Professional Documents
Culture Documents
129, Kurfurstenstrasse
D-10785
Berlin
) eicontractors@compuserve.com
Please note: The contracts and guides contained in the present collection have
been selected for illustrative purposes only. Juris International shall not be liable
for their contents or use.
FIDIC and EIC have held many constructive discussions since the September 1997 draft of
the Conditions of Contract for EPC Turnkey Projects (known as the Silver Book) was issued.
As a result of these discussions and those held with other interested parties, the first edition
of the Silver Book has incorporated some improvements by comparison with the original
draft. To EIC however, the Silver Book represents such a significant departure from FIDIC's
traditional approach to the contractual and risk sharing relationship that has prevailed over
the years between Employer and Contractor that EIC has decided to take the unusual step
of publishing a contractor's guide to the Silver Book. Contractors often take comfort from the
fact that a contract is to be carried out under FIDIC terms and conditions but this will
certainly not be the case where the Silver Book is used. The purpose of this guide is to
highlight the potential risks and pitfalls.
It is FIDIC's view that the individual nature of the turnkey project invariably requires a fair
degree of flexibility on the part of Employer and Contractor and extensive negotiations are
essential prior to contract signature and they offer the Silver Book as a good starting point
for negotiation. EIC does not share this view and in the preparation of this guide, EIC has
tried to highlight for contractors, particularly those who may be confronted with this form of
turnkey contract for the first time, some of the more important issues to be addressed in bid
preparation and client discussions.
EIC wishes to make it clear that this document is not exhaustive and is intended for
guidance only. Expert legal advice should always be obtained before submitting an offer or
making any commitment to enter into a contract. Neither EIC nor the authors of this
document accept any responsibility or liability in respect of any use made by any person or
entity of this document or its contents which is and shall remain entirely at the user's risk.
To ensure that this Guide provides the maximum benefit, we would like to receive comments
from EIC member companies on its usefulness and relevance. We would particularly like to
hear about any contracts which have been put out to tender under the Silver Book. All
communications should be sent to the EIC Secretariat in Berlin.
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
Acknowledgements
EIC would like to thank the FIDIC Contracts Committee for the time they devoted to
explaining the philosophy behind the publication of the Silver Book and for listening patiently
to our arguments. We would also like to thank the Organisme de Liaison Industries
Metalliques Europeennes (ORGALIME) and Mr Robert Akenhead QC for the important
contributions they made in reviewing the final draft of this Guide and recommending
improvements.
EIC would also like to express its appreciation of the work carried out by members of the the
Conditions of Contract Working Group who produced this Guide: Lidia Amadio, Astaldi;
Louise Axton-Wilkins, Costain; Eric Eggink, Ballast Nedam; John Fenwick, Amec; Dr
Joachim Goedel, Hochtief; Frank Kennedy (Chairman), Carillion; Andrew Lee, Balfour
Beatty; Agne Sandberg, Skanska; Charles Shankland, Eiffage. Thanks also to the Working
Group's secretary Frank Kehlenbach and Martin Carrey of Carillion.
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
4
Executive Summary
In their Introductory Note to the Silver Book, FIDIC describe the benefits to the Employer of
turnkey project execution and state that passing responsibility for designing and constructing
the works to the Contractor will relieve the Employer of responsibility for close supervision of
the design and construction processes. FIDIC also maintain that there will be an increased
certainty of the final price and fewer disputes if the Contractor assumes responsibility for the
wide range of risks set out in the Silver Book. Regrettably, EIC cannot endorse this view
and believe that the Silver Book falls a long way short of meeting the objectives which FIDIC
set down for it.
Contractors accept that, by choosing a turnkey approach, Employers can reasonably expect
the Contract to transfer as much risk as practicable to the Contractor, offer a high degree of
certainty on the final price, facilitate the speedy completion of the Works and, in the event of
dispute, provide for their rapid resolution. Contractors on their part, are quite prepared to
contract on a turnkey basis and accept additional risk, provided that risks can be identified,
priced and managed, design and construction of the works is free of disruptive interference
and disputes are resolved quickly and equitably.
In a number of important respects, the Silver Book does not adequately satisfy the
respective aspirations of Employer and Contractor and its failure to do so is best illustrated
by consideration of those matters that most commonly give rise to disputes in turnkey
projects;
.inadequate definition of the scope of work,
.disruption of the design and construction process,
.inequitable allocation of risk and
.claims and dispute resolution.
