You are on page 1of 7

Journal of the Air Pollution Control Association

ISSN: 0002-2470 (Print) (Online) Journal homepage: https://www.tandfonline.com/loi/uawm16

Energy Requirements of a Limestone FGD System

Edward S. Rubin & Due G. Nguyen

To cite this article: Edward S. Rubin & Due G. Nguyen (1978) Energy Requirements of a
Limestone FGD System, Journal of the Air Pollution Control Association, 28:12, 1207-1212, DOI:
10.1080/00022470.1978.10470728

To link to this article: https://doi.org/10.1080/00022470.1978.10470728

Published online: 14 Mar 2012.

Submit your article to this journal

Article views: 2343

View related articles

Citing articles: 5 View citing articles

Full Terms & Conditions of access and use can be found at


https://www.tandfonline.com/action/journalInformation?journalCode=uawm20
Energy Requirements of a
Limestone FGD System

Edward S. Rubin and Due G. Nguyen


Carnegie-Mellon University

A computerized simulation model has been developed to compute In recent years, utilities have been concerned principally
energy requirements of a limestone slurry flue gas desulfurization with overcoming operational and reliability problems common
(FGD) system as a function of FGD system design parameters, power in early FGD designs. With many of these problems now re-
solved, attention is increasingly focused on the economic as-
plant characteristics, coal properties, and sulfur dioxide emission
pects of FGD technology. Besides the high capital cost of FGD
regulation. Results are illustrated for a "base case" plant of 500 MW, systems, operating costs are also substantial, in large part
burning 3.5% sulfur coal, meeting the federal new source perfor- because of the energy-intensive nature of this technology. To
mance standard of 1.2 Ib SO 2 /10 6 Btu. The flue gas is cleaned by an date, relatively little attention has been paid to optimizing
electrostatic precipitator followed by a limestone FGD system with FGD systems with respect to energy consumption. The
present study was therefore undertaken to systematically
a TCA scrubbing vessel and an optimized in-line steam reheater. The
analyze FGD energy requirements, and to investigate methods
total FGD system energy requirement for this case was found to be of minimizing these to improve the net efficiency of electric
3.4% of the total energy input to the boiler. Sensitivity analyses were power generation. The analysis focused on a limestone system,
then performed in which the nominal values of ten system parameters the most widespread process now in use.
were individually varied. This caused the total FGD system energy The following section of this paper briefly reviews the na-
requirement to vary between 2.5 % and 6.1 % of the gross plant output
ture of FGD system operation. Following this, an analytical
model is described which was developed to study FGD system
for the range of parameters tested. The most sensitive parameters energy requirements and optimization. Results are presented
were found to be scrubbing slurry pH, which affects pumping re- in terms of sensitivity analyses showing the effect of plant,
quirements, and stack gas exit temperature, which affects reheat coal, regulatory, and FGD system parameters on overall en-
requirements. In all cases, FGD energy requirements were minimized ergy requirements. These results are discussed in light of the
when the SO 2 emission standard was met by partially bypassing the
1977 Clean Air Act Amendments, which were enacted sub-
sequent to the completion of this study.
scrubber. In light of the recent Clean Air Act Amendments this option
may not be feasible in the future. FGD System Components

Figure 1 shows the flow diagram for a power plant boiler


equipped with a typical limestone slurry system. The three
Since passage of the 1970 Clean Air Act Amendments, electric main areas of interest are, (1) SO2 scrubbing module and
utilities throughout the country have been adopting flue gas demister, (2) stack gas reheater, and, (3) materials handling
desulfurization (FGD) systems in increasing numbers to and sludge disposal.
achieve federal or state standards for sulfur dioxide emissions
at coal-fired facilities. At the present time, the most widely Scrubber Module and Demister
used type of flue gas desulfurization system is a lime or lime-
stone wet scrubbing process which absorbs SO2 from power The function of the scrubbing module is to absorb SO2 from
plant flue gases and produces a sulfur-bearing sludge to be the stream of mixed combustion gases leaving the boiler.
disposed on land. Lime/limestone systems are employed on Particulate matter may be removed simultaneously, or pref-
98% of all new U.S. capacity with operating FGD systems, and erably by dry collection upstream of the scrubber. SO2 is re-
on 91% of new capacity with FGD systems under construction. moved by contacting the gas with a limestone slurry con-
Of these, the majority use limestone rather than lime as the
scrubbing agent.1 Ccipyright 1978-Air Pollution Control Association

