Professional Documents
Culture Documents
Abstract—This paper describes modelling procedure for modelling of complete transmission line with large number
calculating energy stresses of transmission line surge arresters. input and output data.
A 110 kV shielded transmission line is modelled using
ElectroMagnetic Transient Program – Restructured Version
II. MODELLING PROCEDURE
(EMTP – RV). Some parts of transmission line such as
transmission line towers and stations on both ends of line are Transmission line is modelled into several parts: towers,
modelled thanks to EMTP – RV possibility of grouping insulators, phase conductors, shield wire, line surge arresters
electrical elements into subcircuits. Also it was possible to create and tower footing resistance. Lightning stroke is modelled as
subcircuit consists of number of other subcircuit. This a current source (so called 'I – point by point source'). The
possibility was very important for dividing transmission line
studied 110 kV transmission line is 42 km long, span or line
into number of sections that consists of number of towers.
Arrester current and voltage, energy duty, insulator voltage and length between two towers is considered as a mean value of
voltage on tower top due to bipolar lightning are calculated and 300 meters. It is taken that line has a different footing
presented. resistance along the line route, so tower footing resistance
value is varied. Soil resistivity is 1200 Ωm. In the case when
Keywords: Bipolar Lightning Stroke, Line Surge Arrester, tower is equipped with one LSA it is installed on bottom
Energy duty, EMTP – RV, Transmission line, Modelling, phase. For installation configuration with two LSA, LSA are
Simulation.
installed on bottom and middle phase [2].
I. INTRODUCTION A. Tower model
S. Grebovic is PhD student at Graz University of Technology and with Faculty Fig. 1. Tower representation.
of Electrical Engineering University of Sarajevo (e-mail: s_grebovic@aol.com). Each tower is divided in four parts. First part is section of the
S. Pack is with Institute of High Voltage Engineering and System Management, tower from bottom crossarm to the ground and it is
Graz University of Technology (e-mail: pack@tugraz.at).
S. Sadovic is with the Department of Electrical Engineering, Faculty of
represented as the propagation element, which is defined by
Electrical Engineering University of Sarajevo (e-mail: sadovic@aol.com). the surge impedance and the propagation length. In EMTP –
RV software this part is modelled as constant parameter (CP)
Paper submitted to the International Conference on Power Systems
and line model (1 – phase version). Second part is sections
Transients (IPST2015) in Cavtat, Croatia June 15-18, 2015
between tower top and top crossarm. Third and fourth part
are sections between crossarms. Sections on the tower top B. Line insulation flashover model
(between tower top and top crossarm and between crossarms) Insulators are modeled as Air Gap elements. It operates
are modelled as inductance branches. On this way it was based on equal area flashover model. Flashover occurs when
possible to calculate transient on tower top. Tower surge the following integral becomes greater or equal to D [3,4]:
impedance is calculated according tower shape theory. t K
Branch inductance is determined according to the section
t0
v gap t V0 dt D (1)
length, tower surge impedance and propagation velocity.
Wave propagation speed on the tower was taken to be equal to where:
the velocity of light [1]. vgap – voltage across insulator string
Figure 2 shows described tower model in EMTP – RV with V0 – reference voltage
insulators and pins that enable electrical connection with K=1
D=0,2045d
other elements. On this way it is possible to connect line
d – length of gap (m)
surge arresters in parallel to the phase conductor insulators
t – time to flashover (µs).
and model tower footing resistance.
CFO – critical flashover voltage can be represented by
T1
c
C1
0
2.8uH
L1
?vi>S +
A1 t
Air1
L2
B1 + ?vi>S
B2
Rated voltage: 108 (kVrms)
504kV
MCOV: 86 (kV)
IEC class: II
C2
0
c
L3
c
C3
0
?vi>S +
C1 represented by the U – I characteristic [2,3].
Air3
+
resistance
basically three types of bipolar lightning discharges, although
Fig. 2. Tower model in EMTP – RV.
some events may belong to more than one category [6, 8].
Pin for connection Lightning current (bipolar) shown on Figure 4 was
DEV1
with tower top
Tower top measure on Corsica. The negative charge transfer is
Phase A
A2 determined by integrating the absolute value of the current
Pins for
connection with over the negative current component duration. The positive
phase A charge transfer is determined by integrating the current over
B2 A1
Pins for
Phase B
the positive current component duration. The trapezoidal rule
connection with
phase B
is used for integration. The total transfer is summary of the
B1 Phase C C2 negative and positive charge transfers. The negative part has
Pins for peak current of -52,86 kA and positive part has peak current
connection with
phase C of +26,3 kA, with total charge transfers being -3,3025 As and
C1
+1,2414 As, respectively.