It is stating the obvious to say that an offer to work on a fixed lump sum basis can only be
made if the Works are sufficiently well defined. This requires an adequate preliminary
design, comprehensive technical specifications and clear and unambiguous performance
criteria. The Contractor will carry out the majority of these tasks in a turnkey project.
However, it is essential that the Employer fully understands and accepts what is on offer and
the required clarity of understanding will only be achieved through detailed and lengthy
negotiation between employer and contractor. Manifestly, this cannot possibly be achieved
during the tender period with all bidders and, until such time as agreement has been
reached, any offer should remain conditional.
The obligations placed upon contractors by the Silver Book are onerous, whereas the
Employer's most significant responsibility is limited to providing a definition of the intended
purposes of the Works and setting criteria for testing and performance. The Employer is not
even responsible for the accuracy of the "Employer's Requirements"! The Contractor is
required to make all necessary investigations, verify relevant information and carry out
design in sufficient detail to price the Works. Such demands, combined with the allocation of
risks to the Contractor which may be impossible to predict or cost accurately, may make it
impossible for the Contractor to establish precisely the full scope and extent of his liability.
In particular, it will be practically impossible for the Contractor to fully comply with all of these
obligations during the tender period especially the full verification of the Employer's
Requirements and the development of a fully detailed design. Contractors must decide
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects
5
whether it will be feasible to clarify all of these matters following tender submission and prior
to the signature of a binding contract. In most circumstances, contractors will be well
advised to submit an appropriately conditioned offer which makes it clear that a full and
binding offer will only be made (to the extent that this is practically possible) following
extensive and conclusive negotiations.
Arguably I the submission of a qualified bid might lead to disqualification of the Contractor's
tender despite FIDIC's recommendation in their Introductory Note that it should be used as a
starting point for negotiations. Clarification of the Employer's position on qualified tenders
should be established before any decision is made to submit a bid.
In many instances, clauses in the Silver Book are in direct conflict with the obligations placed
on Contractors. Not only is the obligation to define the scope of the Works loosely defined, it
is also subject to reviews by the Employer who has the same power to interfere through
instructions, approvals, variations and determinations as the Engineer in a conventional
construct only contract. Paradoxically, should any Employer exercise his right to interfere in
this way it will inevitably undermine FIDIC's primary objective, certainty of the final price.
Only the Employer can make the choice of a turnkey contract and should only do so if he
has confidence in the competence, resources and experience of his potential Contractor. To
achieve this level of confidence demands a serious and comprehensive pre-qualification and
tendering process aimed at selecting the best contractor for the project. Thereafter, there
can be no justification for detailed supervision and interference and clearly specified
monitoring at defined milestone events should be perfectly adequate. For a Contractor to
enter into a contract of fixed time and price his obligations must also be fixed and once the
contract is signed, the Employer should not be able to unilaterally impose his will on the
design and construction process.
The extent to which the Employer might disrupt the design and construction process is the
most fundamental area of concern for contractors working on turnkey projects. FIDIC would
appear to accept this important principle by stating in the Introductory Note to the Silver
Book,
Consequently, in the event that the Employer orders the Contractor to design or construct all
or part of the works in a particular way, then the Employer must accept full responsibility for
the consequences of his actions. Should the Contractor be responsible for the achievement
of any Performance Criteria then the Contractor must have the right to refuse an instruction,
which, in his opinion, is likely to have an adverse effect on the achievement of the
Performance Criteria.
EIC accept that Contractors will bear considerably more risk under a turnkey contract
compared to that of a conventional construct only contract but EIC cannot accept the extent
to which Silver Book goes in attempting to make the Contractor responsible for almost every
eventuality however unforeseeable. EIC believe that the Employer cannot pass liability for
all risks to the Contractor and any contract signed under the Silver Book should clearly
EJC Contractor's Guide to the FJDIC Conditions of Contract for EPC Turnkey Projects
6
define where liability lies to ensure that contractors are in a position to accurately identify,
price and manage those risks which are to be their responsibility.
The Contractor must be especially alert to uninsurable risks, risks that are completely out
with his control or risks that are likely to increase as. a consequence of the actions of the
Employer or third parties. Contractors should also be wary of those clauses, which, as
drafted, could leave the Contractor at the mercy of an unscrupulous Employer.
