ABSTRACT OF COST
Name of Works:Construction of Aqueduct
Location:Jajarkot
ITEM (I) Fabrication of gabion boxes including rolling , cutting and weaving
A. Hexagonal Mesh Size - 100 mm. X 120mm.
UNIT b. 3 X 1 X 1
Mesh wire 10 SWG. And Selvedge wire 8 SWG
S.N. 44.1 B (ii) Resp. Clause of Spec. 17-1.4,17-5 & 17-6
Source Type Quantity Unit Rate Amount Total (Rs.)
Labor Skilled 0.57 m-day 950.00 541.50 541.50
Unskilled 0.28 m-day 715.00 200.20 200.20
Constructio Mesh Wire 34.08 kg. 95.00 3237.60 3237.60
Materials Selvedge wi 4.03 kg. 95.00 382.85 382.85
Actual Rate 4362.15
Overhead @ 15 % 654.32
Sub Total 5016.47
Rate per m³ 1672.16