December 1978 Volume 28, No. 12 1207


Steam from
steam plant
Optional^ SO2 I
bypass \ absorber r-*-|Reheater
e—•r-—H I——-—
Economizer I

Pulverized coal

Hoppers, feeders &


conveyors Feeders -
Weigh belts-
Gyratory crushers - Mills Slurry Pump
Elevators • product Pump feed
tank tank

Figure 1. Limestone slurry process flow diagram (adapted from Reference 2).

taining approximately 60% solids. The slurry is recirculated to the atmosphere. The temperature of the scrubbed gas must
to a holding tank where limestone is added while part of the also be above the sulfuric acid dew point to avoid excessive
spent solution is bled off to a settling pond feed tank. Pre- corrosion of fans, reheater tubes, and ductwork. Although exit
cipitating calcium sulfate, calcium sulfite, unreacted lime- temperature requirements will depend on specific site pa-
stone, and other solids form a complicated chemical sludge rameters, the Tennessee Valley Authority (TVA) reports that
which is suspended in the holding tank by agitation, then a 175°F exit temperature is usually sufficient for dispersion
pumped to a settling pond for disposal. and corrosion protection.2 In other studies, however, exit
The efficiency of SO2 removal is a function of the scrubbing temperatures as high as 250° F are reported.3
module design as well as gas composition and process condi- Reheaters currently in use utilize oil firing, hot air injection,
tions including inlet SO2 concentration, flue gas velocity, or an in-line steam heat exchanger to increase the stack gas
slurry composition, liquid-to-gas ratio, and slurry pH. Al- temperature. With oil firing, the hot combustion gases are
though scrubber chemistry is not completely understood in mixed directly with the flue gas to increase the bulk temper-
detail, existing semi-empirical models can adequately predict ature. This method is likely to diminish in the future in light
the performance of current limestone systems.2 of energy policies aimed at reducing oil and natural gas con-
Energy is needed in the scrubbing process to pump slurry sumption. Methods utilizing steam typically draw energy from
through the scrubber circuit and to drive the fans needed to an intermediate turbine stage of the power plant. The in-line
overcome gas phase pressure drops through the SO2 absorber reheater accomplishes heat exchange by condensing steam in
vessel and associated ductwork. Pumping power is a function tubes directly within the flue gas stream. Alternatively, steam
of liquid flow and pressure drop, dependent on contactor can be used to heat air which is then injected into the flue gas
design. Similarly, fan power requirements increase directly stream to achieve the desired reheat. Although this is more
with the flow rate of flue gas treated and the gas phase pres- costly, it may be preferable where scaling or corrosion of an
sure drop through the system. Both fan power and pumping in-line exchanger becomes excessive. The total energy re-
power also depend on the mechanical fan or pump efficiency quirement for gas reheat is then the sum of the input thermal
and the electro-mechanical efficiency of motor drives. energy plus the electrical power required by fans to overcome
Energy requirements are also influenced by the demister the pressure drop of the flue gas across the reheater and as-
downstream of the scrubber. The purpose of this device is to sociated breeching.
remove liquid slurry entrained in the flue gas. The demister
thus adds to the pressure drop incurred in the scrubber, al- Raw Materials Handling and Sludge Disposal
though this is small during nominal operation. Current
practice is periodically to wash the demister with clean water The final area of an FGD system requiring ancillary energy
to remove deposits and prevent clogging. As a result, liquid is materials handling. This refers to the various stages required
droplets from the demister wash water, as well as some liquid to process, store and feed the limestone slurry reagent, as well
scrubber slurry, inevitably escape the demister and remain as equipment to handle and dispose of the waste sludge gen-
entrained in the flue gas. Evaporation of this entrained liquid erated in the scrubber. Energy is required in the form of
increases the energy required in reheating the gas downstream electricity to operate the various pumps, conveyors, and me-
of the demister. chanical equipment needed to handle raw and waste materials.
Studies by TVA indicate that only about 10% of the total en-
Stack Gas Reheater ergy required by a limestone FGD system is needed for ma-
terials handling.2 In the present study, therefore, energy re-
Reheating of the scrubbed flue gas is done to restore plume quirements of the SO2 scrubber and stack gas reheater were
buoyancy to achieve adequate dispersion of flue gases emitted the prime areas of study.