However, it is probable that the greatest challenge and consequently the greatest risk will be
the difficulty of checking and confirming the accuracy or adequacy of the information and
data supplied by the Employer. Contractors who accept contracts under the Silver Book are
responsible for the accuracy and correctness of all information and data regardless of its
source. Contractors are advised to take particular care with clauses dealing with the
definition of fitness for purpose and liability for unforeseeable difficulties and adverse
physical conditions.
Despite FIDIC's claims to the contrary the Silver Book is likely to give rise to disputes
between the Parties unless several of its provisions are modified during negotiation. In
particular due to the time constraints placed on the Contractor to submit a notice of an
intention to claim are impractical and the sanctions for non-compliance are unreasonably
punitive. By contrast the Employer is neither required to observe similar time limits nor
suffer any sanction provided he gives notice as soon as practicable. This is yet another
example of an inequitable contract.
The Contractor should only be required to advise the Employer of an intention to claim as
soon as reasonably practicable and there should be no time deadline after which the
contractor would lose his rights. This should also apply to the procedure to be followed
where details of the claim are to be submitted. Events may have a continuing effect and it is
not always possible to establish the final effect resulting from an event until later.
If further evidence is required to demonstrate EIC's concerns regarding the Silver Book the
following comparison of these two books highlights how far FIDIC have departed from their
normal fair-handed and equitable distribution of risk and responsibility. Consequently the
Yellow Book provides a useful source of reference when drafting an alternative allocation of
risk and design responsibility. It is also extremely important to remember and to point out to
clients at every opportunity that FIDIC is well aware of the fact that the Silver Book is highly
unsuitable for certain types of turnkey projects. FIDIC makes this clear in the Introductory
Note to the First Edition by stating that it IS not suitable in the following circumstances and
that the Yellow Book should be used:
- If there is insufficient time or information for tenderers to scrutinise and check the
Employer's Requirements or to carry out the necessary designs, risk assessment studies
and estimating (taking particular account of Sub-Clauses 4.12 [Unforeseeable Difficulties]
and 5.1 [General Design Obligations])
- If construction will involve substantial work underground or work in other areas which
tenderers cannot inspect.
- If the Employer intends to supervise closely or control the Contractor's work, or to review
most of the construction drawings.
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects
If the amount of each interim payment is to be determined by an official or other
intermediary .
EIC consider that the following circumstances could be added to the list;
- Where part of the design is made by the Employer and is binding on the Contractor -see
also comments on Sub-Clause 5.1 [General Design Obligations] in this Guide.
- In competitive bidding without negotiations.
As a final word the principal differences between the Yellow and Silver Books are worth
highlighting:
It should be noted however, that the above only describes the overall responsibilities of the
parties and that important exceptions apply in each particular case.
Comments on a number of individual clauses follow and deal with the matters referred to
above in greater detail. Where considered appropriate comparative references are made to
the Yellow Book.
EIC Contractor's Guide to the FIOIC Conditions of Contract for EPC Turnkey Projects.
.
8
General Provisions
1.13 The Contractor shall comply with all applicable laws. However
the responsibility for obtaining permits, licenses or approvals is
Compliance
not entirely clear when Sub-Clauses 1.13 (a) and (b) are
with Laws
compared:
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
1
9
2
2.3 This Sub-Clause relates to the Employer's obligations in respect
of his personnel and contractors employed directly by him. It
Employer's should be noted that there is no express obligation on the
Personnel
Employer to secure generally that his other contractors co-
operate with the Contractor other than in the respects
identified.
2.4 FIDIC recognises the need for the Contractor to be satisfied that
the Employer has the necessary financial strength to undertake
Employer's his obligations under the Contract. This Sub-Clause requires
Financial that "the Employer shall submit, within 28 days after
Arrangements receiving any request from the Contractor, reasonable
evidence that financial arrangements have been made and
are being maintained which will enable the Employer to pay
the Contract Price".
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
10
Employer fail to furnish reasonable evidence. The Contractor is
entitled to suspend the work or terminate the Contract under
Sub-Clauses 16.1 [Contractor's Entitlement to Suspend Work]
and 16.2 [Termination by Contractor]. However, what
constitutes "reasonable evidence" is undefined and the
Contractor should establish this prior to submitting a tender.
