NOTE
MEPL Reference dwg no:
A
MEPL/19-20/DWG/034 for Total earthing layout. 1. All dimensions are in mm. A

MEPL/19-20/DWG/035 for Switch yard earthing. 2. 50x12mm MS flat used for earth
MEPL/19-20/DWG/036 for Transformer hall earthing. grid.(equivalent size of conductor to be
MEPL/19-20/DWG/037 for Power house earthing. used)
MEPL/19-20/DWG/038 for Butterfly valve chamber earthing. 3. 50x12mm MS flat used as riser.
MEPL/19-20/DWG/039 for BOQ. 4. All joints shall be painted using
Bituminous paint to avoid corrosion.
B B

SJVNL Refer dwg no:


PH-C2-AR3-C01/R1
TB-3-405-316-001(01of02)
TB-3-405-316-001(02of02)
C PH-AR3-BID-003 C

PH-AR3-BID-017
PH-AR3-BID-014
PH-AR3-BID-015
Flat PH-AR3-BID-016
PH-AR3-BID-012
PH-AR3-BID-019
D
PH-C2-AR3-C23/R1 D

PH-C2-AR3-C21
PH-C2-AR3-C17/R1
PH-C2-AR3-C34 LEGEND
PH-C2-AR3-C35
2 PH-C2-AR3-C36
PH-C2-AR3-C37 1 Earthgrid Conductor
E
1 PH-C2-AR3-C38
E

PH-C2-AR3-C39
2 Electric Arc Welding
5

F F

50 PROJECT:
GROUNDING SYSTEM DESIGN OF ARUN-3, HEP
CLIENT:
G SJVN Arun-3 Power Development Company(SAPDC) G

SAPDC'S CONSULTANT:
SJVN LIMITED
EARTHING CONSULTANT:
MANAV ENERGY PVT LTD®
Sheet.Size
NAME SIGN DATE TITLE
A3
DESIGN MANI 21/10 /'19 WELDING STANDARD FOR
CHKD. VIJAY 22/10 /'19 EARTHMAT TO FLAT CONNECTION
APPD. NAVEEN 23/10 /'19
MANAV DWG NO: CID:400 SCALE PROJECTION

H
12/02 /'20 02 th
Updated as per comments received on 7 February 2020 VIJAY NAVEEN
MEPL/19-20/DWG/033 NTS H

01/02 /'20 01

25/10 /'19 00
Updated as per comments received on 3rd January 2020

INITIAL RELEASE
VIJAY NAVEEN

VIJAY NAVEEN
MANAV ENERGY PVT. LTD
DATE REV.NO. DESCRIPTION CHECKED APPROVED SUBMITTED FOR APPROVAL INFORMATION REFERENCE RECORDS CONSTRUCTION