Pin for connection Grounding
Lightning stroke is modelled as a current source (so called
with tower footing 'I – point by point source') because it is possible to import
resistance
measured data point by point. The current shapes and values
Fig. 3. EMTP – RV symbol for tower subcircuit. can be changed in order to study different lightning stroke
All elements shown on Figure 2 are grouped in subcircuit. currents.
This subcircuit is illustrated on Figure 3 and can be use many
times for modelling complete transmission line.
Bipolar Lightning Current
40
t =55,2 (s) t =81,2 (s)
SADOVIC measurements
1
t2 =78,5 (s) 3
30
20
10
0
Current (kA)
-10
-20
-30
-40
-50
-60
0 100 200 300 400 500 600
Time (s)
Middle of
the span for
phase A
Middle of Middle of
the span for the span for
shield wire phase B
Connection Middle of
with tower the span for
top phase C
DEV1
T_1_2_s
T_1_2_c
T_2_3_s
T_2_3_c
T_3_4_s
T_3_4_c
T_4_5_s
T_4_5_c
T_5_6_s
T_5_6_c
T_6_7_s
T_6_7_c
T_7_8_s
T_7_8_c
T_8_9_s
T_8_9_c
T_9_10_s
T_9_10_c
T1
T2
T3
T4
T5
T6
T7
T8
T9
T10
T_1_2_a
T_1_2_b
T_2_3_a
T_2_3_b
T_3_4_a
T_3_4_b
T_4_5_a
T_4_5_b
T_5_6_a
T_5_6_b
T_6_7_a
T_6_7_b
T_7_8_a
T_7_8_b
T_8_9_a
T_8_9_b
T_9_10_a
T_9_10_b
S_1 S_10
A_1 A_10
B_1 B_10
C_1 C_10
Section_from_1_to_10
Energy (kJ)
5
TABLE I
CPU TIMINGS (S) 4
Total 27,18750
400
200
Figure 4. -200
0
2.5
-200
Voltage(kV)
2
-400
-600
Current (kA)
1.5
-800
1
-1000
0.5 -1200
-1400
0 100 200 300 400 500 600
0 Time ( s)
Fig. 10. Voltages on the tower top and at the bottom phase – case 1.
-0.5
0 100 200 300
Time (s)
400 500 600
Second case is that lightning hitting tower top and on
Fig. 6. Current through arrester – case 1. tower are installed two line surge arrester and tower footing
Arrester voltage
300
Arrester voltage - bottom phase
resistance is 50 Ω. On Figures 11 and 12 are presented
respectively currents and voltages for arresters installed on
200
bottom and middle phase.
Arrester current
100 4
Arrester current - bottom phase
Arrester current - middle phase
Voltage (kV)
3.5
0
3
2.5
-100
2
Current (kA)
-200 1.5
-300
0 100 200 300 400 500 600 0.5
Time (s)
0
Fig. 7. Arrester voltage – case 1.
On Figure 8 is shown energy duty for arrester installed on -0.5
-1
bottom phase. Voltage waves across insulators are presented 0 100 200 300
Time (s)
400 500 600
on Figure 9. Coupling between the shield wire and the phase Fig. 11. Currents through arresters – case 2.
Arrester voltage
300
Arrester voltage - middle phase
respectively currents and voltages for arresters installed on
Arrester voltage - bottom phase
bottom, middle and top phase.
200
Arrester current
5
Arrester current - top phase
Arrester current - middle phase
100 Arrester current - bottom phase
4
Voltage (kV)
0
3
Current (kA)
-100
2
-200
1
-300
0 100 200 300 400 500 600
Time (s) 0
on bottom and middle phase. Voltage waves across insulators Fig. 16. Currents through arresters – case 3.
are presented on Figure 14. Voltages on the tower top and at 300
Arrester voltage
100
10
Voltage (kV)
0
8
Energy (kJ)
-100
6
-200
4
-300
2 0 100 200 300 400 500 600
Time (s)
Energy duty for arrester installed on middle phase
Energy duty for arrester installed on bottom phase
Fig. 17. Voltages on arresters – case 3.