Failure to do so could prejudice any attempt to obtain more
detailed information during the currency of the Contract, for
example in the event of a major Variation being instructed.
3
3.1 The Employer is completely free to appoint any person to act as
the Employer's Representative and/or to revoke any such
The Employer's
appointment. Invariably it will be important for the Contractor to
Representative establish whether that representative will be an independent
Consulting Engineer or a member of the Employer's personnel.
It is also important for the Contractor to be aware of the exact
nature of the duties and authority assigned to the
representative( s).
EIC Contractors Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
discretion and impartiality even when fulfilling the role of
Employer's Representative.
3.5 Notwithstanding the fact that FIDIC has drafted the Silver Book
as a two-party contract, the Employer is given the unilateral
Determinations
right under this Sub-Clause to determine matters in respect of a
broad range of matters. The thinking behind this was
presumably to ensure that decisions are taken when required to
minimise delay. The Employer has such rights in respect of the
Sub-Clauses listed below.
Erc Contractor's Guide to the FIDI.C Conditions of Contract tor EPC Turnkey Projects
12
17.4 [Consequences of Employer's Risks];
19.4 [Consequences of Force Majeure];
20.1 [Contractor's Claims].
It may seem strange that one of the parties has the right to
make determinations regarding the respective rights of the
parties. This was normally reserved for the truly impartial
engineer -a rare bird nowadays. However, the Contractor is
not obliged to give effect to the determination provided he gives
notice of his dissatisfaction within 14 days in which case the
determination is not binding.
4 The Contractor
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Project
Obligations] ,
- Nominated subcontractors, Sub-Clause 4.5 [Nominated
Subcontractors],
- Setting out, Sub-Clause 4.7 [Setting Out],
- Site Data, Sub-Clause 4. 10 [Site Data],
-
Unforeseen difficulties, Sub-Clause 4.12 [Unforeseen
Difficulties].
With regard to the full extent of the obligation to design for fitness
for purpose it may not be possible to pass the full liability on to
any third party design consultant appointed by contractors.
Current practice is for consultants to accept only an obligation to
design with "reasonable skill and care" because insurance to
cover the risk associated with fitness for purpose is not presently
universally available and is a particular. problem for British
consultants.
EIC Contractors Guide to the FIDICConditions of Contract tor EPC Turnkey Projects.
14
4.7 Taken at face value, the obligations under this Sub-Clause would
appear to be fair and reasonable and in accordance with normal
Setting Out
practice. "The Contractor shall set out the Works...and shall
be responsible for the correct positioning of all parts of the
Works, and shall rectify any error". However, Sub-Clause 5.1
[General Design Obligations], which deals with the Contractor's
design obligations, makes the Contractor responsible for the
accuracy of the information provided by the Employer! There are
some exceptions to this general requirement, but they are at
best, limited and somewhat confusing in their application. Two
courses of action are open to contractors:
-If practicable, check the setting out data prior to
submission of the tender, or
-Clarify the basis of the offer and propose that the
Employer retain responsibility under Sub-Clause 5.1.
4.10 The obligations and risks to consider under this Sub-Clause are
essentially similar to, but much more wide-ranging than, those
Site Data
identified above under Sub-Clause 4.7[Setting Out]. "The
Employer shall have no responsibility for the accuracy,
sufficiency or completeness of such data, except as stated in
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects
15
EIC Contractor's Guide to the FIDIC Conditions of Contract tor EPC Turnkey Projects.
16
On certain projects there could well be an inconsistency between
4.15
this Sub-Clause and Sub-Clause 2.1 [Right of Access to Site]
Access Route
which requires the Employer to give the Contractor the "right of
access" to the site. A matter to be clarified pre-contract.
5
A number of references have already been made to Clause 5,
largely because it deals with the responsibility of the respective
parties for the basic data, and it is for that same reason that it is
considered to be one of the most important in the Silver Book. As
has already been explained, Clause 5 [Design] establishes the
fundamental and crucial principle that the Contractor has wide
responsibility for the correctness of the Employer's Requirements
and there are only limited and inadequately defined exceptions to
this principle. It is in the Contractor's interest to make all
proposed exceptions clear and precise.
