety is primary, while that of
a guarantor is secondary. It appearing that Letter of Guarantee No. 81-194-F merely
stated that in the event of default by respondent VPECI the
petitioner shall pay, the obligation assumed by the petitioner
4. A surety is an original promissor and debtor from was simply that of an unconditional guaranty, not conditional
the beginning, while a guarantor is charged on his guaranty. But as earlier ruled the fact that petitioner's guaranty
own undertaking. is unconditional does not make it a surety. Besides, surety is
never presumed. A party should not be considered a surety
5. A surety is, ordinarily, held to know every default where the contract itself stipulates that he is acting only as a
of his principal; whereas a guarantor is not bound to guarantor. It is only when the guarantor binds himself
take notice of the non-performance of his principal. solidarily with the principal debtor that the contract becomes
one of suretyship.42
6. Usually, a surety will not be discharged either by
the mere indulgence of the creditor to the principal or Having determined petitioner's liability as guarantor, the next
by want of notice of the default of the principal, no question we have to grapple with is whether the respondent
matter how much he may be injured thereby. A contractor has defaulted in its obligations that would justify
guarantor is often discharged by the mere indulgence resort to the guaranty. This is a mixed question of fact and law
of the creditor to the principal, and is usually not that is better addressed by the lower courts, since this Court is
liable unless notified of the default of the principal. 38 not a trier of facts.
In determining petitioner's status, it is necessary to read Letter It is a fundamental and settled rule that the findings of fact of
of Guarantee No. 81-194-F, which provides in part as follows: the trial court and the Court of Appeals are binding or
conclusive upon this Court unless they are not supported by
In consideration of your issuing the above the evidence or unless strong and cogent reasons dictate
performance guarantee/counter-guarantee, we hereby otherwise.43 The factual findings of the Court of Appeals are
unconditionally and irrevocably guarantee, under our normally not reviewable by us under Rule 45 of the Rules of
Ref. No. LG-81-194 F to pay you on your first Court except when they are at variance with those of the trial
written or telex demand Iraq Dinars Two Hundred court. 44 The trial court and the Court of Appeals were in
Seventy One Thousand Eight Hundred Eight and fils unison that the respondent contractor cannot be considered to
six hundred ten (ID271,808/610) representing 100% have defaulted in its obligations because the cause of the delay
of the performance bond required of V.P. EUSEBIO was not primarily attributable to it.
for the construction of the Physical Therapy Institute,
Phase II, Baghdad, Iraq, plus interest and other A corollary issue is what law should be applied in determining
incidental expenses related thereto. whether the respondent contractor has defaulted in the
performance of its obligations under the service contract. The
In the event of default by V.P. EUSEBIO, we shall question of whether there is a breach of an agreement, which
pay you 100% of the obligation unpaid but in no includes default or mora,45 pertains to the essential or intrinsic
case shall such amount exceed Iraq Dinars (ID) validity of a contract. 46
271,808/610 plus interest and other incidental
expenses…. (Emphasis supplied)39 No conflicts rule on essential validity of contracts is expressly
provided for in our laws. The rule followed by most legal
systems, however, is that the intrinsic validity of a contract
must be governed by the lex contractus or "proper law of the payment by SOB purely in Dinars adversely affected the
contract." This is the law voluntarily agreed upon by the completion of the project; thus:
parties (the lex loci voluntatis) or the law intended by them
either expressly or implicitly (the lex loci intentionis). The law 4. Despite protests from the plaintiff, SOB continued
selected may be implied from such factors as substantial paying the accomplishment billings of the Contractor
connection with the transaction, or the nationality or domicile purely in Iraqi Dinars and which payment came only
of the parties.47 Philippine courts would do well to adopt the after some delays.
first and most basic rule in most legal systems, namely, to
allow the parties to select the law applicable to their contract, 5. SOB is fully aware of the following:
subject to the limitation that it is not against the law, morals,
or public policy of the forum and that the chosen law must
bear a substantive relationship to the transaction. 48 …
It must be noted that the service contract between SOB and 5.2 That Plaintiff is a foreign contractor in Iraq and as
VPECI contains no express choice of the law that would such, would need foreign currency (US$), to finance
govern it. In the United States and Europe, the two rules that the purchase of various equipment, materials,
now seem to have emerged as "kings of the hill" are (1) the supplies, tools and to pay for the cost of project
parties may choose the governing law; and (2) in the absence management, supervision and skilled labor not
of such a choice, the applicable law is that of the State that available in Iraq and therefore have to be imported
"has the most significant relationship to the transaction and the and or obtained from the Philippines and other
parties."49 Another authority proposed that all matters relating sources outside Iraq.
to the time, place, and manner of performance and valid
excuses for non-performance are determined by the law of the 5.3 That the Ministry of Labor and Employment of
place of performance or lex loci solutionis, which is useful the Philippines requires the remittance into the
because it is undoubtedly always connected to the contract in a Philippines of 70% of the salaries of Filipino workers
significant way.50 working abroad in US Dollars;
Our law, specifically Article 1169, last paragraph, of the Civil 5.7 That the government of Iraq prohibits the
Code, provides: "In reciprocal obligations, neither party incurs bringing of local currency (Iraqui Dinars) out of Iraq
in delay if the other party does not comply or is not ready to and hence, imported materials, equipment, etc.,
comply in a proper manner with what is incumbent upon him." cannot be purchased or obtained using Iraqui Dinars
as medium of acquisition.
Default or mora on the part of the debtor is the delay in the
fulfillment of the prestation by reason of a cause imputable to …
the former. 52 It is the non-fulfillment of an obligation with
respect to time.53
8. Following the approved construction program of
the CONTRACT, upon completion of the civil works
It is undisputed that only 51.7% of the total work had been portion of the installation of equipment for the
accomplished. The 48.3% unfinished portion consisted in the building, should immediately follow, however, the
purchase and installation of electro-mechanical equipment and CONTRACT specified that these equipment which
materials, which were available from foreign suppliers, thus are to be installed and to form part of the PROJECT
requiring US Dollars for their importation. The monthly have to be procured outside Iraq since these are not
billings and payments made by SOB 54 reveal that the being locally manufactured. Copy f the relevant
agreement between the parties was a periodic payment by the portion of the Technical Specification is hereto
Project owner to the contractor depending on the percentage of attached as Annex "C" and made an integral part
accomplishment within the period. 55 The payments were, in hereof;
turn, to be used by the contractor to finance the subsequent
phase of the work. 56 However, as explained by VPECI in its
…
letter to the Department of Foreign Affairs (DFA), the
10. Due to the lack of Foreign currency in Iraq for VPECI has taken every possible measure for the
this purpose, and if only to assist the Iraqi completion of the project but the war situation in Iraq
government in completing the PROJECT, the particularly the lack of foreign exchange is proving to
Contractor without any obligation on its part to do so be a great obstacle. Our performance
but with the knowledge and consent of SOB and the counterguarantee was called last 26 October 1986
Ministry of Housing & Construction of Iraq, offered when the negotiations for a foreign currency loan
to arrange on behalf of SOB, a foreign currency loan, with the Italian government through Banco de Roma
through the facilities of Circle International S.A., the bogged down following news report that Iraq has
Contractor's Sub-contractor and SACE MEDIO defaulted in its obligation with major European
CREDITO which will act as the guarantor for this banks. Unless the situation in Iraq is improved as to
foreign currency loan. allay the bank's apprehension, there is no assurance
that the project will ever be completed. 58
Arrangements were first made with Banco di Roma.