0
0 100 200 300
Time (s)
400 500 600
On Figure 18 is shown energy duty for arresters installed
Fig. 13. Energy duties for arresters – case 2. on bottom, middle and top phase. Voltage waves across
Voltage across insulator strings
800
Voltage across insulator strings - top phase
insulators are presented on Figure 19. Voltages on the tower
Voltage across insulator strings - middle phase
Voltage across insulator strings - bottom phase top and at the bottom phase are shown on figure 20.
600
Energy duty
14
400
12
Voltage(kV)
200 10
8
Energy (kJ)
6
-200
4
-400
0 100 200 300 400 500 600
Time (s)
2
Energy duty for arrester installed on top phase
Fig. 14. Insulator voltages – case 2. Energy duty for arrester installed on middle phase
Energy duty for arrester installed on bottom phase
Voltage on tower top and at bottom phase 0
1000 0 100 200 300 400 500 600
Voltage on tower top Time (s)
Voltage at bottom phase
500
Fig. 18. Energy duties for arresters – case 3.
Voltage across insulator strings
300
Voltage across insulator strings - top phase
0 Voltage across insulator strings - middle phase
Voltage across insulator strings - bottom phase
200
Voltage(kV)
-500
100
Voltage(kV)
-1000
-1500
-100
-2000
0 100 200 300 400 500 600
Time (s) -200
Fig. 15. Voltages on the tower top and at the bottom phase – case 2.
Third case is that lightning hitting tower top and on tower -300
0 100 200 300 400 500 600
Time (s)
are installed three line surge arrester and tower footing Fig. 19. Insulator voltages – case 3.
resistance is 60 Ω. On Figures 16 and 17 are presented
1000
Voltage on tower top and at bottom phase
-500
duty depends of arrester current shape. So, a knowledge of the
-1000
occurrence and characteristics of bipolar lightning is needed
for the selection of the arrester class (arrester block size) as
-1500
well as for designing adequate lightning protection schemes
-2000
for various objects and systems.
0 100 200 300 400 500 600
Time (s)
Fig. 20. Voltages on the tower top and at the bottom phase – case 3. VI. REFERENCES
In Table 2 are presented LSA current and voltage peaks [1] S. Sadovic, M. Babuder, M. Hrast, D. Bokal, M. Marnisek and T. Sadovic,
and energies for all three cases. "Line Surge Arrester Application on 123 kV Double Circuit Line",
TABLE II International Symposium on High Voltage Engineering, Johannesburg,
LSA DATA South Africa, 2009.
CASE Phase U (kV) I (kA) W (kJ) [2] A. Xemard, S. Sadovic, T. Sadovic, M. Mesic, A. Guerrier, "Lightning
Bottom 256,27 2,86 8,24 current measurement on an overhead line equipped with line arresters",
CIGRE Colloquium, 2010.
1 LSA Middle - - -
[3] T. Sadovic, S. Sadovic, "EMTP – RV modelling for the transmission line
Top - - - lightning performance computation", User Group Meeting, 20 April
Bottom 263,15 3,52 11,93 2009, Dubrovnik, 2009.
2 LSA Middle 263,27 3,54 9,73 [4] IEEE Guide for Improving the Lightning Performance of Transmission
Top - - - Lines, IEEE Standards Department, June. 1996.
Bottom 269,28 4,23 12,38 [5] CIGRE WG C4.407, "Lightning Parameters for Engineering
3 LSA Middle 261,18 3,32 9,68 Applications", CIGRE Technical brochure no 549, August 2013.
Top 250,67 2,28 6,15 [6] V.A. Rakov, M.A. Uman, "Lightning Physics and Effects, Cambridge
Univ. Press, Cambridge, U. K, 2003, pp. 232-240.
In table 3 are shown peak values of insulator voltages. [7] K. Narita, Y. Goto, H. Komuro, and S. Sawada, "Bipolar lightning in
TABLE III winter at Maki, Japan" J. Geophys. Res., vol. 94, 13,191-13,195, 1989.
INSULATOR VOLTAGES [8] V.A. Rakov, "A Review of Positive and Bipolar Lightning Discharges",
American Meteorological Society, 2003.
CASE Phase Ui (kV)
Bottom 256,35
1 LSA Middle (no LSA) 771,38
Top (no LSA) 786,59
Bottom 263,15
2 LSA Middle 263,53
Top (no LSA) 793,29
Bottom 269,49
3 LSA Middle 261,63
Top 251,37
V. CONCLUSIONS
This paper presents powerful and effective EMTP – RV
modelling. Grouping of elements into subcircuits and creating