5.1 This is a complex Sub-Clause with many potential pitfalls for the
unwary and it is well worth having a further look at the major
General Design
disclaimer it contains. "The Employer shall not be responsible
Obligations for any error, inaccuracy or omission of any kind in the
Employer's Requirements as originally included in the
Contract". The problem created by this statement is particularly
evident when considering the important matter of the Employer's
responsibility for design criteria. This would normally be the
Employer's responsibility, yet the Silver Book fails to establish this
as a fundamental principle and this should be covered by the
exceptions provided for in this Sub-Clause.
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
17
only establish whether the design criteria are factually correct but
must also establish whether they are adequate to achieve the
desired performance and intended purpose, all in the limited time
available during the tender period! Inevitably, it will be prudent for
contractors to establish their own design criteria to ensure
compatibility with their own design and to make this an integral
part of the offer, even where design criteria have been provided
by the Employer.
EIC Contractors Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
18
Unfortunately, the Silver Book does not deal with the situation
where the Employer has provided no clear and identifiable
definition. If this important issue is left unresolved, it could well be
that the definition could only be established later by an
interpretation of the Employer's Requirements. Such a situation
would be unsatisfactory in the extreme and contractors would be
well advised to insist that a definition be provided in the
Employer's Requirements.
EIC Contractor's Guide to the FIDIC Conditions of Contract tor EPC Turnkey Projects.
19
EIC Contractor's Guide to the FIDIC Conditions of Contract tor EPC Turnkey Projects
20
8
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
21
8.6 If, in the opinion of the Employer, the Contractor is working too
slowly he can instruct acceleration measures. This applies not
Rate ofress
only when the agreed Time for Completion is at risk but also
Prog where "progress has fallen (or will fall) behind the current
programme under Sub-Clause 8.3 [Programme]".
EIC Contractors Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects
22
8.7 The maximum amount of Liquidated Damages shall be stated in
the Particular Conditions. However, damages in the event of
Delay Damages
delay can exceed this amount e.g. if the Contractor has to pay the
Employers costs under Sub-Clause 8.6 [Rate of Progress] or the
Contract is terminated.
It is not unusual for contracts to state that that the Employer may
not terminate the Contract before the aggregate of liquidated
damages has reached the maximum amount. The Silver Book
does not contain such limitation but, on the other hand, in
accordance with Sub-Clause 15.2 [Termination by Employer]
there have to be qualified reasons for termination due to delay.
9
9.2 The references in this Sub-Clause to Sub-Clause 7.4 [Testing]
(fifth paragraph) and Sub-Clause 10.3 [Interference with Tests on
Delayed Tests
Completion] are confusing because these sub-clauses provide
relief to the Contractor for the circumstances set out in those sub-
clauses and not specifically for those set out in Sub-Clause 9.2
[Delayed Tests].
9.4 If the Works fail to pass repeated Tests on Completion and the
failure "deprives the Employer of substantially the whole
Failure to Pass
benefit of the Works or Section..." then the Employer has the
Tests on
right to reject the Works, terminate the Contract, recover all sums
Completion
paid for the Works, plus financing costs, costs for dismantling the
Works and clearing the Site.
EIC Contractors Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
23
pay the Employer's additional costs. In circumstances where the
Works contain technology which is "in the public domain", then
the same principle should apply. However, it should be
recognised that in such a case design responsibility for the whole
of the Works could rest with the new Contractor and contractors
faced with such a prospect should take due regard of the risks
involved. It is important to understand the implications of this
requirement, as the Contractor could be in a very serious
situation in the event that Tests on Completion are not
successful.
10
11
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
24
cost for remedying defects caused thereby. The Employer's
responsibility under Sub-Clause 11.2 (a) should be entirely
consistent with that set out in Sub-Clause 5.1.
13
13.1 The Employer may initiate Variations prior to issuing the Taking
Over Certificate for the Works, and the Contractor has only
Right to Vary
limited grounds for refusing to undertake the instructed Variation,
which are:
"(i) the Contractor cannot readily obtain the Goods required
for the Variation, or (ii) it will reduce the safety or suitability
of the Works, or (iii) it will have an adverse impact on the
achievement of the Performance Guarantees",
Notwithstanding any objections raised by the Contractor, the
Employer may still confirm his instruction.
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
25
Price resulting from the Variation Order.
EIC Contractors Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
26
This Sub-Clause contains provisions in respect of the recovery
13.7
of additional Costs associated with changes in legislation.
Adjustments for
Changes in
Contractors should note however that the recovery of losses only
Legislation applies to changes in legislation in the Country in which the Site
of the Permanent Works is located.
