Professional Documents
Culture Documents
PMP Cheat Sheet PDF
PMP Cheat Sheet PDF
EAC = BAC / CPI Tools: Interviews, Sensitivity Analysis, Decision Tree Analysis, 27. Manage Project Team
EAC = AC + ETC Simulation, Monte Carlo Analysis. Project Communications
EAC = AC + (BAC + EV) / CPI Closing Management
ETC = EAC - AC Contract Close: Before project close 28. Identify Stakeholders
Project or Phase Close: Lessons Learned
VAC = BAC - EAC 29. Plan Communications
PMI Code of Ethics: Respect, Fair, Honest.
BCWS = PV 30. Distribute Information
BCWP = EV Key Formulas Time Management 31. Manage Stakeholder Expectations
ACWP = AC Standard Deviation = (P - O) / 6 Precedence Diagramming Method 32. Report Performance
Tips: PERT = (O + 4M + P) / 6 PDM: Activity-on-Node (AON)
Project Risk Management
Negative is bad Total Float = LS—ES or LF –EF Arrow Diagram Method
33. Plan Risk Management
Positive is good ADM: Activity-on-Arrow (AOA)
Comm Channels = N (N-1) / 2 34. Identify Risks
If Variance: EV - Something Where: Conditional Diagram Method
If Index: EV / Something Graphical Evaluation and Review 35. Perform Qualitative Risk Analysis
P = Pessimistic
If Cost related use AC O = Optimistic Technique (GERT): Allows loop 36. Perform Quantitative Risk Analysis
If Time related use PV M = Most likely; Realistic Crashing: Add more resources 37. Plan Risk Responses
Most formulas start with EV N = # Project Members Fast Tracking: Tasks in parallel 38. Monitor and Control Risks
Benefit Cost Ratio = Forward Pass: Early start, early Project Procurement Management
Rules Based on Numbers Cost / Benefits finish
BCR < 1 Unfavorable 39. Plan Procurements
80 Hour Rule = Max size of Backward Pass: Late start, late
work packages BCR > 1 Higher is Better 40. Conduct Procurements
finish
80/20 Rule = Pareto’s Law Net Present Value = 41. Administer Procurements
Float; Slack: activity margin off
20% of causes responsible for FV / (1 + r)^n critical path 42. Close Procurements
80% of problems Future Value =
PV (1 + i)^n Free Float: activity margin not
0/50/100 = Work package impacting early start of next de- Copyright © 2009 PMServicesNW
completion. No credit until Internal Rate of Return pendant activity All rights reserved
50% complete. No additional Higher is better
Project Float www.PMServicesNW.com
credit until 100% complete. Six Sigma: 99.99% defect free