Professional Documents
Culture Documents
pubs.acs.org/IECR
ABSTRACT: A natural gas liquefaction and liquid recovery sequence is proposed for top-side offshore floating liquefied natural
gas processing. During liquefaction, a single mixed refrigerant is separated into heavy and light key components, separately
compressed after the main cryogenic heat exchanger and then mixed again to make a single mixed refrigerant. The proposed
liquefaction cycle has a simple, compact structure and is suitable for power-efficient, offshore, floating liquefied natural gas
liquefaction. The natural gas liquid recovery process employs space- and energy-efficient dividing wall columns for the integration
of depropanization and debutanization. The columns were optimized by response surface methodology. A compact top dividing
wall column configuration could reduce total annual costs. A combined process integrating natural gas liquefaction and liquid
recovery is finally proposed.
© 2012 American Chemical Society 10021 dx.doi.org/10.1021/ie2029283 | Ind. Eng. Chem. Res. 2012, 51, 10021−10030
Industrial & Engineering Chemistry Research Article
exchangers. Since no mixtures are used, the process is simple precooling cycle of C3MR is replaced by a MR JT cycle to
and robust in operation. Drawbacks include its large size and remove the bottleneck of the propane compressor. The LINDE
large amount of equipment. process has three JT cycles, similar to the cascade process, but
The simplest natural gas liquefaction process employs SMR employs MRs in all three cycles. IFP/AXENS developed a new
(single mixed refrigerant, Figure 1) because there is only one liquefaction process called LIQUEFIN, which also incorporates
two MR JT cycles.
Several analyses of dividing wall columns (DWCs, Figure 2)
for ternary separations have shown that they can achieve energy
and space savings of up to 30% over conventional direct and
indirect distillation sequences.22−24 DWCs allow reversible
splits with no part of the separation performed twice, the main
reason for their superior energy efficiency.25 However, their
design is more complex than conventional arrangements because
of the greater number of degrees of freedom26 that interact with
each other and need to be optimized simultaneously. Optimization
studies rely on statistical approaches, with response surface
methodology (RSM) being routinely used in several biotechno-
logical and industrial multivariable processes.27,28 In RSM, the
Box−Behnken design only has three levels (low, medium, and
high, coded as −1, 0, +1) and requires a small number of experi-
ments or simulation runs. It is more efficient and easier to arrange
and interpret than other methods.
This work proposes a new, simple, compact, and power-
efficient natural gas liquefaction cycle and natural gas liquid
(NGL) recovery sequence for offshore FLNG with the capacity
of 2.5MTPA. The proposed liquefaction cycle was optimized
using the temperature profiles in the cryogenic heat exchanger and
the compressor power of each separated compressor. In the
proposed NGL recovery process, feed splitting and a top dividing
wall column were employed to maximize energy efficiency and
plant compactness.
Figure 2. Dividing wall columns (DWCs): (a) conventional DWC; (b) top DWC; (c) bottom DWC.
Figure 4. (a) The proposed process (basic type, Cycle-1) and (b) its
temperature−heat flow.
Figure 3. A DMR cycle.
number of stages of the MR’s compressors. The optimal
exchanger. The two MRs generally contain nitrogen, methane,
number of stages of the LK and HK compressors in Cycle-1
ethane, and propane. One of the cycles precools the precooling
were respectively 4 and 2. The multicomponent refrigerant was
zone in the heat exchanger, and the other cycle liquefies the
also optimized to find the appropriate composition of the MR.
natural gas to LNG. The compositions of each cycle are
The main optimizing variables were MR composition (N2,
different to achieve the most effective temperature range; they
must be optimized independently. C1, C2, C3), MR flow rate, high pressure of MR compressor,
In this study, to take advantage of both DMR and SMR inlet pressure of HK MR compressor, precooling temperature
cycles, the DMR cycle was structurally modified into a SMR using HK.