14
EIC Contractor's Guide to the FIDIC Conditions of Contract tor EPC Turnkey Projects.
27
EIC Contractor's Guide to the FIDIC Conditions of Contract tor EPC Turnkey Projects.
28
14.9 The amount of any Retention Money will be defined within the
Particular Conditions and this Sub-Clause provides for the first
Payment of half of the Retention Money to be released after the Taking-Over
Retention Certificate has been issued provided that the Works have
Money passed all specified tests, including any Tests after Completion.
EIC Contractors Guide to the FIDIC Conditions of Contract lor EPC Turnkey PrQiects.
29
This is a very important Sub-Clause in respect of any
14.14 Contractor's claims. If the Contractor fails to notify them in the
Cessation of
Final Statement and the Statement at completion required by
Employer's
Sub-Clause 14.10 [Statement on Completion], then, with minor
Liability exceptions, they will be barred. The notifications under this Sub-
Clause are in addition to those required under Sub-Clause 20.1
[Contractor's Claims].
15
This Sub-Clause gives the Employer, in addition to the right to
15.1 give instructions under Sub-Clause 3.4 [Instructions], an unlimited
Notice to
right to require the Contractor by notice to make good any alleged
Correct
failure to carry out any obligation under the Contract. If the
Contractor fails to comply with such notice, the Employer has the
right to terminate the Contract under Sub-Clause 15.2
[Termination by Employer].
EIC Contractor's Guide to the FIDIC-Conditions of Contract for EPC Turnkey Projects.
30
These time limits are too long. The Contractor must continue
working even if the Employer has failed to pay. It would be more
equitable if (similar to the other grounds for termination in Sub-
Clause 16.2) the Contractor were required to give 14 days' notice,
particularly in the case of suspension of work by the Contractor.
17
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
31
responsible according to Sub-Clause 5.1 [General Design
Obligations]. If any loss or damage to the Works is caused by
these responsibilities then the Employer must remain liable.
17.4 If, and to the extent that, the Employer requires the Contractor to
rectify the loss or damage to the Works, Goods or Contractor's
Consequences
Documents resulting from any of the Employer's Risks, the
of Employer's
Contractor is entitled to time extension and payment of the Cost
risks
incurred, but not to any uplift for profit, for rectifying the loss or
damage.
EIC Contractor's Guide to the FIDIC Conditions of Contract tor EPC Turnkey Projec
32
19.4 In the event that the Contractor is prevented from performing any
of his obligations under the Contract due to an event of Force
Consequences
Majeure, the Contractor can claim for time extension and the Cost
of Force
incurred. The claims for Cost are limited to the events listed in
Majeure
Sub-Clause 19.1 (i) to (iv) [Definition of Force Majeure]. Such
limitation is difficult to understand given the fact that the
catalogue of Force Majeure events is not exhaustive.
20.1 This Sub-Clause details the procedure that the Contractor must
follow when he considers himself entitled to an extension of Time
Contractor's
for Completion and/or additional payment under any of the
Claims
Clauses or otherwise in connection with the Contract.
EIC Contractors Guide to the FIDIC Conditions of Contract tor EPC Turnkey Proje<
A comparison of the notice provisions under Sub-Clause 20.1
with the notice provisions under Sub-Clause 2.5 [Employer's
Claims] where the Employer is required to give notice as soon as
practicable after becoming aware of the event or circumstance.
This demonstrates an unfair imbalance between the position of
the Employer and that of the Contractor without any reason being
offered for such imbalance.
EIC Contractor's Guide to the FIDIC Conditions of Contract for EPC Turnkey Projects.
34
Red Book are to be preferred for such projects. Under these rules
the DAB is appointed at the start of the Contract and remains in
existence for the duration of the Contract unless agreed
otherwise by the Parties.
20.4 It should be noted that, if the DAB has given its decision as
required by this Sub-Clause and if neither Party has given notice
Obtaining of dissatisfaction within 28 days after having received the DAB's
Dispute
decision, the decision becomes final and binding on both Parties.
Adjudication
Even in the case of dissatisfaction by either Party it would appear
Board's
that the intention is that decisions of the DAB are binding on both
Decision
Parties "unless and until it shall be revised in an amicable
settlement or an arbitral award".
EIC Contractor's Guide to the FIDIC Conditions of Contract for Epc.:rumkey Projects.