1208 Journal of the Air Pollution Control Association


Energy Optimization Model absorber (TCA), the sulfur dioxide removal efficiency is given
by:6*
In order to analyze FGD energy requirements systemati- 4 81 0 36
17SO2 = l - exp {-2.05 X 10- (L/G)°- u - •
cally, a computerized model of a coal-fired steam electric exp [4.3 X 10~3 v (h/d + N) + 0.81 pH - 1.7 X 10"4 SO2
power plant was developed. The model included a conven-
tional pulvurized coal-fired boiler, an electrostatic precipitator + 7.9 X 10~5 Mg + 1.3 X 10~5 Cl]j (1)
for particulate removal, a wet limestone FGD system with where, 77so2 = fraction of SO2 removed from flue gas
optional flue gas bypass, an in-line steam reheater, and a L/G = liquid-to-gas contacting ratio (gal/1000 acfm
separate induced draft fan for each scrubbing train. A detailed at scrubber outlet conditions)
description of the model is given by Carnahan, et al. in Ref- v = flue gas velocity at contactor conditions
erence 4. A summary of model input parameters is shown in (ft/sec)
Table I, along with numerical values for a "base case" plant h = static packing height (in.)
configuration discussed later. d = packing diameter (in.)
The size of the FGD system and minimum number of trains N = number of TCA grids
were determined through a calculation of flue gas volumetric pH = inlet slurry pH
flow rate based on plant size, boiler firing characteristics, and SO2 = inlet SO2 concentration (ppm)
coal composition. The model assumed complete combustion Mg = effective liquor Mg ++ concentration (ppm)
with some retention of sulfur in the boiler bottom ash. The Cl = liquor Cl concentration (ppm)
TVA criterion of 93.6 m2 was used for the maximum cross-
sectional area of a single scrubber module.5 Performance of In a similar manner, pressure drop across the scrubber was
the scrubber was modeled using semi-empirical correlations calculated from correlations developed by Bechtel for dif-
developed by the Bechtel Corporation in conjunction with the ferent scrubber configurations.4-6 The scrubbing liquor
Tennessee Valley Authority Shawnee Test Program using * An alternative form of Eq. (1) has been published more recently,7 but gives similar re-
packed bed and spray tower absorbers. For a turbulent contact sults.

Table I. Input parameters for FGD energy consumption model.


Boiler and equipment characteristics Base case values
Gross power generation 500 MW
Gross cycle heat rate 9000 Btu/kwh (9496 kJ/kwh)
Boiler thermal efficiency 85.0%
Percent excess air (including leakage) 33.0%
Air absolute humidity 0.0044 lb H2O/lb dry air
Sulfur in gas stream 95.0%
Fly ash in gas stream 80.0%
Electrostatic precipitator efficiency 99.5%
Hot gas temperature 300°F (149°C)
Coal moisture content (as fired) 9.80%
Coal analysis (dry basis)
Carbon 65.41%
Hydrogen 4.70%
Oxygen 7.34%
Nitrogen 1.18%
Sulfur 3.50%
Ash 17.74%
Coal heating value (as fired) 10,500 Btu/lb (24,428 kJ/kg)
Environmental regulatory constraints
Sulfur dioxide emission limit 1.2 lb/106 Btu (520 ng/J)
Scrubber system characteristics (TCA)
Scrubbing pH 5.65
Liquor Mg and Cl 0 ppm
Number of beds 3
Number of grids 4
Heights of spheres per bed 5.0 in. (127 mm)
Scrubber gas velocity 12.0 ft/sec (3.0 m/sec)
Flue gas inlet temperature 300°F(149°C)
Flue gas exit temperature 127°F (53°C)
SO2 removal efficiency (optional) (calculated)
Water entrainment of demister 0.1% wt. of flue gas
Fan efficiency 60%
Pump efficiency 60%
Motor efficiency 90%
Steam reheater characteristics
Flue gas face velocity 25.0 ft/sec (7.6 m/sec)
Inlet steam temperature 470°F (243°C)
Heat of vaporization of steam 750 Btu/lb (1745 kJ/kg)
Stack exit temperature 175°F (75°C)
Outside tube diameter 1.0 in. (25.4 mm)
Transverse tube spacing 1.5 in. (38.1 mm)