Negotiation started in June 1985. SOB is informed of In order that the debtor may be in default it is necessary that
the developments of this negotiation, attached is a the following requisites be present: (1) that the obligation be
copy of the draft of the loan Agreement between demandable and already liquidated; (2) that the debtor delays
SOB as the Borrower and Agent. The Several Banks, performance; and (3) that the creditor requires the
as Lender, and counter-guaranteed by Istituto performance because it must appear that the tolerance or
Centrale Per II Credito A Medio Termine benevolence of the creditor must have ended. 59
(Mediocredito) Sezione Speciale Per L'Assicurazione
Del Credito All'Exportazione (Sace). Negotiations As stated earlier, SOB cannot yet demand complete
went on and continued until it suddenly collapsed due performance from VPECI because it has not yet itself
to the reported default by Iraq in the payment of its performed its obligation in a proper manner, particularly the
obligations with Italian government, copy of the payment of the 75% of the cost of the Project in US Dollars.
news clipping dated June 18, 1986 is hereto attached The VPECI cannot yet be said to have incurred in delay. Even
as Annex "D" to form an integral part hereof; assuming that there was delay and that the delay was
attributable to VPECI, still the effects of that delay ceased
15. On September 15, 1986, Contractor received upon the renunciation by the creditor, SOB, which could be
information from Circle International S.A. that implied when the latter granted several extensions of time to
because of the news report that Iraq defaulted in its the former. 60 Besides, no demand has yet been made by SOB
obligations with European banks, the approval by against the respondent contractor. Demand is generally
Banco di Roma of the loan to SOB shall be deferred necessary even if a period has been fixed in the obligation.
indefinitely, a copy of the letter of Circle And default generally begins from the moment the creditor
International together with the news clippings are demands judicially or extra-judicially the performance of the
hereto attached as Annexes "F" and "F-1", obligation. Without such demand, the effects of default will
respectively.57 not arise.61
As found by both the Court of Appeals and the trial court, the Moreover, the petitioner as a guarantor is entitled to the
delay or the non-completion of the Project was caused by benefit of excussion, that is, it cannot be compelled to pay the
factors not imputable to the respondent contractor. It was creditor SOB unless the property of the debtor VPECI has
rather due mainly to the persistent violations by SOB of the been exhausted and all legal remedies against the said debtor
terms and conditions of the contract, particularly its failure to have been resorted to by the creditor. 62 It could also set up
pay 75% of the accomplished work in US Dollars. Indeed, compensation as regards what the creditor SOB may owe the
where one of the parties to a contract does not perform in a principal debtor VPECI.63 In this case, however, the petitioner
proper manner the prestation which he is bound to perform has clearly waived these rights and remedies by making the
under the contract, he is not entitled to demand the payment of an obligation that was yet to be shown to be
performance of the other party. A party does not incur in delay rightfully due the creditor and demandable of the principal
if the other party fails to perform the obligation incumbent debtor.
upon him.
As found by the Court of Appeals, the petitioner fully knew
The petitioner, however, maintains that the payments by SOB that the joint venture contractor had collectibles from SOB
of the monthly billings in purely Iraqi Dinars did not render which could be set off with the amount covered by the
impossible the performance of the Project by VPECI. Such performance guarantee. In February 1987, the OMEAA
posture is quite contrary to its previous representations. In his transmitted to the petitioner a copy of a telex dated 10
26 March 1987 letter to the Office of the Middle Eastern and February 1987 of the Philippine Ambassador in Baghdad,
African Affairs (OMEAA), DFA, Manila, petitioner's Iraq, informing it of the note verbale sent by the Iraqi Ministry
Executive Vice-President Jesus M. Tañedo stated that while of Foreign Affairs stating that the past due obligations of the
VPECI had taken every possible measure to complete the joint venture contractor from the petitioner would "be
Project, the war situation in Iraq, particularly the lack of deducted from the dues of the two contractors."64
foreign exchange, was proving to be a great obstacle; thus:
Also, in the project situationer attached to the letter to the This brings us to the next question: May the petitioner as a
OMEAA dated 26 March 1987, the petitioner raised as among guarantor secure reimbursement from the respondents for what
the arguments to be presented in support of the cancellation of it has paid under Letter of Guarantee No. 81-194-F?
the counter-guarantee the fact that the amount of
ID281,414/066 retained by SOB from the Project was more As a rule, a guarantor who pays for a debtor should be
than enough to cover the counter-guarantee of ID271,808/610; indemnified by the latter 67 and would be legally subrogated to
thus: the rights which the creditor has against the debtor. 68 However,
a person who makes payment without the knowledge or
6.1 Present the following arguments in cancelling the against the will of the debtor has the right to recover only
counterguarantee: insofar as the payment has been beneficial to the debtor. 69 If
the obligation was subject to defenses on the part of the
· The Iraqi Government does not have the debtor, the same defenses which could have been set up
foreign exchange to fulfill its contractual against the creditor can be set up against the paying
obligations of paying 75% of progress guarantor.70
billings in US dollars.
From the findings of the Court of Appeals and the trial court,
… it is clear that the payment made by the petitioner guarantor
did not in any way benefit the principal debtor, given the
· It could also be argued that the amount of project status and the conditions obtaining at the Project site at
ID281,414/066 retained by SOB from the that time. Moreover, the respondent contractor was found to
proposed project is more than the amount of have valid defenses against SOB, which are fully supported by
the outstanding counterguarantee.65 evidence and which have been meritoriously set up against the
paying guarantor, the petitioner in this case. And even if the
deed of undertaking and the surety bond secured petitioner's
In a nutshell, since the petitioner was aware of the contractor's guaranty, the petitioner is precluded from enforcing the same
outstanding receivables from SOB, it should have set up by reason of the petitioner's undue payment on the guaranty.
compensation as was proposed in its project situationer. Rights under the deed of undertaking and the surety bond do
not arise because these contracts depend on the validity of the
Moreover, the petitioner was very much aware of the enforcement of the guaranty.
predicament of the respondents. In fact, in its 13 May 1987
letter to the OMEAA, DFA, Manila, it stated: The petitioner guarantor should have waited for the natural
course of guaranty: the debtor VPECI should have, in the first
VPECI also maintains that the delay in the place, defaulted in its obligation and that the creditor SOB
completion of the project was mainly due to SOB's should have first made a demand from the principal debtor. It
violation of contract terms and as such, call on the is only when the debtor does not or cannot pay, in whole or in
guarantee has no basis. part, that the guarantor should pay. 71 When the petitioner
guarantor in this case paid against the will of the debtor
While PHILGUARANTEE is prepared to honor its VPECI, the debtor VPECI may set up against it defenses
commitment under the guarantee, available against the creditor SOB at the time of payment.
