You are on page 1of 1

42 Project Management Processes

PMP Cheat Sheet and Study Notes


Based on PMBOK V4 Project Integration Management
The reader is responsible to verify and confirm all information presented herein. 1. Develop Project Charter
2. Develop Project Management Plan
Processes Human Resource Management
3. Direct / Manage Project Execution
Initiation Organizational Structures: Functional, Matrix (weak, balanced,
strong) , Projectized, Composite 4. Monitor / Control Project Work
Planning
Maslow’s Hierarchy of Needs: Physiological, Safety, Social, Self 5. Perform Integrated Change Control
Execution -esteem, Self-actualization. 6. Close Project or Phase
Monitor and Control McGregor: Theory X, Theory Y. Project Scope Management
Closing Ouchi: Theory Z. Motivated by commitment, opportunity advancement.
7. Collect Requirements
Knowledge Areas Herzberg’s Theory of Motivation: Hygiene factors, Motivating Agents.
8. Define Scope
Integration Leadership Styles: Directing, Facilitating, Coaching, Supporting,
Autocratic, Consultative, Consensus. 9. Create WBS
Scope Management
Project Manager Powers: Formal (legitimate,) Reward, Penalty 10. Verify Scope
Time Management
(coercive), Expert, Referent. 11. Control Scope
Cost Management Conflict Management: Withdraw (avoid), Smooth (accommodate), Project Time Management
Quality Management Compromise, Force, Collaborate, Confront (problem solving.)
12. Define Activities
HR Management Quality Management
13. Sequence Activities
Communications Management Ishikawa = Fishbone Diagram: cause and effect.
14. Estimate Activity Resources
Procurement Management Pareto Diagram: Identify problems and frequency. 80/20 Rule.
Flow Charts; Control Charts. 15. Estimate Activity Durations
Risk Management
Just in Time: Reduces inventory; requires additional quality control. 16. Develop Schedule
Professional Responsibility
Quality Theories: Kaizen (continuous improvement,) Six Sigma, TQM 17. Control Schedule
(total quality management.) Project Cost Management
Earned Value Management
Kaizen: Small improvements to reduce costs and improve consistency. 18. Estimate Costs
BAC = Budget At Completion
Deming Cycle: Plan, Do Check, Act. 19. Determine Budget
EV = Actual % * BAC
Cost Management
PV = Planned % * BAC 20. Control Costs
Cost Estimating - Accuracy
AC = Sum of all incurred costs Rough Order of Magnitude (ROM): -50% to +100% Project Quality Management

CV = EV - AC Budgetary: -10% to +25% 21. Plan Quality


Definitive: -5% to + 10% 22. Perform Quality Assurance
SV = EV - PV
Risk Management 23. Perform Quality Control
CPI = EV / AC
Risk Strategies (threats): Avoid, Transfer, Mitigate, Accept. Project Human Resource
< 1 = Over Budget
Risk Strategies (opportunities): Exploit, Share, Enhance, Accept. Management
> 1 = Under Budget
Qualitative Risk Analysis: Chance and impact of risk occurrence 24. Develop Human Resource Plan
SPI = EV / PV Results in prioritized list of risks; risk ranking.
< 1 = Behind Schedule 25. Acquire Project Team
Quantitative Risk Analysis: Numerical analysis of probability
> 1 = Ahead of Schedule and impact. 26. Develop Project Team

EAC = BAC / CPI Tools: Interviews, Sensitivity Analysis, Decision Tree Analysis, 27. Manage Project Team
EAC = AC + ETC Simulation, Monte Carlo Analysis. Project Communications
EAC = AC + (BAC + EV) / CPI Closing Management
ETC = EAC - AC Contract Close: Before project close 28. Identify Stakeholders
Project or Phase Close: Lessons Learned
VAC = BAC - EAC 29. Plan Communications
PMI Code of Ethics: Respect, Fair, Honest.
BCWS = PV 30. Distribute Information
BCWP = EV Key Formulas Time Management 31. Manage Stakeholder Expectations
ACWP = AC Standard Deviation = (P - O) / 6 Precedence Diagramming Method 32. Report Performance
Tips: PERT = (O + 4M + P) / 6 PDM: Activity-on-Node (AON)
Project Risk Management
Negative is bad Total Float = LS—ES or LF –EF Arrow Diagram Method
33. Plan Risk Management
Positive is good ADM: Activity-on-Arrow (AOA)
Comm Channels = N (N-1) / 2 34. Identify Risks
If Variance: EV - Something Where: Conditional Diagram Method
If Index: EV / Something Graphical Evaluation and Review 35. Perform Qualitative Risk Analysis
P = Pessimistic
If Cost related use AC O = Optimistic Technique (GERT): Allows loop 36. Perform Quantitative Risk Analysis
If Time related use PV M = Most likely; Realistic Crashing: Add more resources 37. Plan Risk Responses
Most formulas start with EV N = # Project Members Fast Tracking: Tasks in parallel 38. Monitor and Control Risks
Benefit Cost Ratio = Forward Pass: Early start, early Project Procurement Management
Rules Based on Numbers Cost / Benefits finish
BCR < 1 Unfavorable 39. Plan Procurements
80 Hour Rule = Max size of Backward Pass: Late start, late
work packages BCR > 1 Higher is Better 40. Conduct Procurements
finish
80/20 Rule = Pareto’s Law Net Present Value = 41. Administer Procurements
Float; Slack: activity margin off
20% of causes responsible for FV / (1 + r)^n critical path 42. Close Procurements
80% of problems Future Value =
PV (1 + i)^n Free Float: activity margin not
0/50/100 = Work package impacting early start of next de- Copyright © 2009 PMServicesNW
completion. No credit until Internal Rate of Return pendant activity All rights reserved
50% complete. No additional Higher is better
Project Float www.PMServicesNW.com
credit until 100% complete. Six Sigma: 99.99% defect free

You might also like