December 1978 Volume 28, No. 12 1209


pumping head and ductwork pressure drop were derived from 5.0
earlier TVA studies of packed and spray tower absorbers.4'5
From this, electrical power requirements were calculated from Coal sulfur content =
the equation: (dry basis)
5.0%

(
3.5%
VeVm
where, E = electrical power requirement
Q = volumetric flow rate
AP = pressure drop or head
r)e = electromechanical motor efficiency 2.0%
t]m — mechanical fan or pump efficiency.
This energy was then referred back to an equivalent coal en- Increasing bypass-
ergy input to the boiler utilizing the gross cycle heat rate
(coal-to-electric efficiency) for the power plant. Energy re- 0.0
quirements for raw materials handling and scrubber sludge 65 70 75 80 85 90 95 100
Percent SO2 removal from treated gas
disposal were estimated at a constant value of 0.4% of total
gross generation based on TVA studies cited earlier. Figure 3. Effects of coal sulfur content on total FGD energy requirements (all
Performance of the demister was modeled in terms of the other parameters at base case values).
mass of entrained water carried downstream to the stack gas
reheater. Though these levels are generally not well quantified, moving 93% from two-thirds of the gas then mixing it with the
and vary with demister design, a range of estimates were remaining third that bypasses the scrubber. Although the
available from laboratory and pilot plant studies which higher SO2 removal efficiency increases the energy penalty
characterized water entrainment as a percentage of the mass in the scrubber, the energy requirement for reheat is reduced
of flue gas crossing the demister.5 Entrainment was nominally because hot bypass gas is available to mix with the saturated
taken to be 0.1% of the flue gas mass flow, with a wider range gas leaving the scrubber. Reheat energy requirements are
explored in sensitivity analyses. reduced in proportion to the fraction of gas bypassed, while
Performance of the stack gas reheater was modeled as an scrubber energy requirements increase nonlinearly as the
in-line cross flow heat exchanger in a rectangular duct. Figure treated gas requires continually higher removal efficiencies.
2 shows a schematic of the flow and pipe arrangement. Given The result is an optimum level of bypass at which total system
the inlet flue gas properties, flow rate, reheater tube diameter, energy is minimized while still achieving the applicable SO2
and transverse tube spacing, a gas dynamic optimum cross- emission standard. This is illustrated in Figure 3 for a 500 MW
sectional area was calculated to determine the gas velocity at plant using a relatively high sulfur (3.5%) eastern coal and a
which the most favorable trade-off is achieved between heat TCA scrubber. Other characteristics of this "base case" power
transfer coefficient and pressure drop.4 A pressure drop cor- plant are summarized in Table I. Optimum bypass calcula-
relation for the flow of a gas over banks of tubes8 was then used tions assume that the SO2 removal efficiency is increased by
to calculate the optimum number of pipes per bank (mini- raising the slurry pumping rate (L/G) to the value dictated
mizing overall pressure drop), and total required heat ex- by Eq. (1) when all other parameters are held at their nominal
changer area was calculated using the Effectiveness-NTU (zero bypass) values.
method described by Kays and London.9 High temperature It should be noted that the 1977 Clean Air Act Amendments
steam in the reheater was assumed to enter as saturated vapor may well preclude the use of bypass in the future because of
and leave as saturated liquid. The total thermal energy re- the requirements for "best available control technology"
quirement for reheat was expressed in terms of equivalent coal (BACT) and "lowest achievable emissions reduction"
input utilizing the boiler thermal efficiency. (LAER). The energy consequences of this policy are explored
A final feature of the energy utilization model was a calcu- in the next section of this paper, together with the influence
lation of the optimum level of scrubber bypass which mini- of various system parameters on total FGD energy require-
mizes the total system energy requirement. Bypassing part ments.
of the stack gas around the scrubber is feasible when an elec-
trostatic precipitator or other device is used to achieve the Results of Sensitivity Analysis
particulate emission standard upstream of the scrubber, and
the SO2 emission standard does not require all of the exhaust Relative to the "base case" plant configuration of Table I,
gas to be treated. For example, at a plant burning a 2% sulfur sensitivity analyses were undertaken to determine the effect
eastern coal, an SO2 emission standard of 1.2 lb/106 Btu can on nominal FGD energy of changes in 10 system parameters.
be met by removing 63% of SO2 from all the gas, or by re- For each of 30 cases, the fraction of flue gas bypassing the
scrubber was also systematically varied from zero to some
maximum value corresponding to an SO2 removal efficiency
Flow duct of 90%. A summary of the parameter ranges tested and their
corresponding effect on energy requirements is given in Table
II. Illustrative results showing the effect of partial bypass are
given in Figures 3-6. In these figures, the minimum SO2 re-
moval efficiency needed to achieve the applicable emission
standard is found at the extreme left of each curve, which
corresponds to zero bypass. As the level of bypass is increased
the SO2 removal efficiency of the treated gas stream increases
proportionately so that the mixed stack gas achieves the same
emission standard. The total FGD energy requirement is given
as a percent of the gross power plant output (equivalent to the
boiler heat input times* the gross cycle heat rate.)
Two general conclusions are drawn from the results of these
FRONT VIEW SIDE VIEW sensitivity analyses. First, the absolute level of auxiliary en-
Figure 2. In-line steam reheater configuration. ergy required by the FGD system varies with many coal,

