Professional Documents
Culture Documents
V100R010C10
Installation Guide
Issue: 01
Date: 2015-07-30
Diagonal pliers Cable cutter Wire stripper RJ11 crimping tool Power cable crimping
tool
Phillips torque
screwdriver
ESD gloves Protective gloves Torque wreench (bore crown saw (Ø60 bore) (M4 to M6)
size: 10 mm)
- - -
Port Description
Port Description
Micro SD Anchor slot for the Micro SD card ussed for deployment
Mini USB Port for clock output
Micro SIM Anchor slot for the Micro SIM card used
u for EAP-AKA authentication
RGPS Port for clock synchronization
PoE Port for transmission and power suppply
Use for anti-theft of the BTS3911B Anti-theft
A locks are not delivered, and they must be prepared
by customers if required
PSE
Port Description
- Power port that supplies power to the PSE
DATA Data input port that connects to transmission
equipment of an operator
PoE PoE output port that connects to the BTS3911B
3
Installation Scenarios
Installation Installation Requirements Installation Diagram
Scenarios Modes
Installing a
BTS3911B on Through an
• The wall can bearr a load at least four times
a wall attachment the weight of a BT
TS3911B.
• The thickness of th
he wall is less than 45 mm.
plate
NOTE
When the wall (weak wall such as EPS S or MDF walls, or walls that cannot be drilled) does not
have a capacity of bearing at least fourr times the weight of the BTS3911B, add an attachment
plate and follow the preceding installattion methods to secure the BTS3911B on the attachment
plate.
• The ceiling, such as
a a concrete ceiling, can
bear a load at leasst four times the weight of
the BTS3911B.
By drilling holes • The screws must be b tightened with a torque
of 1.5 N·m. This ensures the screws work
properly and the ceiling
c remains intact
without cracks in it.
4
Clearance Requirements
z For a BTS3911B z For a PSE
Other Requirements
• The BTS3911B cannot be installed near air con nditioner outlet or near other heat-generating
appliances.
• The BTS3911B cannot be installed near a stron ng heat source of any kind
kind.
• The BTS3911B cannot be installed near placess where water may leak or drip, such as near
outdoor air conditioner units, water pipes, pipelines, and roofs with water leaks or dripping runoff.
• The installation must be protected against rain. No window exists at either side of the wall where
the BTS3911B is installed.
• The installation position must be far away from high voltage, highly corrosive devices, flammable
or explosive substances, and electromagnetic interference.
• The BTS3911B must be installed in a dry dry, well-v
well ventilated,
v
ventilated and dustproof place
place.
• If the BTS3911B is installed in parking areas orr basements, the installation position must be well
ventilated.
5
Installation Process
6
Installing a BTS3911B
BTS3911B can be installed on a wall or ceiling.
Mounting Kits
z Installation on a wall or ceiling by drilling holes z Installation on a plate, keel or steel hangers
Mark anchor p
points Drill holes and install Insttall mounting
g kits Install the BTS3911B on the wall
plastic expansion
sleeves
Mark anchor points Install mounting kitts Install the BTS3911B on the ceiling plate
Fit the rotation axis on the
BTS3911B into the hooks on the
mounting bracket.
Push the BTS3911B against the
mounting bracket until a click is
heard.
7
Installing a BTS3911B on a Ceiling
By drilling holes
Mark anchor points Drill holes and install Insstall mounting kits Install the BTS3911B on the ceiling
plastic expansion
sleeves
By using a keel
Mark anchor points Install mounting kits Install the BTS3911B on the plate
Plate U-shaped keel
By
y using
g a steel hangers
g
Installing steel Installing the U-shaped Insstalling the mounting Installing a BTS3911B
hangers metal plate onto the braacket
steel hangers
8
By an existing plate
(1) Plate
(2) Mounting bracket
(3) Anchor points
Use a hammer drill with Ф6 Fit the rotation axis on the BTS3911B into the
bore to drill holes hooks on the mounting bracket.
Push the BTS3911B against the mounting
bracket until a click is heard
heard.
Secure mounting kits to the ceiling plate Install the BTS3911B on the ceiling plate
9
(Optional) Locking the protection screw
The protection screw protects the BTS3911B from being removed and must be locked if required.
The following figure takes installation the BTS3911B on a steel hangers as an example.
M4 threaded hole
Quincunx screw
10
Installing BTS3911B and PSE Cables
Requirements for Cable Layout
z National Standards
- Code for Engineering Design of Generic Cabling Systtem for Building and Campus (GB 5031150311-2007)
2007)
- Code for Engineering Acceptance of Generic Cabling System for Building and Campus (GB50312-2007).
