TOTAL Rp 38,249,845,296.06
TERBILANG
PROYEK : PEMBANGUNAN KANDANG AYAM CLOSE HOUSE PT.
JENIS : KONSTRUKSI BAJA JL.
UKURAN : 12 mtr x 126 mtr
LOKASI : CIAMIS TASIKMALAYA GARUT JAWA BARAT
NO : 05/HAS
NO DESKRIPSI SPESIFIKASI QTY UNIT TOTAL UNIT PRICE TOTAL PRICE REMARK
A PEKERJAAN SIPIL
1 PEKERJAAN PERSIAPAN
a Pekerjaan Direksi Keet 1.00 Ls Rp 25,000,000.00 Rp 25,000,000.00
b Pemasangan Bow plank 1,820.00 m2 Rp 81,633.55 Rp 148,573,068.43
c Pemasangan Batu Pondasi 85.64 m3 Rp 945,298.01 Rp 80,955,321.85
d Galian Pondasi Batu Kali 85.64 m3 Rp 49,801.32 Rp 4,264,985.43
e Galian Cakar Ayam 56.00 m3 Rp 49,801.32 Rp 2,788,874.17
f Galian Sloop 100.50 m3 Rp 49,801.32 Rp 5,005,033.11
g Pekerjaan Pemadatan Lahan 1,764.00 m2 Rp 24,900.66 Rp 43,924,768.21
sub jumlah PEKERJAAN PERSIAPAN Rp 310,512,051.21
2 PEKERJAAN CAKAR AYAM
a Pekerjaan Cakar Ayam 18.50 m3 Rp 2,927,602.65 Rp 54,160,649.01
b Pekerjaan Sloop 14.44 m3 Rp 2,927,602.65 Rp 42,274,582.25
sub jumlah PEKERJAAN CAKAR AYAM Rp 96,435,231.26
3 PEKERJAAN PASANGAN DINDING
a Coneblok (tanpa plesteran) 415.00 m2 Rp 258,531.13 Rp 107,290,417.22
b Plesteran dan acian 850.00 m2 Rp 59,449.01 Rp 50,531,655.63
c pekerjaan Floor lantai tembok t:10cm 1,778.00 m2 Rp 2,434,960.26 Rp 4,329,359,350.99
d pekerjaan pondasi cailing feet 4.80 m3 Rp 2,927,602.65 Rp 14,052,492.72
e Pekerjaan bak cailing feet 2.00 unit Rp 25,000,000.00 Rp 50,000,000.00
f Bak air pintu masuk 1.00 unit Rp 18,500,000.00 Rp 18,500,000.00
sub jumlah PEKERJAAN DINDING Rp 4,569,733,916.56
B PEKERJAAN KONSTRUKSI
1 Kolom IWF 150 2,772.00 Kg Rp 26,095.36 Rp 72,336,349.67
2 Kuda - kuda 4,368.00 Kg Rp 26,095.36 Rp 113,984,550.99
3 Rehel Portal IWF 150 1,008.00 Kg Rp 26,095.36 Rp 26,304,127.15
4 Kolom Gebel + Cuve 1,133.00 Kg Rp 26,095.36 Rp 29,566,047.68
5 Rehel bawah CNP 100 (2x) 2,268.00 Kg Rp 26,095.36 Rp 59,184,286.09
6 Rehel Atas CNP 100 (2x) 2,268.00 Kg Rp 26,095.36 Rp 59,184,286.09
7 Rehel Ampig 100 (2x) 810.00 Kg Rp 26,095.36 Rp 21,137,245.03
8 Gording CNP 100 10,692.00 Kg Rp 26,095.36 Rp 279,011,634.44
9 Lisplang 270.00 Kg Rp 26,095.36 Rp 7,045,748.34
10 Trekstang dia 10 mm 370.00 Kg Rp 26,095.36 Rp 9,655,284.77
11 Bressing dia 10 mm 294.00 Kg Rp 26,095.36 Rp 7,672,037.09
12 Base Plat (25x25x10mm) 330.00 Kg Rp 26,095.36 Rp 8,611,470.20
13 Plat simpul kuda kuda 396.00 Kg Rp 26,095.36 Rp 10,333,764.24
14 Plat Behel + plat Gordeng 477.00 Kg Rp 26,095.36 Rp 12,447,488.74
15 Plat Stepiner 170.00 Kg Rp 26,095.36 Rp 4,436,211.92
sub jumlah PEKERJAAN KONSTRUKSI Rp 720,910,532.45
F PEKERJAAN WIREMESH
1 Dinding Wiremesh M5 3,420.00 Kg Rp 21,459.60 Rp 73,391,841.06
2 Lantai Wiremesh (2x) 9,900.00 Kg Rp 21,459.60 Rp 212,450,066.23
sub jumlah PEKERJAAN WIREMESH Rp 285,841,907.28
TOTAL Rp 7,649,969,059.21
TERBILANG