cycle by separating the single MR into two refrigerant streams. The lowest pressure of the MR, that is, the inlet pressure of
In the proposed cycle, the MR is separated into two different the MR compressor (1.3 bar), was chosen to be slightly higher
MRs from a vapor−liquid separator, with each separated MR than atmospheric pressure for safety. The objective for optimiza-
having its own refrigerant role in the main cryogenic heat tion is to minimize total compression power. The minimum
exchanger (MCHE). After the MCHE, each MR is compressed approach temperature of the MCHE was constrained to above
separately and then mixed again to become single MR. 3 °C. Mesh searching or Brute force method was employed for
2.3. The Proposed Cycle (Cycle-1). Figure 4a outlines the optimization.
basic type (Cycle-1) of the proposed liquefaction cycle, in Figure 1b shows the temperature−heat flow diagram of the
which MR is separated into heavier liquid (HK, heavy key) and optimized SMR cycle. SMR cycles normally show large gaps
lighter vapor (LK, light key) refrigerants in a flash drum. The between the temperature profiles of the hot and cold com-
single MR is separated into two MRs that act separately in the ponents in the precooling zone (−60 to 40 °C) of the heat
MCHE: HK precools the refrigerants and natural gas, and LK exchanger because the C3 component of the MR begins
precools LK refrigerant and liquefies natural gas to −150 °C. vaporizing in the precooling zone. Optimizing the SMR cycle
The MRs are then mixed after the compressor and after-cooler. reduces the gap of the temperature profiles in the liquefaction
The refrigerants comprise nitrogen, methane, ethane, and zone while the precooling zone’s gap widens.
propane as per C3MR. The gap between the hot and cold component temperature
The compressor outlet pressures of the MRs are same, but profiles in the temperature-heat flow diagram of Cycle-1
their inlet pressures could be different. Therefore the proposed (Figure 4b) starts to increase at about −60 °C, similar to the
cycle could be optimized using inlet pressure levels and the SMR cycle, but the cold component profile is different above
10023 dx.doi.org/10.1021/ie2029283 | Ind. Eng. Chem. Res. 2012, 51, 10021−10030
Industrial & Engineering Chemistry Research Article
this temperature. There is an additional C3 vaporizing point in specific power percent of specific
[kw·hr/kg of LNG] power
Cycle-1 because of the higher pressure of HK than LK.
SMR cycle 0.4760 100%
Therefore, there are two bending points in the cold component
cascade 0.4444 93%
profile. The liquefaction cycle could be optimized using the two
C3MR 0.2945 62%
bending points.
proposed Cycle-1 0.3204 67%
The specific power of Cycle-1 to liquefy 1 kg of LNG was cycle Cycle-2 0.3106 65%
found to be 0.3204 kWh/kg LNG, very efficient compared with
Cycle-3 0.3184 67%
the SMR cycle (0.4760 kWh/kg LNG). The proposed cycle
could achieve high performance, decreasing the gap between and to precool the natural gas and other refrigerants. The
the hot and cold component temperature profiles in the
precooling zone. temperature-heat flow diagram of Cycle-2 (Figure 5b) shows
2.4. The Proposed Cycle (Cycle-2). Cycle-1 requires an closer hot and cold component temperature profiles in the
LK compressor with four stages and an HK compressor with precooling zone than in Cycle-1 because of the three bending
two stages. The last stages of both compressors can be com- points in the cold component temperature profile. This can
bined into one single-stage compressor. Therefore, the struc- lead to improved performance. The specific power of Cycle-2
ture of compressor system becomes a LK compressor with three after optimization is 0.3106 kWh/kg LNG.
stages, a single-stage HK compressor, and a single-stage MK (LK 2.5. The Proposed Cycle (Cycle-3). Cycle-2 requires three
+ HK) compressor. After the compressors are combined, there is compressors in parallel. Its high performance is achieved through
liquid refrigerant at the mixing point of LK and MK after each a complex structure. In Cycle-3, HHK liquid from a vapor−liquid
after-cooler. Therefore, a vapor−liquid separator is necessary after
the mixing point of LK and MK. It generates a new refrigerant separator can be mixed with HK liquid, simplifying the structure
liquid (HHK, heavy heavy key) that is heavier than HK. (Figure 6a). The temperature-heat flow diagram of Cycle-3
HHK can be used as a new refrigerant in the proposed cycle. (Figure 6b) shows only two bending points, resulting in some
Figure 5a outlines Cycle-2, another proposed liquefaction cycle. loss of efficiency. Cycle-3 has an optimized specific power of
HHK refrigerant is expanded after the vapor−liquid separator 0.3184 kWh/kg LNG.