1210 Journal of the Air Pollution Control Association


Table II. Sensitivity analysis of FGD system energy requirements.
Corresponding Average percent
total FGD energy Corresponding increase in FGD
Range of with zero bypass percent energy energy for a
System parameter values (% boiler heat savings at 10% increase in
varied testeda input)b optimum bypass0 parameterd
Coal parameters
Sulfur content (Wt. %) 2.0-5.0 2.93-3.92 50.5-2.0 13.4
Heating value (Btu/lb) 9,500-13,500 3.79-2.61 2.5-22.6 -13.2
Boiler/plant parameters
Gross cycle heat rate 8,700-9,300 3.36-3.44 12.8-11.9 5.0
(Btu/kwh)
Total excess air (%) 10-50 2.97-3.72 10.8-13.4 1.6
Scrubber inlet temp. (°F) 300-350 3.40 12.4-19.1 -4.6
FGD system parameters
Slurry inlet pH 5.45-5.85 3.58-3.25 8.4-15.4 -25.1
Scrubber AP (in. H 2 0) 2.044-10.885 2.90-3.40 19.3-12.4 2.6
Demister entrainment 0.0-0.5 3.26-3.97 12.6-12.3 0.4
(Wt. % Flue Gas)
Reheater exit temp. (°F) 150-250 2.49-6.09 16.1-7.6 20.7
Emission constraint
SO2 emission level 0.6-1.5 3.87-3.26 0.5-22.1 -5.9
(lb/106 Btu)
a
All other parameters held at the "base case" values in Table I.
b
Sum of scrubber, reheater, and materials handling energy requirements as an equivalent percentage
of total heat input to the boiler.
c
Relative to total energy with zero bypass. Optimum bypass fraction ranged from 2.2 to 32.2% of total
flue gas.
d
Average of three cases tested for each parameter. Negative numbers indicate that energy requirements
decrease when value of the parameter increases.