PHILGUARANTEE does not want to be an This is the hard lesson that the petitioner must learn.
instrument in any case of inequity committed against
a Filipino contractor. It is for this reason that we are As the government arm in pursuing its objective of providing
constrained to seek your assistance not only in "the necessary support and assistance in order to enable …
ascertaining the veracity of Al Ahli Bank's claim that [Filipino exporters and contractors to operate viably under the
it has paid Rafidain Bank but possibly averting such prevailing economic and business conditions,"72 the petitioner
an event. As any payment effected by the banks will should have exercised prudence and caution under the
complicate matters, we cannot help underscore the circumstances. As aptly put by the Court of Appeals, it would
urgency of VPECI's bid for government intervention be the height of inequity to allow the petitioner to pass on its
for the amicable termination of the contract and losses to the Filipino contractor VPECI which had sternly
release of the performance guarantee. 66 warned against paying the Al Ahli Bank and constantly
apprised it of the developments in the Project implementation.
But surprisingly, though fully cognizant of SOB's violations of
the service contract and VPECI's outstanding receivables from WHEREFORE, the petition for review on certiorari is
SOB, as well as the situation obtaining in the Project site hereby DENIED for lack of merit, and the decision of the
compounded by the Iran-Iraq war, the petitioner opted to pay Court of appeals in CA-G.R. CV No. 39302 is AFFIRMED.
the second layer guarantor not only the full amount of the
performance bond counter-guarantee but also interests and No pronouncement as to costs.
penalty charges.
SO ORDERED.
FIRST DIVISION
DECISION
KAPUNAN, J.:
The Fontanillas were not booked on the next flight, which No pronouncement as to costs.
departed for San Francisco at 11:00 am It was only at 12:00
noon that they were able to leave Los Angeles on United SO ORDERED. 16
Airlines Flight No. 803.
Petitioner United Airlines now comes to this Court raising the
Petitioner United Airlines has a different version of what following assignment of errors:chanrob1es virtual 1aw library
occurred at the Los Angeles Airport on May 5, 1989.
I
According to United Airlines, the Fontanillas did not initially
go to the check-in counter to get their seat assignments for UA
Flight 1108. They instead proceeded to join the queue RESPONDENT COURT OF APPEALS GRAVELY ERRED
boarding the aircraft without first securing their seat IN RULING THAT THE TRIAL COURT WAS WRONG IN
assignments as required in their ticket and boarding passes. FAILING TO CONSIDER THE ALLEGED ADMISSION
Having no seat assignments, the stewardess at the door of the THAT PRIVATE RESPONDENT OBSERVED THE
plane instructed them to go to the check-in counter. When the CHECK-IN REQUIREMENT.
Fontanillas proceeded to the check-in counter, Linda Allen,
the United Airlines Customer Representative at the counter II
informed them that the flight was overbooked. She booked
them on the next available flight and offered them denied
RESPONDENT COURT OF APPEALS GRAVELY ERRED The rule authorizing an answer that the defendant has no
IN RULING THAT PRIVATE RESPONDENT’S FAILURE knowledge or information sufficient to form a belief as to the
TO CHECK-IN WILL NOT DEFEAT HIS CLAIMS truth of an averment and giving such answer the effect of a
BECAUSE THE DENIED BOARDING RULES WERE NOT denial, does not apply where the fact as to which want of
COMPLIED WITH knowledge is asserted is so plainly and necessarily within the
defendant’s knowledge that his averment of ignorance must be
III palpably untrue. 22 Whether or not private respondents
checked in at petitioner’s designated counter at the airport at
9:45 a.m. on May 5, 1989 must necessarily be within
RESPONDENT COURT OF APPEALS GRAVELY ERRED petitioner’s knowledge.
IN RULING THAT PRIVATE RESPONDENT IS
ENTITLED TO MORAL DAMAGES OF P200, 000. While there was no specific denial as to the fact of compliance
with the "check-in" requirement by private respondents,
IV petitioner presented evidence to support its contention that
there indeed was no compliance.
RESPONDENT COURT OF APPEALS GRAVELY ERRED Private respondents then are said to have waived the rule on
IN RULING THAT PRIVATE RESPONDENT IS admission. It not only presented evidence to support its
ENTITLED TO EXEMPLARY DAMAGES OF P200, 000. contention that there was compliance with the check-in
requirement even allowed petitioner to present rebuttal
evidence. In the case of Yu Chuck v. "Kong Li Po," we ruled
V
that:chanrob1es virtual 1aw library
Aniceto Fontanilla’s assertion that upon arrival at the airport at The law of the forum on the subject matter is Economic
9:45 a.m., he immediately proceeded to the check-in counter, Regulations No. 7 as amended by Boarding Priority and
and that Linda Allen punched in something into the computer Denied Boarding Compensation of the Civil Aeronautics
is specious and not supported by the evidence on record. In Board, which provides that the check-in requirement be
support of their allegations, private respondents submitted a complied with before a passenger may claim against a carrier
copy of the boarding pass. Explicitly printed on the boarding for being denied boarding:chanrob1es virtual 1aw library
pass are the words "Check-In Required." Curiously, the said
pass did not indicate any seat number. If indeed the SECTION 5. Amount of Denied Boarding Compensation —
Fontanillas checked in at the designated time as they claimed, Subject to the exceptions provided hereinafter under Section 6,
why then were they not assigned seat numbers? Absent any carriers shall pay to passengers holding confirmed reserved
showing that Linda was so motivated, we do not buy into space and who have presented themselves at the proper place
private respondents’ claim that Linda intentionally deceived and time and fully complied with the carrier’s check-in and
him, and made him the laughing stock among the passengers. reconfirmation procedures and who are acceptable for carriage
28 Hence, as correctly observed by the trial court:chanrob1es under the Carrier’s tariffs but who have been denied boarding
virtual 1aw library for lack of space, a compensation at the rate of: . .