10024 dx.doi.org/10.1021/ie2029283 | Ind. Eng. Chem. Res. 2012, 51, 10021−10030
Industrial & Engineering Chemistry Research Article
Table 1 summarizes the performances of the proposed cycles Table 2. Feed Mixture Conditions
compared with the SMR cycle. Cycle-2 shows best performance
nitrogen (% mol fraction) 1.54
in terms of the specific power. Cycle-3 seems to be most
methane (% mol fraction) 86.39
suitable for a FLNG plant, showing only a slight degradation of
ethane (% mol fraction) 6.47
efficiency for the simpler structure.
propane (% mol fraction) 2.87
i-butane (% mol fraction) 0.72
3. THE PROPOSED NGL RECOVERY PROCESS
n-butane (% mol fraction) 0.82
During onshore processing, liquid hydrocarbons recovered i-pentane (% mol fraction) 0.41
from NGL are typically separated into relatively pure ethane n-pentane (% mol fraction) 0.31
(C2), propane (C3), isobutane (iC4), normal butane (nC4), and n-hexane (% mol fraction) 0.31
gasoline (C5+) products. This is conventionally done by the n-heptane (% mol fraction) 0.15
sequential distillation of C2, C3, and C4 from gasoline, followed total mass flow rate (kg/h) 292 418
by further distillation of iC4 from nC4 (Figure 7).4,5,7,8 The temperature (°C) 35
similar boiling points of iso- and normal butane make their pressure (bar) 71
separation require many trays with a high reflux ratio. An
offshore plant must be able to withstand waves, most notably the
distillation and separation columns. For this reason, columns be minimized because of the limited space and safety concerns.
should be designed to withstand motion, limiting the column Due to restrictions of column height and the number of product
height and making the packed-type column designs suitable.30 In tanks, a deisobutanizer would likely be excluded from an FLNG
addition, the number of products and product tanks should also plant.
10025 dx.doi.org/10.1021/ie2029283 | Ind. Eng. Chem. Res. 2012, 51, 10021−10030
Industrial & Engineering Chemistry Research Article
Figure 9. Effect of feed split ratio on the operating cost of the Figure 10. Effect of the number of trays on the reboiler duty of the
demethanizer and depropanizer. TDWC.
3.1. Base Sequence. A new NGL recovery process is pressure conditions are listed in Table 2. To determine each
proposed for FLNG facilities with the following constraints and column’s maximum flooding, rating modes were simulated using
assumptions: (a) All columns are designed as packed type each column’s internal specifications, that is, internal type, column
columns for greater stability against motion. (b) The maximum diameter, and number of passes. Table 3 lists the conditions and
allowable height of each column is restricted to that of 20 the energy requirements of the columns considered here. The
equivalent ideal trays to limit the motion of wind and waves columns were designed with for loads near 80% of the flooding
and to avoid excessive bending moments. (c) The operating load to prevent flooding. Simulations were performed using the
velocity of all columns is near 80% of the flooding velocity. (d) Aspen HYSYS V7.1 simulator. The Peng−Robinson equation of
A deisobutanizer and a deethanizer are excluded due to state supporting the widest range of operating conditions and the
restrictions of column height and/or the number of inventory greatest variety of systems was used to predict the simulations’
tanks. (e) The product specifications are as follows: C1, 89% vapor−liquid equilibria.31 The Lee−Kesler method of enthalpy
(top of demethanizer); LPG, 98% (top of debutanizer); C5+, calculation was employed.
99% (bottom of debutanizer). 3.2. Improvement of Base Sequence. 3.2.1. Feed Split.
Based on the feed conditions and the product specifications, Instead of precooling the entire feed stream, it can first be
simulations were performed to quantify energy consumption. divided into two streams: one is cooled before entering the
The demethanizer, with 10 theoretical trays, was designed for column like a feed, and one is fed into the column’s bottom
use at 69.5 bar (Figure 8). A turbo-expander configuration, (dashed line, Figure 8). This sequence can eliminate one reboiler
which is most popular for the demethanizers in onshore LNG in the demethanizer and save energy in precooler C0. However,
plants, is not economical for FLNG situation, and thus was not energy consumption is increased in condenser C1 in the
considered here. The sharp separation of methane from C2+ demethanizer and the reboiler in the depropanizer. Note that the
increases energy consumption. Therefore, a depropanizer column refrigeration used in precooler C0 and condenser C1 are at low
is used to recycle light components in the bottom stream of the temperatures; their prices are listed in Table 4.32 Therefore,
demethanizer. The 20-tray debutanizer column was designed for adjustment of the feed split ratio is important in the optimization
use at 8.0 bar, as commercial LPG can be condensed with cooling (Figure 9). A feed split ratio of 15% is optimal, reducing reboiler
water at this pressure. The feed composition, temperature, and duty and operating costs by 47.43% and 9.64%, respectively.