process, and plant characteristics. For the cases examined, the ments. For the cases tested here, a 10% increase in stack exit
energy requirement of an FGD system without bypass ranged temperature increased the total FGD energy requirement by
from 2.5% to 6.1% of the total energy input (or gross power approximately 21%. This suggests the need for careful study
output) of the plant. to determine the minimum acceptable stack exit temperature
The second general conclusion is that for any fixed set of for any specific application. This energy penalty could also
coal and plant characteristics, FGD energy use is minimized be reduced substantially if improved heat transfer technology
by operating scrubbers at a high efficiency (90-93%), while allows waste heat utilization to become economically attrac-
bypassing as much flue gas as permitted by the applicable tive such that reheat energy could be supplied from low
emission standard. An economic analysis of the base case plant quality (turbine outlet) steam that would not penalize the
design further indicated that FGD capital costs as well as electrical generation cycle.
operating costs were reduced using partial bypass.4 Although
widespread use of this option may be precluded by the recent §5.0
Clean Air Act Amendments, as noted earlier, it is of interest Percent bypass
to note that the energy savings potential can be significant. 5 10 15 20
For example, with 2.0% sulfur coal (Figure 3), an FGD system 4.0
removing 63% SO2 from 100% of the gas to achieve an emission
level of 1.2 lb SO2/IO6 Btu requires approximately twice the
energy of a system in which 32% of the gas is bypassed and the ;3.o
remainder treated to a removal efficiency of 93% to achieve
the same stack emission standard. With 3.5% sulfur coal, the
.2 2.0
total energy requirement with zero bypass was generally 10%
to 30% larger than with optimum partial bypass.
Table IF shows the sensitivity of total FGD energy re- 1.0
quirement to changes in the nominal value of different system
characteristics. The results show the percentage change in
total energy resulting from a 10% increase in the base case 75 80 85 90 95 100
value of the indicated parameter. Of the parameters tested, Percent SO2 removal from treated gas
the most sensitive were the scrubbing liquid pH and the stack
Figure 4. FGD energy requirements as a percent of total power
gas exit temperature. Based on the Bechtel correlations for plant requirements for the base case configuration (Table I).
a TCA scrubber, a 10% increase in inlet slurry pH reduced the
nominal FGD energy requirement by approximately 25%. For
a spray tower absorber, where total pressure drop in the Table II shows that coal characteristics play an important
scrubber is significantly lower than the TCA design, sensitivity part in determining FGD energy requirements. Decreasing
to pH still remains high. This is because pH affects the the base case sulfur content substantially reduced both the
amount of slurry that must be pumped, and this in turn di- size and energy requirement of the FGD system needed to
rectly affects the energy requirement. To minimize energy achieve new source emission standards. Thus, washing of high
consumption, pH should be kept relatively high. sulfur coals to achieve lower inlet sulfur levels could be at-
The sensitivity of total energy requirement to stack gas exit tractive from the viewpoint of the power plant operator.
temperature is related directly to thermal reheat require- Similarly, increasing the heating value of coal reduced FGD

December 1978 Volume 28, No. 12 1211


g5.0 a 5.0
Reheater exit temperature = emission level =
200°F ^ ^
•g 4 . 0 - "5 4 . 0 -
Zero - / I Zero bypass
I£3.0 bypass \
I
__^
175°F ^ ^ ^
>3.0

150°F ^^y
2 2.0- §2.0

Increasing bypass-
•R 1-Oh Increasing bypass

8
0.0 1 1 1

70 75 80 85 90 95 100 i 0.0 75 80 85 90 95 100


Percent SO2 removal from treated gas Percent SO2 removal from treated gas

Figure 5. Effects of reheater exit temperature on total FGD en- Figure 6. Effect of SO2 emission constraint on total FGD energy
ergy requirements (all other parameters at base case values). requirement (all other parameters at base case values).