Plaintiffs fail to realize that their failure to check in, as Private respondents’ narration that they were subjected to
expressly required in their boarding passes, is the very reason harsh and derogatory remarks seems incredulous. However,
why they were not given their respective seat numbers, which this Court will not attempt to surmise what really happened.
resulted in their being denied boarding. 29 Suffice to say, private respondent was not able to prove his
cause of action, for as the trial court correctly
Neither do we agree with the conclusion reached by the observed:chanrob1es virtual 1aw library
appellate court that private respondents’ failure to comply
with the check-in requirement will not defeat his claim as the . . . plaintiffs claim to have been discriminated against and
denied boarding rules were not complied with. Notably, the insulted in the presence of several people. Unfortunately
appellate court relied on the Code of Federal Regulation Part plaintiffs limited their evidence to the testimony [of] Aniceto
on Oversales, which states:chanrob1es virtua1 1aw 1ibrary Fontanilla, without any corroboration by the people who saw
or heard the discriminatory remarks and insults; while such
250.6 Exceptions to eligibility for denied boarding limited testimony could possibly be true, it does not enable the
compensation. Court to reach the conclusion that plaintiffs have, by a
preponderance of evidence, proven that they are entitled to
A passenger denied board involuntarily from an oversold P1,650,000.00 damages from defendant. 31
flight shall not be eligible for denied board compensation
if:chanrob1es virtual 1aw library As to the award of moral and exemplary damages, we find
error in the award of such by the Court of Appeals. For the
(a) The passenger does not comply with the carrier’s contract plaintiff to be entitled to an award of moral damages arising
of carriage or tariff provisions regarding ticketing, from a breach of contract of carriage, the carrier must have
reconfirmation, check-in, and acceptability for transformation. acted with fraud or bad faith. The appellate court predicated its
award on our pronouncement in the case of Zalamea v. Court
The appellate court, however, erred in applying the laws of the of Appeals, supra, where we stated:chanrob1es virtual 1aw
United States as, in the case at bar, Philippine law is the library
applicable law. Although, the contract of carriage was to be
performed in the United States, the tickets were purchased Existing jurisprudence explicitly states that overbooking
through petitioner’s agent in Manila. It is true that the tickets amounts to bad faith, entitling passengers concerned to an
were "rewritten" in Washington, D.C. However, such fact did award of moral damages. In Alitalia Airways v. Court of
not change the nature of the original contract of carriage Appeals, where passengers with confirmed booking were
entered into by the parties in Manila. refused carriage on the last minute, this Court held that when
an airline issues a ticket to a passenger confirmed on a
In the case of Zalamea v. Court of Appeals, 30 this Court particular flight, on a certain date, a contract of carriage arises,
applied the doctrine of lex loci contractus. According to the and the passenger has every right to expect that he would fly
doctrine, as a general rule, the law of the place where a on that flight and on that date. If he does not, then the carrier
contract is made or entered into governs with respect to its opens itself to a suit for breach of contract of carriage. Where
nature and validity, obligation and interpretation. This has an airline had deliberately overbooked, it took the risk of
been said to be the rule even though the place where the having to deprive some passengers of their seats in case all of
contract was made is different from the place where it is to be them would show up for check in. For the indignity and
performed, and particularly so, if the place of the making and inconvenience of being refused a confirmed seat on the last
the place of performance are the same. Hence, the court minute, said passenger is entitled to moral damages.
should apply the law of the place where the airline ticket was (Emphasis supplied.)
However, the Court’s ruling in said case should be read in
consonance with existing laws, particularly, Economic
Regulations No. 7, as amended, of the Civil Aeronautics
Board:chanrob1es virtual 1aw library
The Facts
Defendants are also directed to pay Plaintiffs actual expenses C. The Honorable Court erred in not holding that the Petition
in the amount of P20,000 and attorneys fees of P20,000 for Certiorari was time barred
including costs of this suit.
D. The Honorable Court of Appeals erred in holding that the
xxx proceedings in the lower court are null and void due to invalid
and defective service of summons and the court did not
On January 5, 2000, [respondent] Helen Boyon, who was then acquire jurisdiction over the person of the
residing in the United States of America, was surprised to respondents.6cräläwvirtualibräry
learn from her sister Elizabeth Boyon, of the resolution issued
by the respondent court. On January 18, 2000, [respondents] In sum, the main issue revolves around the validity of the
filed an Ad Cautelam motion questioning, among others, the service of summons on respondents.
validity of the service of summons effected by the court a
quo. On March 17, 2000, the public respondent issued an The Courts Ruling
Order denying the said motion on the basis of the defaulted
[respondents] supposed loss of standing in court. On March The Petition has no merit.
29, 2000, the [respondents] once again raised the issue of
jurisdiction of the trial court via a motion for reconsideration.
Main Issue:
On June 22, 2000, however, an Order was issued by the public
respondent denying the said motion. The [petitioners] moved
for the execution of the controverted judgment which the Validity of the Service of Summons
respondent judge ultimately granted.4cräläwvirtualibräry
Petitioners aver that the CA erred in ruling that the service of
Thereafter, respondents filed before the CA a Petition for summons on respondents was invalid. They submit that
certiorari under Rule 65 of the Revised Rules of Civil although the case filed before the trial court was denominated
Procedure, questioning the jurisdiction of the regional trial as an action for specific performance, it was actually an
court (RTC). action quasi in rem, because it involved a piece of real
property located in the Philippines. They further argue that in
actions quasi in rem involving ownership of a parcel of land,
Ruling of the Court of Appeals
it is sufficient that the trial court acquire jurisdiction over
the res. Thus, the summons by publication, which they
The CA held that the trial court had no authority to issue the effected subsequent to the substituted service of summons,
questioned Resolution and Orders. According to the appellate was allegedly sufficient.
court, the RTC never acquired jurisdiction over respondents
because of the invalid service of summons upon them. First,
On the other hand, respondents maintain that the proceedings
the sheriff failed to comply with the requirements of
in the trial court were null and void because of the invalid and
defective service of summons. According to them, the Return must (a) indicate the impossibility of service of summons
of Summons issued by the process server of the RTC failed to within a reasonable time; (b) specify the efforts exerted to
state that he had exerted earnest efforts to effect the service of locate the defendant; and (c) state that the summons was
summons. He allegedly tried to serve it personally on them served upon a person of sufficient age and discretion who is
on July 22, 1998 at No. 32 Ariza Drive, Camella Homes, residing in the address, or who is in charge of the office or
Alabang. He, however, resorted to substituted service on that regular place of business, of the defendant. 7 It is likewise
same day, supposedly because he could not find respondents required that the pertinent facts proving these circumstances
in the above address. They further allege that the person to be stated in the proof of service or in the officers return. The
whom he gave the summons was not even a resident of that failure to comply faithfully, strictly and fully with all the
address. foregoing requirements of substituted service renders the
service of summons ineffective.8
Respondents contend that when summons is served by
substituted service, the return must show that it was Defective Personal
impossible to serve the summons personally, and that efforts Service of Summons
had been exerted toward that end. They add that
noncompliance with the rule on substituted service renders In the instant case, it appears that the process server hastily
invalid all proceedings relative thereto. and capriciously resorted to substituted service of summons
without actually exerting any genuine effort to locate
As to the summons by publication subsequently effected by respondents. A review of the records 9 reveals that the only
petitioners, respondents argue that the case filed before the effort he exerted was to go to No. 32 Ariza Drive, Camella
trial court was an action for specific performance and, Homes, Alabang on July 22, 1998, to try to serve the
therefore, an action in personam. As such, the summons by summons personally on respondents. While the Return of
publication was insufficient to enable the trial court to acquire Summons states that efforts to do so were ineffectual and
jurisdiction over the persons of respondents. unavailing because Helen Boyon was in the United States and
Romeo Boyon was in Bicol, it did not mention exactly what
Respondents conclude that even granting that the service of efforts -- if any -- were undertaken to find respondents.
