Professional Documents
Culture Documents
L1.-Geotechncial Design and Uncertainty 2019
L1.-Geotechncial Design and Uncertainty 2019
1.2 Geotechnical elements in the context of the rest of the whole structure
All built structures touch the ground in some way and hence all need some form of
foundation. Other geotechnical elements include retaining walls and ground anchors.
Sometimes they can be shallow, e.g. pad footings or gravity retaining walls; other times
they are deep, such as piles or embedded retaining walls. Often they rely on geotechnical
processes such as ground improvement to produce a geotechnical element.
All foundations and other geotechnical elements have a number of characteristics that
distinguish them from other parts of the structures that they support:
1) they tend to be amongst the most heavily loaded elements in any structure;
3) their capacity is very dependent on the ground of the site, which is always
characterised by few observations and tests, and is normally very heterogeneous
and may contain hazards that are difficult to foresee;
4) their capacity is strongly influenced by the method of construction and how well it is
controlled.
Hence, the risk of failure tends to be significantly higher than that for other parts of the
structure. The management of ground uncertainty is an important part of the design and
construction process in order to produce elements that have the required degree of
reliability.
CIV E 489 Geotechnical Design L1: Overview 3 / 22
A vital consideration in geotechnical design is the interaction of the structural element
that is inserted into the ground with the ground itself – so-called ‘soil–structure
interaction’. Structural loads are applied to the element and the ground resists – generally
either by friction along the element, or by bearing of the element against the ground. Both
these resistances can occur vertically or horizontally, as shown in Figure 1.1. Normally
ground stresses are maintained within failure limits, so the resulting displacements
depend on the stiffness of both the element and the ground.
• They must not fail, or else the structure they support will also fail. In terms of limit
state design, failure by any mode is termed reaching or exceeding an ‘ultimate’ limit
state, and may involve failure of a structural element or rupture along a soil–
structure or a soil–soil interface.
• They must not move excessively or else the structure they support may become
impaired or fail to operate as intended. In terms of limit state design, excessive
deflection involves breaching a ‘serviceability’ limit state.
• They must last for as long as intended. Unlike many other building elements,
foundations are hugely difficult to upgrade or repair and so their longevity will often
dictate the life of the structure that they support.
1.3.2 Ultimate limit state modes of failure
There is a range of ways in which geotechnical structures can fail an ultimate limit state,
and these are shown in Figure 1.2.
• it has been subjected to physical processes, such as repeated loading cycles causing
fatigue, or excessive damage from impacts;
• it fails to meet new design or material standards and so offers a less than
acceptable level of resistance against load, corrosion, etc.
Relevant design lives for structures are defined in Canadian Building Code and are
generally distinguished according to whether the structure is a building or a piece of
infrastructure. The design life is project specific. Most permanent civil structures today
have a minimum design life of 100 years while temporary structures can be limited to <10
years.
• The consequences of failure – where the consequences are mild and do not
threaten safety, then a lower factor may be permissible provided the economic
consequences are judged and agreed as acceptable.
There are three distinct but interlinked aspects that have to be considered in tackling any
geotechnical engineering problem:
1 the ground profile including groundwater conditions;
2 the measured behaviour of the ground from Site investigations;
3 the appropriate model for assessing and predicting performance.
CIV E 489 Geotechnical Design L1: Overview 7 / 22
Figure: The geotechnical triangle. Each activity has its own distinct methodology and its own rigour
This formal design process was coined by Terzaghi and Peck in 1948. It was subsequently
published by: “Peck RB, 1969. Ninth Rankine Lecture: Advantages and limitations of the
CIV E 489 Geotechnical Design L1: Overview 8 / 22
a. Summarize available information for the site, including the history of the site
b. In an urban environment, be aware of environmentally contaminated soil;
i.e., old gas stations or businesses that use hazardous chemicals (dry cleaners)
c. Develop a geological (soil, rock, water) profile of the site and expected
Ground Characteristics (Soft or Firm soils, rock type, depth of water)
d. Assess the modes of failure that may be possible given the project scope and
the expected ground conditions.