10026 dx.doi.org/10.1021/ie2029283 | Ind. Eng. Chem. Res. 2012, 51, 10021−10030
Industrial & Engineering Chemistry Research Article
Figure 11. Three-dimensional response surface plots of interactions between the main design variables N1, N2, and N3.
Figure 14. Integration of NGL recovery and NG liquefaction for FLNG processing.
value by the software. The greatest reboiler duty saving (11.89%) natural gas is first precooled using refrigeration from the
was predicted to have coded levels of −0.8192, 0.8192, and −1 liquefaction process and then introduced into the demethan-
corresponding to the numbers of trays in the top, bottom, and izer. A methane-rich overhead stream is formed, which is then
feed rectifying sections, respectively (Figure 12). The variables’ cooled, condensed, and subcooled during liquefaction. A por-
natural values can be derived from the coded levels. The tion of HHK refrigerant is expanded after the vapor−liquid
optimized TDWC system (Figure 13) had a simulated saving of separator to reduce the temperature. This stream is then used
11.79%, in good agreement with the predicted value. to condense the top vapor stream of the depropanizer. By
This column can be used to integrate two columns, whose integrating liquefaction and liquid recovery, investment and
condensers are cooled by different coolants; particularly the operating costs can be reduced along with the space required
depropanizer requires refrigeration, while the debutanizer can for the plant.
condense the top vapor stream under water cooling. Table 3
lists the conditions and the energy requirements of the TDWC. 5. CONCLUSIONS
The simulation results show that the TDWC can save up to
Several new, energy-efficient, compact, single mixed refrigerant
35.09% of refrigeration costs compared with a conventional
cycles were proposed for offshore FLNG plants. All the opti-
column sequence. The duties of condenser (C3) and the
mized proposed cycles showed improved performance com-
reboiler can be reduced by 21.42% and 11.79%, respectively.
pared with the conventional SMR process in terms of specific
Using a 1.5 m diameter TDWC could reduce energy consump-
power. In particular, Cycle-3 was most suitable for a FLNG
tion by 15.36% in terms of TAC compared with a conventional
plant with its simpler structure, showing only a slight degradation
column sequence. Therefore, the proposed TDWC can reduce
of efficiency than Cycle-2.
energy consumption (refrigeration energy and reboiler and
A new, energy-efficient, compact NGL recovery process was
condenser duty) and investment costs (replacing two columns
also proposed for offshore FLNG plants by utilizing the DWC.
with one and eliminating a reboiler).
In the proposed NGL recovery process, feed splitting could
eliminate the demethanizer reboiler and reduce precooling
4. INTEGRATION OF LIQUEFACTION AND RECOVERY energy. Operating costs were minimized at a feed split ratio
PROCESSES of 15%. The proposed TDWC allows more energy-efficient
Integrating liquefaction and recovery processes (Figure 14) depropanization and debutanization with a single compact
could make a plant more efficient and save money. The treated column.
10028 dx.doi.org/10.1021/ie2029283 | Ind. Eng. Chem. Res. 2012, 51, 10021−10030
Industrial & Engineering Chemistry Research
■
Article
■
Notes
The authors declare no competing financial interest.
■
APPENDIX
Column Cost Correlations ACKNOWLEDGMENTS
a. Column Sizing. Column diameter was determined by a
flooding condition that fixed the upper limit of vapor velocity. This research was supported by a grant from the Gas Plant
Operating velocity is normally 70−90% of the flooding velocity.33,34 R&D Center funded by the Ministry of Land, Transportation
and Maritime Affairs (MLTM) of the Korean government.