summons by publication was permissible under the Furthermore, it did not specify where or from whom the
circumstances, it would still be defective and invalid because process server obtained the information on their whereabouts.
of the failure of petitioners to observe the requirements of law, The pertinent portion of the Return of Summons is reproduced
like an Affidavit attesting that the latter deposited in the post as follows:
office a copy of the summons and of the order of publication,
paid the postage, and sent the documents by registered mail to That efforts to serve the said Summons personally upon
the formers last known address. defendants Sps. Helen and Romeo Boyon were made but the
same were ineffectual and unavailing for the reason that
We agree with respondents. In general, trial courts acquire defendant Helen Boyon is somewhere in the United States of
jurisdiction over the person of the defendant by the service of America and defendant Romeo Boyon is in Bicol thus
summons. Where the action is in personam and the defendant substituted service was made in accordance with Section 7,
is in the Philippines, such service may be done by personal or Rule 14, of the Revised Rules of Court.10cräläwvirtualibräry
substituted service, following the procedures laid out in
Sections 6 and 7 of Rule 14 of the Revised Rules of Court, The Return of Summons shows that no effort was actually
which read: exerted and no positive step taken by either the process server
or petitioners to locate and serve the summons personally on
Section 6. Service in person on defendant. - Whenever respondents. At best, the Return merely states the alleged
practicable, the summons shall be served by handing a copy whereabouts of respondents without indicating that such
thereof to the defendant in person, or, if he refuses to receive information was verified from a person who had knowledge
and sign for it, by tendering it to him. thereof. Certainly, without specifying the details of the
attendant circumstances or of the efforts exerted to serve the
Section 7. Substituted service. - If, for justifiable causes, the summons, a general statement that such efforts were made will
defendant cannot be served within a reasonable time as not suffice for purposes of complying with the rules of
provided in the preceding section, service may be effected (a) substituted service of summons.
by leaving copies of the summons at the defendant's residence
with some person of suitable age and discretion then residing The necessity of stating in the process servers Return or Proof
therein, or (b) by leaving the copies at defendants office or of Service the material facts and circumstances sustaining the
regular place of business with some competent person in validity of substituted service was explained by this Court
charge thereof. in Hamilton v. Levy,11 from which we quote:
As can be gleaned from the above-quoted Sections, personal x x x The pertinent facts and circumstances attendant to the
service of summons is preferred to substituted service. Only if service of summons must be stated in the proof of service or
the former cannot be made promptly can the process server Officers Return; otherwise, any substituted service made in
resort to the latter. Moreover, the proof of service of summons lieu of personal service cannot be upheld. This is necessary
because substituted service is in derogation of the usual
method of service. It is a method extraordinary in character
and hence may be used only as prescribed and in the
circumstances authorized by statute. Here, no such explanation
was made. Failure to faithfully, strictly, and fully comply with
the requirements of substituted service renders said service
ineffective.12cräläwvirtualibräry
In the instant case, what was filed before the trial court was an GRIÑO-AQUINO, J.:
action for specific performance directed against respondents.
While the suit incidentally involved a piece of land, the The petitioners are foreign corporations organized and existing
ownership or possession thereof was not put in issue, since under the laws of the United States, the United Kingdom, and
they did not assert any interest or right over it. Moreover, this Malaysia, are not domiciled in the Philippines, nor do they
Court has consistently declared that an action for specific have officers or agents, place of business, or property in the
performance is an action in personam.16cräläwvirtualibräry Philippines; they are not licensed to engage, and are not
engaged, in business here. The respondent Imperial Vegetable
Having failed to serve the summons on respondents properly, Oil Company, Inc. (or "IVO" for brevity) is a Philippine
the RTC did not validly acquire jurisdiction over their persons. corporation which through its president, Dominador
Consequently, due process demands that all the proceedings Monteverde, had entered into several contracts for the delivery
conducted subsequent thereto should be deemed null and of coconut oil to the petitioners. Those contracts stipulate that
void.17cräläwvirtualibräry any dispute between the parties will be settled through
arbitration under the rules of either the Federation of Oils
WHEREFORE, the Petition is DENIED and the assailed Seeds and Fats Association (FOSFA) or the National Institute
Decision and Resolution AFFIRMED. Costs against of Oil Seed Products (NIOP). Because IVO defaulted under
petitioners. the contracts, the petitioners and 15 others, initiated arbitration
proceedings abroad, and some have already obtained
arbitration awards against IVO.
SO ORDERED.
On April 8, 1987, IVO filed a complaint for injunction and
damages against nineteen (19) foreign coconut oil buyers
including the petitioners, with whom its president, Dominador
Monteverde, had entered into contracts for the delivery of
coconut oil (Civil Case No. 87-40166, RTC Manila entitled not found in the Philippines and the action
"Imperial Vegetable Oil Co., Inc. vs. Dial Corporation et al."). affects the personal status of the plaintiff or
IVO repudiated Monteverde's contracts on the grounds that relates to, or the subject of which is,
they were mere "paper trading in futures" as no actual delivery property within the Philippines, in which the
of the coconut oil was allegedly intended by the parties; that defendant has or claims a lien or interest,
the Board of Directors of IVO convened in a special meeting actual or contingent, or in which the relief
on March 21, 1987 and removed Dominador Monteverde from demanded consists, wholly or in part, in
his position as president of the corporation, named in his excluding the defendant from any interest
place, Rodrigo Monteverde, and disowned Dominador therein, or the property of the defendant has
Monteverde's allegedly illegal and unauthorized acts; that the been attached within the Philippines, service
defendants have allegedly "harassed" IVO to comply with may, by leave of court, be effected out of the
Dominador's contracts and to come to a settlement with them. Philippines by personal service as under
IVO prayed for the issuance of a temporary restraining order section 7; or by publication in a newspaper
or writ of preliminary injunction to stop the defendants from of general circulation in such places and for
harassing IVO with their insistent demands to recognize the such time as the court may order, in which
contracts entered into by Dominador Monteverde and from case a copy of the summons and order of the
portraying the IVO as one that defaults on its contracts and court shall be sent by registered mail to the
obligations and has fallen into bad times and from interfering last known address of the defendant, or in
with IVO's normal conduct of business. IVO also prayed that any other manner the court may deem
the defendants pay it moral damages of P5 million, actual sufficient. Any order granting such leave
damages of P10 million, exemplary damages of P5 million, shall specify a reasonable time, which shag
attorney's fees of P1 million, P3,000 per appearance of not be less than sixty (60) days after notice,
counsel, and litigation expenses. within which the defendant must answer.