3) Site Investigation
a. Field investigation Program
i. Drilling, sampling, in-situ testing
b. Laboratory testing program
4) Preliminary Design
a. Determine the geotechnical parameters needed for the design
b. Carry out the design calculations
5) Preliminary Risk Assessment: Assess the uncertainty in the choice of the
Geotechnical parameters on the Design
A Site Investigation (SI) should concentrate on the greatest uncertainties usually revealed
by the desk study. A ground investigation based on a poor desk study will inevitably be hit-
and-miss. Considering that less than 0.03% of the soil beneath is seen, it will tend to miss
CIV E 489 Geotechnical Design L1: Overview 10 / 22
more than it hits. A good site investigation will target the most likely hazards, which will
often be the near-surface stratum boundaries as man’s activities will tend to be more
erratic (in most cases) than geological processes.
The results from the Site Investigation are contained in a Geotechnical Data report. This
report does not assess the impact of the geotechnical description of the site, it simply
reports the data.
• Terms of reference of the investigation
• Scope of the investigation
• Procedures and equipment used in the investigation
• Proposed-structure or structures
• Geological setting
• Topography, vegetation, and other surface features
• Soil profile and properties
• Groundwater observations
• Existing adjacent structures
• Foundation studies, including alternatives
• Recommended field instrumentation and monitoring
• Recommended construction procedures, if appropriate
• Recommended field services
Conclusions and recommendations
• Limitations of the investigation
Often these man-made issues are a bigger risk for the project than normal geological
variability. SI that only consider, for instance, easily available mapping and not mapping
data that go back to the start of the site’s development, should be seen as potentially
deficient.
Example: Cost Estimate for Building Foundation
Desk study
$10,000
Ground investigation
• 5 Boreholes 20–40 m $50,000
• 10 Test pits $10,000
• Contamination testing $10,000
• Soils laboratory testing $10,000 $80,000
$90,000
1.7 Design Basis Memorandums
The basis for the design must be documented. This is usually contained in a Design Basis
Memorandum(s).
The purpose of these memorandums is to document all the calculations that forms the
basis of the design. These typically have multiple authors and are signed by the Design
Team.
There are tour distinct categories of calculation methods in geotechnical design as follows
I. Empirical Direct use of in-situ or laboratory test results, relying on
correlation with performance data and experience
2. Semi-empirical Indirect use of in-situ or laboratory test results, combining
field experience and simple theory
3. Analytical Theoretical models based on elasticity, plasticity, etc.
4. Numerical Complex soil models based at least in part on real soil
behavior
The complexity of soil behaviour has resulted in a need for empiricism and so a substantial
number of current design methods in geotechnical engineering practice fall in categories I
and 2. This has led to the development of a large number of design methods, each
applicable to one specific design case. Charts are frequently available to aid in design.
Because design methods were developed using properties determined in a particular
manner, it is important 10 follow design approaches in their entirety as the previous
success of the approach may rely on compensating errors. One area in which this is
particularly important is pile design. Pile installation alters soil properties. The magnitude
CIV E 489 Geotechnical Design L1: Overview 12 / 22
of the change in soil properties depends on the installation method and on the initial
conditions. This effect of changes in ground conditions as a result of foundation
construction must be specifically considered during site characterization and selection of
design parameters.
Historically, design has involved separate consideration of strength and deformation. Limit
equilibrium has been used to design against failure and linear elasticity or the non-linear
theory of consolidation has been used to estimate deformation. In the limit equilibrium
approach, the mobilized strength at failure will likely vary along the particular failure
surface under consideration and will differ from peak strength. Site variability and soil
strength anisotropy become important when selecting the design strength.
Advances in numerical modeling have given engineers the capability to model soil
response to all stages of site development. Constitutive models have been developed
which account for some or all of the above aspects of material behaviour. These models
have been implemented in numerical models in commercially available computer
programs. The determination of appropriate input parameters requires judgment and a
good understanding of soil behaviour. It is critical that any model used in design should be
calibrated by comparison to case histories of similar foundation elements or systems in
similar soil conditions.
Provides the basis for the design. Identifies the design constraints and significant
design issues. It also assesses potential constructability issues.
§ Given: Fill Elevation (set by client – a project constraint)
Stability:
• What are the maximum slopes for the fill – with what FoS?
• How fast can the fill be placed (metres/week)?
• Special loading conditions (seismic, embankment loading after
construction)
Settlement:
• How much will the fill settle?
§ What are the consequences – can it be tolerated?
• What is the time for the settlement?
§ Can the time for settlement be reduced?
CIV E 489 Geotechnical Design L1: Overview 13 / 22