- Security Protection Engineering Technology Specifica ations (GB 50348-2004)
- Code for Construction and Acceptance of the Electron nic Information System Room (GB 50462-2008)
- Code for Quality Acceptance of the Intelligent Building
g Engineering (GB 50339-2003)
- Code for Quality Acceptance of Electric Engineering Construction
C in Building (GB 50303-2002)
- Technical Specification for Construction and Acceptan nce of Telecommunication Conduit Engineering
(GB 50374-2006)
z International Standards
- Generic Cabling for Customer Premises (ISO/IEC 118 801)
- Commercial Building Telecommunications Cabling Sttandard (EIA/TIA 568)
- Commercial Building Standard for Telecommunication n Pathways and Spaces (EIA/TIA 569)
- Administration Standard for Commercial Telecommun nications Infrastructure (EIA/TIA 606)
- Grounding and Bonding Requirements for Telecommu unications in Commercial Buildings (EIA/TIA 607)
- Generic Cabling Systems for Information Technology (EN 50173)
- C bli IInstallation
Cabling t ll ti ffor IInformation
f ti T Technology
h l (EN 50
0174)
z Cable binding
- Cables of the same type are bound together.
- Different types of cables must be separately routed withw a minimum spacing of 30 mm and cannot be entangled.
- The cables are bound tightly and neatly and the sheatths of the cables is intact.
- The cable ties face the same direction and all cable ties bound at similar positions must be in a straight line.
- The extra length of each indoor cable tie must be cut off. A slack of 5 mm is reserved for each outdoor cable tie
before the extra length is cut off. All cut surfaces are without
w sharp edges.
- Labels or nameplates are attached to both ends, jointts, or turns of cables after they are installed.
z Safety
- The steel pipe or fire-resistant rigid polyvinyl chloride pipe should be used for the cable duct or for routing
cables. The cross-sectional usage of the cable duct should be 30% to 50% and that of the pipe for routing
cables should be 25% to 30%.
- Cables are placed away from sharp objects or wall bu urrs. If these positions are inevitable, protection pipes are
required for the cables.
- Cables are routed away from heat sources, or heat-insulation materials are added between cables and heat
sources.
- A clearance is reserved at turns of a cable or the position close to a device, facilitating cable and device
maintenance. The recommended clearance is about 0.1 0 m.
11
Installing the cables
NOTE
• The total length of cables connected between the
BTS3911B, PSE, and external transmission device does
not exceed 100 m.
• RGPS signal cables, when routed outdoors, must be led
through PVC pipes instead of metal pipes.
• The lightning rod is prepared by customers
customers, when using
RGPS antenna.
Installation Check
SN Check Item
1 The installation position conforms to the engineering design and meets clearance requirements.
2 The BTS3911B is securelyy installed.
In wall-mounted scenarios, the holes on the mounting g bracket are well aligned with the holes of the expansion
3
bolt assemblies. In addition, the mounting bracket is secured
s on the wall evenly and tightly.
The surface of the BTS3911B is neat and clean. The external paint is intact. The labels, tags, and nameplates are
4
correct, legible, and complete.
In the wall-mounted scenario, the holes of the mountiing bracket are well aligned with the holes of the expansion
5
bolt assemblies. In addition, the mounting bracket is secured
s on the wall evenly and steadily.
None of power cables or signal cables is short-circuitted or reverse connected. All cables are not damaged or
6
broken.
7 Th power cables
The bl are b boundd and
d routed
t d separately
t l ffrrom other
th cables.
bl
8 The connectors of the signal cables are intact and securely connected. The signal cables are intact.
9 Labels are correct, legible, and complete at both endss of each cable.
Power-on Check
Check Process Checking the Indicator Status
If… Then…
NOTE
• During the BTS3911B startup, there is no need to
observe the indicator status.
• During a start, the BTS3911B reads and writes the
flash and therefore the indicators blinking quickly
may blink irregularly for 1-2 seconds, which does not
affect services.
services
• The other status of indicator, see Ports and
Indicators in BTS3911B Product Description.
12
Appendix 3: WIFI MAC and ESN collectio
on template
The WIFI MAC and ESN collection template is used to reccord the installation position and WIFI MAC and ESN of
the site at the initial installation stage to facilitate subsequ
uent commissioning and maintenance.
Site
No. Site Name ESN WIFI MAC Location Information
Number
Note: This template is essential to the engineering stage and subsequent maintenance, especially when multiple
devices are installed within a short distance. This is beca
ause the template defines the radio network to access.
Please carefully maintain this template.
HUAW
WEI TECHNOLOGIES CO
CO., LTD
LTD.
H
Huawei Industrial Base Bantian Longgang
Shenzhen 518129
People's Republic of China
www.huawei.com
13