On motion of IVO, respondent Judge authorized it to effect Only in four (4) instances is extraterritorial service of
extraterritorial service of summons to all the defendants summons proper, namely: "(1) when the action affects the
through DHL Philippines corporation (Annex B). Pursuant to personal status of the plaintiffs; (2) when the action relates to,
that order, the petitioners were served with summons and copy or the subject of which is, property within the Philippines, in
of the complaint by DHL courier service. which the defendant has or claims a lien or interest, actual or
contingent; (3) when the relief demanded in such action
On April 25, 1987, without submitting to the court's consists, wholly or in part, in excluding the defendant from
jurisdiction and only for the purpose of objecting to said any interest in property located in the Philippines; and (4)
jurisdiction over their persons, the petitioners filed motions to when the defendant non-resident's property has been attached
dismiss the complaint against them on the ground that the within the Philippines" (De Midgely vs. Fernandos, 64 SCRA
extraterritorial service of summons to them was improper and 23).
that hence the court did not acquire jurisdiction over them. On
December 15, 1987, the court denied their motions to dismiss The complaint in this case does not involve the personal status
and upheld the validity of the extraterritorial service of of the plaintiff, nor any property in the Philippines in which
summons to them on the ground that "the present action the defendants have or claim an interest, or which the plaintiff
relates to property rights which lie in contracts within the has attached. The action is purely an action for injunction to
Philippines, or which defendants claim liens or interests, restrain the defendants from enforcing against IVO ("abusing
actual or inchoate, legal or equitable (par. 2, complaint). And and harassing") its contracts for the delivery of coconut oil to
one of the reliefs demanded consists, wholly or in part, in the defendants, and to recover from the defendants P21
excluding the defendants from any interest in such property million in damages for such "harassment." It is clearly a
for the reason that their transactions with plaintiff's former personal action as well as an action in personam, not an action
president are ultra vires." Furthermore, "as foreign in rem or quasi in rem. "An action in personam is an action
corporations doing business in the Philippines without a against a person on the basis of his personal liability, while
license, they opened themselves to suit before Philippine an action in remedies is an action against the thing itself,
courts, pursuant to Sec. 133 of the Corporation Code of the instead of against the person." (Hernandez vs. Rural Bank of
Philippines." (Annex H) The petitioners' motions for Lucena, Inc., 76 SCRA 85). A personal action is one brought
reconsideration of that order were also denied by the court for the recovery of personal property, for the enforcement of
(Annex M), hence this petition for certiorari with a prayer for some contract or recovery of damages for its breach, or for the
the issuance of a temporary retraining order which We recovery of damages for the commission of an injury to the
granted. person or property (Hernandez vs. Development Bank of the
Philippines, 71 SCRA 292).<äre||anº•1àw>
The petition is meritorious.
As Civil Case No. 87-40166 is a personal action, personal or
Section 17, Rule 14 of the Rules of Court provides: substituted service of summons on the defendants, not
extraterritorial service, is necessary to confer jurisdiction on
Section 17. Extraterritorial service. — the court. The rule is explained in Moran's Comments on the
When the defendant does not reside and is Rules of Court thus:
As a general rule, when the defendant is not The respondent court's finding that, by filing motions to
residing and is not found in the Philippines, dismiss, the petitioners hypothetically admitted the allegations
the Philippine courts cannot try any case of the complaint that they are doing business in the Philippines
against him because of the impossibility of without any license, and that they may be served with
acquiring jurisdiction over his person unless summons and other court processes through their agents or
he voluntarily appears in court. But, when representatives enumerated in paragraph 2 of the complaint, is
the action affects the personal status of the contradicted by its order authorizing IVO to summon them by
plaintiff residing in the Philippines, or is extraterritorial service, a mode of service which is resorted to
intended to seize or dispose of any property, when the defendant is not found in the Philippines, does not
real or personal, of the defendant located in transact business here, and has no resident agent on whom the
the Philippines, it may be validly tried by summons may be served.
the Philippine courts, for then, they have
jurisdiction over the res, i.e., the personal WHEREFORE, We hold that the extraterritorial service of
status of the plaintiff or the property of the summons on the petitioners was improper, hence null and
defendant and their jurisdiction over the void. The petition for certiorari is granted.The orders dated
person of the non-resident defendant is not April 24, 1987 (Annex B) and December 15, 1987 (Annex H)
essential. Venue in such cases may be laid in of the respondent Judge are hereby set aside. The complaint in
the province where the property of the Civil Case No. 87-40166 is hereby dismissed as against the
defendant or a part thereof involved in the petitioners for failure of the court to acquire jurisdiction over
litigation is located. (5 Moran's Comments them.
on the Rules of Court, 2nd Ed., p. 105.)
FIRST DIVISION
In an action for injunction, extraterritorial service of summons
and complaint upon the non-resident defendants cannot G.R. No. L-68741 January 28, 1988
subject them to the processes of the regional trial courts which
are powerless to reach them outside the region over which
they exercise their authority (Sec. 3-a, Interim Rules of Court; NATIONAL GRAINS AUTHORITY, plaintiff-appellee,
Sec. 21, subpar. 1, B.P. Blg. 129). Extraterritorial service of vs.
summons will not confer on the court jurisdiction or power to INTERMEDIATE APPELLATE COURT, MELECIO
compel them to obey its orders. MAGCAMIT, NENA COSICO and EMELITA
MAGCAMIT, defendants-appellants.
Neither may the court by extraterritorial service of summons
acquire jurisdiction to render and enforce a money judgment
against a non-resident defendant who has no property in the
Philippines for "the fundamental rule is that jurisdiction in PARAS, J.:
personam over non-residents, so as to sustain a money
judgment, must be based upon personal service within the This is a petition for review of the decision of the then
state which renders the judgment "(Boudard vs. Tait, 67 Phil. Intermediate Appellate Court * (now Court of Appeals) dated
170, 174). January 31, 1984, reversing the decision of the Court of First
Instance of Laguna and San Pablo City, 8th Judicial District,
Respondents' contention that "the action below is related to Branch III, and of the resolution dated August 28, 1984
property within the Philippines, specifically contractual rights denying the motion for reconsideration filed thereof.
that petitioners are enforcing against IVO" is specious for the
"contractual rights" of the petitioners are not property found in The undisputed facts of this case as found by the Trial Court
the Philippines for the petitioners have not filed an action in and the Intermediate Appellate Court are as follows:
the local courts to enforce said rights. They have not submitted
to the jurisdiction of our courts. On December 2,1971, the spouses Paulino Vivas and Engracia
Lizards, as owners of a parcel of land situated in Bo. San
The lower court invoked Section 33 of the Corporation Code Francisco, Victoria, Laguna, comprising more or less 105,710
which provides that a "foreign corporation transacting square meters, sold for P30,000.00 said property in favor of
business in the Philippines without a license may be sued or spouses Melencio Magcamit and Nena Cosico, and Amelita
proceeded against before Philippine courts or administrative Magcamit (herein private respondents) as evidenced by
tribunal on any valid cause of action recognized under "Kasulatan Ng Bilihang Mabiling Muli." This sale with right
Philippine laws." It assumed that the defendants (herein to repurchase was recorded in the Office of the Register of
petitioners) are doing business in the Philippines, which Deeds of Laguna on December 6,1971 under Act No. 3344.
allegation the latter denied. Even if they can be considered as On January 31,1972 the sale was made absolute by the
such, the Corporation Code did not repeal the rules requiring spouses Vivas and Lizardo in favor of the private respondents
proper service of summons to such corporations as provided in for the sum of P90,000.00; P50,000.00 of which was paid
Rule 14 of the Rules of Court and Section 128 of the upon the execution of the instrument, entitled "Kasulatan Ng
Corporation Code. Bilihan Tuluyan," after being credited with the P30,000.00
consideration of the "Kasulatan Ng Mabibiling Muli," and the
balance of P40,000.00 was to be paid the moment that the to continue in possession of the same, and if the petitioner is
certificate of title is issued. From the execution of said declared the owner of the said property, then, to order it to
Kasulatan, private respondent have remained in peaceful, reconvey or transfer the ownership to them under such terms
adverse and open possession of subject property. and conditions as the court may find just, fair and equitable
under the premises. (Record on Appeal, pp. 2-11).