■
Here, 80% of the flooding velocity was used.
b. Capital Cost. Guthrie’s modular method was applied.35
The investment cost for conventional distillation is the total NOMENCLATURE
cost of the column and auxiliary equipment such as reboilers C1 = methane
and condensers. For the DWC, additional dividing wall costs C2 = ethane
are considered. The Chemical Engineering Plant Cost Index of C3 = propane
575.4 was used here for cost updating. C4 = butane
C5+ = gasoline
updated bare module cost (BMC) = UF × BC B = bottom product flow (kg/h)
D = top product flow (kg/h)
× (MPF + MF − 1) (3)
DWC = dividing wall column
where UF is the update factor, F = Feed flow (kg/h)
LPG = liquefied petroleum gas
present cost index TDWC = top dividing wall column
UF =
base cost index (4) Subscripts and Superscripts
V = vapor
■
BC is bare cost, for vessels,
⎛ L ⎞α ⎛ D ⎞β REFERENCES
BC = BC0 × ⎜ ⎟ × ⎜ ⎟ (1) Kidnay, A. J.; Parrish, W. R. Fundamentals of Natural Gas
⎝ L0 ⎠ ⎝ D0 ⎠ (5) Processing; Taylor and Francis: Boca Raton, 2006.
For the heat exchanger, (2) Elliot, D.; Qualls, W. R.; Huang S.; (Roger) Chen J. J. Benefit of
Integrating NGL Extraction and LNG Liquefaction Technology.
⎛ S ⎞α AIChE Spring National Meeting, 5th topical conference on Natural
BC = BC0 × ⎜ ⎟ Gas Utilization (TI) Session 16c-Gas; Conoco Phillips Co.: Houston,
⎝ S0 ⎠ (6) TX, 2005.
(3) Sheffield, J. A. Offshore LNG ProductionHow to Make it
The area of the heat exchanger, S, is Happen. Business Brief ing: LNG Review; Touch Oil and Gas: London,
2005.
Q (4) Long, N. V. D.; Lee, M. Y. Improvement of Natural Gas Liquid
S=
U ΔT (7) Recovery Energy Efficiency through Thermally Coupled Distillation
Arrangements. Asia Pac. J. Chem. Eng. 2012, 7, S71−S77.
where MPF is the material and pressure factor and MF is the (5) Manley, D. B. Deethanizer/Depropanizer Sequences with
module factor (a typical value), which is affected by the base Thermal and Thermo-mechanical Coupling and Component Dis-
cost. D, L, and S are diameter, length, and area, respectively. tribution. U.S. Pat. 5,673,571, 1997.
c. Operating Cost (Op). (6) Mak, J. Configurations and Methods for Improved NGL
Recovery. U.S. Pat. 7,051,552, 2006.
Op = Csteam + CCW + Crefrigeration + Celectric (8) (7) Long, N. V. D.; Lee, M. Y. Improvement of the Deethanizing and
Depropanizing Steps in NGL Recovery Process Using Dividing Wall
where Cstream is the cost of the steam; CCW is the cost of cooling Column. J. Chem. Eng. Jpn. 2012, 45, 1−10.
water; Crefrigeration is the cost of refrigeration, and Celectric is the (8) Manley, D. B. Multiple Effect and Distributive Separation of
cost of electricity. Isobutane and Normal Butane. U.S. Pat. 8,806,339, 1998.
d. Total Annual Cost (TAC).36 (9) Campbell, R. E.; Wilkinson, J. D. Hydrocarbon Gas Processing. U.S.
Pat. 4,140,504, 1979.
i(1 + i)n (10) Montgomery, G. J. Ethane Recovery System. U.S. Pat.
TAC = capital cost × + Op
(1 + i)n − 1 (9) 4,851,020, 1989.
(11) Andress, D. L.; Watkins, R. J. Beauty of Simplicity: Phillips
where i is the fractional interest rate per year and n is the Optimized Cascade LNG Liquefaction Process. Adv. Cryogen. Eng.
number of years. 2004, 49, 91−98.
■ ASSOCIATED CONTENT
* Supporting Information
S
(12) Naklie, M. Mobil’s Floating LNG Plant. 12th International
Conference & Exhibition on Liquefied Natural Gas, Perth, Australia,
May 4−7, 1998.
(13) Lee, S.; Cha, K.; Park, C.; Lee, C.; Cho, Y.; Yang, Y. The Study
Temperature variation plots for the SMR and proposed cycles, on Natural Gas Liquefaction Cycle Development. The International
equations, and values of parameters for costing detail. This Society of Offshore and Polar Engineers 9th Pacific/Asia Offshore
material is available free of charge via the Internet at http:// Mechanics Symposium, ISOPE PACOMS, Busan, Korea, November
pubs.acs.org. 14−17, 2010.