Professional Documents
Culture Documents
OVERVIEW
This report proposes a possible redesign for the BNSF Railroad Bridge located at River Station (RS) 17.54 on the
Skagit River. The redesign focused on creating a bridge that is more resistant to scour and does not trap debris by
decreasing pier sizes, increasing the deck/roadway, and adding riprap. Analysis was conducted by modeling both
the original bridge and redesigned bridge in HEC-RAS. The redesigned bridge was shown to minimize debris
accumulation and accommodate the 250-year flood without water reaching the low chord of the bridge.
Assumptions used to create the design and for the HEC-RAS model are as follow:
• Bridge design is possible from structural engineering perspective
• River has unsteady flow
• Cost and ease of construction are not prioritized
• Initial flow is 43000 cubic feet per second at RS 23.2
• Boundary condition set to Normal Depth at RS 9.48
DESIGN CHANGES
The redesign focused on changing the piers, deck/roadway, and sloping abutments of the original bridge in order to
make a bridge more resistant to scour and accommodate the 250-year flood without water touching the bridge’s low
chord. The changes for each category are described below.
Piers
In order to decrease the amount of debris the bridge traps, piers that were originally collecting debris were removed,
and the remaining piers were increased in size to account for the fewer number of piers. The cross-section of the
original bridge (Figure 1) is shown below. From Figure 1, it is evident that Piers #3 and #4 collect a lot of debris,
so they are removed.
The 250-year max water surfaces for the original (Figure 2) and redesigned bridges (Figure 3) are compared
below. Piers #7, #9, #10, and #13 were removed to keep the water from reaching the low chord of the bridge.
1
DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING
Finally, Piers #5 and #6 were widened to account for removing piers. The changes to the piers are summarized in
Figures 4 and 5 on the next page.
2
DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING
Figure 4. Pier #5 for Redesigned Bridge Figure 5. Pier #6 for Redesigned Bridge
Deck/Roadway
To accommodate for the requirement of the water not reaching the low chord of the bridge during the 250-year
flood, the bridge deck/roadway was raised 30 feet to be conservative. The difference between the heights can be
seen in Figures 2 and 3 on the previous page.
Figure 6. Left Side Abutment Dimensions for Redesigned Bridge Figure 7. Right Side Abutment Dimensions for Redesigned Bridge
3
DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING
following page summarizes the results of the model. The Table shows that the flows at and after the bridge are
consistently less for the redesign compared to the original bridge.
Table 1. Original vs. Redesign Flows for Max Water Surface Upstream, Downstream, and at Bridge for 10-, 250-, and 500-Year Flows
The water surfaces and velocities at each of the stations defined in the previous section are compared
for the original and redesigned bridges at the max surfaces for 10-Year, 250-Year and 500-Year Flows
(Table 2 and 3).
Comparison
The requirement for not reaching the low chord of the bridge during a 250-year flood was achieved
through the redesign as shown in the comparison between the original bridge with the max water surface
during a 250-year flood (Figure 2) and the redesigned bridge with the max water surface during a 250-
year flood (Figure 3). Figures 2 and 3 are copied below, side by side for viewing ease to see the difference.
4
DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING
Figure 2. 250-Year Max Water Surface for Original Bridge Figure 3. 250-Year Max Water Surface for Redesigned Bridge
The profile plots for the original (Figure 8) and redesigned bridge (Figure 9) at 250-Year flood are
shown below.
Figure 8. Profile Plot for Original Bridge at 250-Year Max Water Surface
5
DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING
Figure 9. Profile Plot for Original Bridge at 250-Year Max Water Surface
The stage flow plots for the original (Figure 10) and redesigned bridge (Figure 11) at 250-Year flood are
shown below.
Figure 10. Stage Flow Plot for Original Bridge at 250-Year Max Water Surface
6
DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING
Figure 11. Stage Flow Plot for Redesigned Bridge at 250-Year Max Water Surface
For the given requirements, the proposed design goes above and beyond what is needed from the bridge.
However, if more restrictions were to be added to the bridge, the design should change to accommodate
these restrictions.