On February 26, 1975, an Original Certificate of Title No. T-
1728 covering the property in question was issued to and in In its answer to the complaint, the petitioner (defendant
the name of the spouses Vivas and Lizardo without the therein) maintained that it was never a privy to any transaction
knowledge of the private respondents and on April 30, 1975, between the private respondents (plaintiffs therein) and the
said Spouses executed a Special Power of Attorney in favor of spouses Paulino Vivas and Engracia Lizardo that it is a
Irenea Ramirez authorizing the latter to mortgage the property purchaser in good faith and for value of the property formerly
with the petitioner, National Grains Authority. covered by OCT No. 1728; and that the title is now
indefeasible, hence, private respondents' cause of action has'
On May 2, 1974, the counsel for the petitioner wrote the already prescribed. (Record on Appeal, pp. 16-22).
Provincial Sheriff in Sta. Cruz, Laguna, requesting for the
extrajudicial foreclosure of the mortgage executed by Irenea After due hearing, the trial court ** rendered its decision on
Ramirez on May 18, 1975, covering, among others, the March 17, 1981, in favor of the petitioner, the dispositive
property involved in this case covered by OCT No. T-1728, portion of said judgment reading as follows:
for unpaid indebtedness in the amount of P63,948.80 in favor
of the petitioner. WHEREFORE, judgment is hereby
rendered as follows:
On May 31, 1974, the Provincial Sheriff caused the issuance
of the notice of sale of the property in question, scheduling the (1) declaring defendant National Grains
public auction sale on June 28, 1974. The petitioner was the Authority the lawful owner of the property
highest and successful bidder so that a Certificate of Sale was in question by virtue of its indefeasible title
issued in its favor on the same date by the Provincial Sheriff. to the same;
On July 10, 1974, the petitioner in its capacity as attorney-in- (2) ordering plaintiffs to turn over
fact of the mortgagor sold the subject real property in favor of possession of the land to defendant National
itself. By virtue of the deed of absolute sale, TCT No. T- Grains Authority;
75171 of the Register of Deeds for the Province of Laguna
was issued in the name of the petitioner on July 16, 1974. It (3) ordering defendants-spouses Paulino
was only in July 1974, that private respondents learned that a Vivas and Engracia Lizardo to pay plaintiffs
title in the name of the Vivas spouses had been issued the sum of P56,000.00 representing the
covering the property in question and that the same property amount paid pursuant to the Kasulatan Ng
had been mortgaged in favor of the petitioner. Private Bilihang Tuluyan marked Exhibit "3", with
respondent Nena Magcamit offered to pay the petitioner NGA legal interest thereon from January 31, 1972
the amount of P40,000.00 which is the balance of the amount until the amount is paid, to pay an additional
due the Vivas spouses under the terms of the absolute deed of amount of P5,000.00 for and as attorney's
sale but the petitioner refused to accept the payment. On July fees, an additional amount of Pl0,000.00 as
31, 1974, counsel for private respondents made a formal moral damages, another amount of
demand on the spouses Vivas and Lizardo to comply with P5,000.00 by way of exemplary damages
their obligation under the terms of the absolute deed of sale; and to pay the costs of this suit. (Rollo, P.
and soon after reiterated to the NGA, the offer to pay the 35).
balance of P40,000.00 due under the absolute deed of sale. On
August 13, 1974 petitioner in its reply informed counsel of
private respondents that petitioner is now the owner of the The private respondents interposed an appeal from the
property in question and has no intention of disposing of the decision of the trial court to the Intermediate Appellate Court.
same.
After proper proceedings, the appellate court rendered its
The private respondents, who as previously stated, are in decision on January 31, 1984, reversing and setting aside the
possession of subject property were asked by petitioner to decision of the trial court as follows:
vacate it but the former refused. Petitioner filed a suit for
ejectment against private respondents in the Municipal Court WHEREFORE, the decision of the lower
of Victoria, Laguna, but the case was dismissed. court is hereby reversed and set aside and
another one is rendered ordering the
On June 4, 1975, private respondents filed a complaint before National Grains Authority to execute a deed
the then Court of First Instance of Laguna and San Pablo City, of reconveyance sufficient in law for
Branch III, San Pablo City, against the petitioner and the purposes of registration and cancellation of
spouses Vivas and Lizardo, praying, among others, that they transfer Certificate of Title No. T-75171 and
be declared the owners of the property in question and entitled the issuance of another title in the names of
plaintiff-appellants, and ordering deed of Absolute Sale which although unregistered under the
defendants-appellees Paulino Vivas and Torrens System allegedly transferred to them the ownership
Engracia Lizardo to pay the National Grains and the possession of the property in question. In fact, they
Authority the sum of P78,375.00 (Exh. 3) argue that they have been and are still in possession of the
within thirty (30) days from the receipts of same openly, continuously, publicly under a claim of
the writ of execution. No damages and costs. ownership adverse to all other claims since the purchase on
(Rollo, p. 19). December 2, 1971 (Rollo, p. 165). It is stressed that not until
the month of July, 1974 did the plaintiff learn that a title had
The petitioner filed a motion for reconsideration of the said been issued covering the property in question (Rollo, p. 15).
decision but the same was denied. (Rollo, p. 26).
Time and time again, this Court has ruled that the proceedings
Hence, this petition. for the registration of title to land under the Torrens System is
an action in rem not in personam, hence, personal notice to all
In the resolution of May 20, 1985, the petition was given due claimants of the res is not necessary in order that the court
course and the parties were required to submit simultaneous may have jurisdiction to deal with and dispose of the res.
memoranda (Rollo, p. 128). The memorandum for the Neither may lack of such personal notice vitiate or invalidate
petitioner was filed on July 3, 1985 (Rollo, p. 129) while the the decree or title issued in a registration proceeding, for the
memorandum for the private respondents was filed on August State, as sovereign over the land situated within it, may
26, 1985 1 Rollo p. 192). provide for the adjudication of title in a proceeding in rem or
one in the nature of or akin a to proceeding in rem which shall
be binding upon all persons, known or unknown (Moscoso vs.
