OCS - DAILY REPORT - STEEL REPLACEMENT

Client ARO Drilling Report No. OCS-ARO-55-030


Asset Name Rig 55 - Scooter Yeargain
Date of Report 4-Mar-20
Owner's Representative Allan Lewis

No of
Crew Permit Record Inspection Record
Crew
Project Engineer 1 Description Location Status Description Tank Status
Tank 36,
33, 35, 29,
Steel Supervisor 2 Gas Free Permit Issued Marking Inspection
34, 18, 23,
8
Tank 36,
33, 35, 29, 34, 35, 29,
Hot Work Permit Issued Fit - Out Inspection
34, 18, 23, 8
Paint Supervisor 2 8
Tank 36,
33, 35, 29, 34, 35,
Work At Height Permit Issued Pre Welding Inspection
34, 18, 23, 29, 8
Scaffolding Supervisor 2 8

Tank 36,
33, 35, 29,
Entry to Tank Issued Weld Completion Inspection
34, 18, 23,
8
Welder 23
Work on
Zone 6 Permit Barge and Issued
Fitter 36 Key side
Scaffolder 14 Steel Progress Summary
UHP Blaster 9 Total Weight of Steel 17,540 kgs
Painter 4 Steel Installed 11,387
Helper 10 No. of Tanks Completed 13
Total Manpower 103 No. of Tanks ABS Cleared 8

Tank Completion Status Report


Tank Description Work Status NDT Status ABS Inspection Status Remarks
Cleared for service and awaiting final
Preload Tank 1 Completed Completed and Cleared Completed
report
Preload Tank 3 Completed In Progress Pending
Cleared for service and awaiting final
Preload Tank 5 Completed Completed and Cleared Completed
report
Cleared for service and awaiting final
Preload Tank 13 Completed Completed and Cleared Completed
report
Cleared for service and awaiting final
Preload Tank 19 Completed Completed and Cleared Completed
report
Cleared for service and awaiting final
Preload Tank 20 Completed Completed and Cleared Completed
report
Cleared for service and awaiting final
Preload Tank 30 Completed Completed and Cleared Completed
report
Cleared for service and awaiting final
Skimmer Tank 40 Completed Completed and Cleared Completed
report
Preload Tank 38 Completed Completed and Cleared Pending

Preload Tank 25 Completed - Pending

Preload Tank 28 Completed - Pending


Preload Tank 39 Completed - Pending
Cleared for service and awaiting final
Fresh Water Tank 11 Completed Completed and Cleared Completed
report

Daily Activity Report


Tank No. Location of Work Activity Description Status Remarks (If Any)

Cropping of Exisitng Steel as


100% Completed
per repair plan
Prefabrication 100% Completed
Preload Tank 36 (S) Bottom Plating
Fitup 100 % Completed
Welding 97% Completed

Prefabrication 100% Completed


Cropping of Exisitng Steel as
100% Complete
per repair plan
Preload Tank 34 (S) Bottom Plating
Fit up 100% Complete

Welding 70% Complete

Marking Inspection 100% Complete


Cropping of Exisitng Steel as
85% Complete
Preload Tank 35 (P) Bottom Plating per repair plan

Fit up 75% Complete


Welding 60% Complete

Marking 100% Complete


Cropping of Exisitng Steel as
80% Complete
Preload Tank 33 (P) Bottom Plating per repair plan
Fit Up 100% Complete
Welding 80% Complete

Cropping of Exisitng Steel as


100% Complete
per repair plan
Preload Tank 29 (P) Bottom Plating
Fit Up 100% Complete
Welding 80% Complete

Cleaning of Eureka at
Drill Water Tank 24 (S) 100% Complete
locations of steel replacement

Cropping of Exisitng Steel as


100% Complete
per repair plan
Drill Water Tank 23 (P) Bottom Plating Fit Up 50% Complete

Welding 35% Complete

Cleaning, ventillation in
100% Complete
progress
Cropping of Existing Steel as
Diesel Tank 8 / 100% Complete
Skid Rail per repair plan
Machinery Space
Fit Up 100% Complete
Welding Commenced

Cleaning of Eureka 100% Complete


Drill Water Tank 18
Crop Out 10% Complete
Port Aft Leg Well
Build up of Scaffolding 100% Completed
Scaffolding

Scaffolding 100% Complete


Trip Tank Extension Cantilever Pre Fabrication of Steel
30% Complete
Plates & Fit Up

Fabrication and welding of


Key Side Fabrication
additional plates as In progress
Area
requested by ARO.

Standy By Time Yes No


Reason For Stand By

Koshy Jose - Project Manager


OCS Services DMCC