The main issue in this case is whether or not violation of the Court of appeals, 128 SCRA 719 [1984], citing: City of
terms of the agreement between the spouses Vivas and Manila vs. Lack, et al., 19 Phil. 324, 337; Roxas vs. Enriquez,
Lizardo, the sellers, and private respondents, the buyers, to 29 Phil. 31; Director of Lands vs. Roman Catholic Archbishop
deliver the certificate of title to the latter, upon its issuance, of Manila, 41 Phil. 120; Aguilar vs. Caogdan, 105 Phil. 661).
constitutes a breach of trust sufficient to defeat the title and It is thus evident that respondents' right over the property was
right acquired by petitioner NGA, an innocent purchaser for barred by res judicata when the decree of registration was
value. issued to spouses Vivas and Lizards. It does not matter that
they may have had some right even the right of ownership,
It is undisputed that: (1) there are two deeds of sale of the BEFORE the grant of the Torrens Title.
same land in favor of private respondents, namely: (a) the
conditional sale with right to repurchase or the 'Kasulatan Ng Thus, under Section 44 of P.D. 1529, every registered owner
Bilihang Mabibiling Muli" which was registered under Act receiving a certificate of title in pursuance of a decree of
3344 and (b) the deed of absolute sale or "Kasulatan ng registration, and every subsequent purchaser of registered land
Bilihang Tuluyan" which was not registered; (2) the condition taking a certificate of title for value and in good faith, shall
that the Certificate of Title will be delivered to the buyers hold the same free from all encumbrances except those noted
upon its issuance and upon payment of the balance of on the certificate and any of the encumbrances which may be
P40,000.00 is contained in the deed of absolute sale; and (3) subsisting, and enumerated in the law. Under said provision,
the land in question at the time of the execution of both sales claims and liens of whatever character, except those
was not yet covered by the Torrens System of registration. mentioned by law as existing, against the land prior to the
issuance of certificate of title, are cut off by such certificate if
It is axiomatic, that while the registration of the conditional not noted thereon, and the certificate so issued binds the whole
sale with right of repurchase may be binding on third persons, world, including the government (Aldecoa and Co. vs. Warner
it is by provision of law "understood to be without prejudice to Barns & Co., 30 Phil. 209 [1915]; Snyder vs. Fiscal of Cebu
third party who has better right" (Section 194 of the and Avila, 42 Phil. 766 [1922]). Under said ruling, if the
Administrative Code, as amended by Act No. 3344). In this purchaser is the only party who appears in the deeds and the
case, it will be noted that the third party NGA, is a registered registration of titles in the property registry, no one except
owner under the Torrens System and has obviously a better such purchaser may be deemed by law to be the owner of the
right than private respondents and that the deed of absolute properties in question (Ibid). Moreover, no title to registered
sale with the suspensive condition is not registered and is land in derogation to that of the registered owner shall be
necessarily binding only on the spouses Vivas and Lizardo and acquired by prescription or adverse possession (Umbay vs.
private respondents. Alecha, 135 SCRA 427 [1985]).
In their complaint at the Regional Trial Court, private It does not appear that private respondents' claim falls under
respondents prayed among others, for two alternative reliefs, any of the exceptions provided for under Section 44 of P.D.
such as: (a) to be declared the owners of the property in 1529 which can be enforced against petitioner herein.
question or (b) to order the declared owner to reconvey or
transfer the ownership of the property in their favor. Thus, it has been invariably restated by this Court, that "The
real purpose of the Torrens System is to quiet title to land and
Private respondents claim a better right to the property in to stop forever any question as to its legality. "Once a title is
question by virtue of the Conditional Sale, later changed to a registered, the owner may rest secure, without the necessity of
waiting in the portals of the court, or sitting on the "mirador su the property, their rights cannot be disregarded (Duran vs.
casato," avoid the possibility of losing his land." "An indirect IAC, 138 SCRA 489 [1985]).
or collateral attack on a Torrens Title is not allowed (Dominga
vs. Santos, 55 Phil. 361; Singian vs. Manila Railroad, 62 Phil. Under the circumstances, the Regional Trial Court could not
467)." have erred in ruling that plaintiffs (private respondents herein)
complaint insofar as it prays that they be declared owners of
The only exception to this rule is where a person obtains a the land in question can not prosper in view of the doctrine of
certificate of title to a land belonging to another and he has indefeasibility of title under the Torrens System, because it is
full knowledge of the rights of the true owner. He is then an established principle that a petition for review of the decree
considered as guilty of fraud and he may be compelled to of registration will not prosper even if filed within one year
transfer the land to the defrauded owner so long as the from the entry of the decree if the title has passed into the
property has not passed to the hands of an innocent purchaser hands of an innocent purchaser for value (Pres. Decree No.
for value (Angeles vs. Sania, 66 Phil. 444 [1938], emphasis 1529, Sec. 32). The setting aside of the decree of registration
supplied). issued in land registration proceedings is operative only
between the parties to the fraud and the parties defrauded and
It will be noted that the spouses Vivas and Lizardo never their privies, but not against acquirers in good faith and for
committed any fraud in procuring the registration of the value and the successors in interest of the latter; as to them the
property in question. On the contrary, their application for decree shall remain in full force and effect forever (Domingo
registration which resulted in the issuance of OCT No. 1728 vs. The Mayon Realty Corp. et al., 102 Phil. 32 [19571).
was with complete knowledge and implied authority of private Assuming, therefore, that there was fraud committed by the
respondents who retained a portion of the consideration until sellers against the buyers in the instant case, petitioner NGA
the issuance to said spouses of a certificate of title applied for who was not privy therein cannot be made to suffer the
under the Torrens Act and the corresponding delivery of said consequences thereof As correctly declared by the trial court,
title to them. The question therefore, is not about the validity the National Grains Authority is the lawful owner of the
of OCT No. 1728 but in the breach of contract between private property in question by virtue of its indefeasible title.
respondents and the Vivas spouses. Petitioner NGA was never
a privy to this transaction. Neither was it shown that it had any As to private respondents' alternative prayer that the declared
knowledge at the time of the execution of the mortgage, of the owner be ordered to reconvey or transfer the ownership of the
existence of the suspensive condition in the deed of absolute property in their favor, it is clear that there is absolutely no
sale much less of its violation. Nothing appeared to excite reason why petitioner, an innocent purchaser for value, should
suspicion. The Special Power of Attorney was regular on its reconvey the land to the private respondents.
face; the OCT was in the name of the mortgagor and the NGA
was the highest bidder in the public auction. Unquestionably, PREMISES CONSIDERED, the decision of the Court of
therefore, the NGA is an innocent purchaser for value, first as Appeals is REVERSED and SET ASIDE, and the decision of
an innocent mortgagee under Section 32 of P.D. 1529 and the Court of First Instance of Laguna and San Pablo City, now
later as innocent purchaser for value in the public auction sale. Regional Trial Court, is REINSTATED.
Private respondents claim that NGA did not even field any SO ORDERED.
representative to the land which was not even in the
possession of the supposed mortgagors, nor present any
witness to prove its allegations in the ANSWER nor submit its
DEED OF MORTGAGE to show its being a mortgages in
good faith and for value (Rollo, p. 110).