energy consumption when the allowable SO2 emission was ration required twice as much energy as the system with
given in terms of boiler heat input. On the other hand, tight- partial bypass. The future viability of bypass, however, ap-
ening the nominal SO2 regulation by 10% produced about a pears restricted by the 1977 Clean Air Act Amendments en-
6% increase in the FGD system energy requirement. Figure acted subsequent to this study.
6 illustrates how the potential for bypass is also reduced as the.
emission constraint becomes more stringent. Acknowledgments
Finally, Table II shows that several of the parameters ex-
amined had a relatively small impact on energy requirements. The authors gratefully acknowledge the assistance and
Decreasing the pressure drop by converting from a packed bed cooperation of the Tennessee Valley Authority, U.S. Envi-
to a spray tower arrangement reduced the gas-side fan re- ronmental Protection Agency, and Bechtel National, Inc. in
quirements substantially, but produced a more modest de- carrying out this work. David R. Carnahan, William D. Latura,
crease in overall energy requirement since pumping power and Charles A. Zaczek of Carnegie-Mellon University con-
increased and reheat requirements were unaffected. Water tributed significantly to the development of the computer
entrainment at the demister also exhibited relatively little codes used here, and are happily acknowledged. Partial sup-
sensitivity to a 10% change in the nominal value, although the . port for this research was provided by grants from Brookhaven
relatively large uncertainty in this value could still produce National Laboratory (DOE), the Pennsylvania Science and
a noticeable impact on total system energy. Variations in the Engineering Foundation, and the Middle Atlantic Power
excess air level and inlet air humidity displayed the weakest Research Committee.
effect on overall energy requirements.
References
Conclusion
1. "Summary Report, Flue Gas Desulfurization Systems, August-
A computerized simulation model was developed to de- September 1977," Prepared by PEDCo Environmental, Inc. for
termine the energy requirements of a limestone flue gas the U.S. EPA Research Triangle Park, NC, Nov. 1977.
2. G. G. McGlamery, R. L. Torstrick, W. J. Broadfoot, J. P. Simpson,
desulfurization (FGD) system of a coal-fired steam-electric L. J. Henson, S. V. Tomlinson, and J. F. Young, "Detailed Cost
power plant. FGD system energy requirements were found to Estimates for Advanced Effluent Desulfurization Processes,"
depend on scrubber design, coal characteristics, power plant EPA-600/2-75-.006, U.S. EPA, Washington, DC, Jan. 1975.
design, and environmental regulatory constraints. Sensitivity 3. D. H. Brown, "Energy Conversion Alternatives Study," Rept. No.
NASA CR-134950, Electric Company, Schenectady, NY, Dec.
analyses were performed in which ten parameters were sys- 1976.
tematically varied from their nominal "base case" values 4. E. S. Rubin, editor, "Comparative Environmental Assessments
corresponding to a 500 MW plant, burning 3.5% sulfur coal, of Coal Utilization Systems. Volume II: Details of Model Devel-
and achieving an SO2 emission level of 1.2 lb/106 Btu with a opment," Center for Energy and Environment Studies, Carne-
gie-Mellon University, Pittsburgh, PA, March 1978.
turbulent contact absorber (TCA) scrubbing vessel and an 5. Private communication, Tennessee Valley Authority, Emission
•in-line steam reheater. Changes in the stack gas exit temper- Control Development Projects, Muscle Shoals, AL, 1976.
ature and the scrubbing slurry pH had the greatest effect on 6. "EPA Alkali Scrubbing Test Facility: Advanced Program, Third
FGD energy requirements for comparable changes in any of Progress Report," EPA 600/7-77-105, Prepared by Bechtel Cor-
poration for U.S. EPA, Sept. 1977.
the system parameters tested. A 10% change in either pH or 7. C. H. Rowland, N. E. Bell, C. C. Lewis, and H. N. Head, "Predicting
, exit temperature produced more than a 20% change in total SO2 Removal by Limestone/Lime Wet Scrubbing: Correlations
FGD energy use. For the range of parameters tested, the total of Shawnee Data," Paper No. 78-46.5, APCA Annual Meeting,
FGD energy requirement was equivalent to between 2.5% and Houston, TX, June 1978.
8. J. P. Holman, Heat Transfer, 4th ed., McGraw-Hill, Inc., New
6.1% of the total power plant output when 100% of the flue gas York, 1976.
was treated in the FGD system. 9. M. W. Kays and A. L. London, Compact Heat Exchangers, 2nd
Optimization studies also showed that if particulate matter ed., McGraw-Hill, Inc. 1964.
is removed upstream of the scrubber, FGD energy require-
ments are minimized by partially bypassing the scrubber
vessel while treating the remaining flue gas to a high SO2 re-
moval efficiency to achieve the applicable (mixed stack gas) Dr. Rubin is Associate Professor of Mechanical Engineer-
emission standard. Sensitivity analyses for the 3.5% sulfur coal ing and Public Policy, and Director of the CMU Center for
showed that treating the entire flue gas stream required 10% Energy and Environmental Studies, Carnegie-Mellon Uni-
to 30% more energy to achieve the same SO2 emission standard versity, Pittsburgh, PA 15213. Mr. Nguyen is a former me-
chanical engineering research assistant, currently with Texa-
as a system with a partial bypass. Capital cost was also lower co Engineering, Houston, TX.
with bypass. For a 2.0% sulfur coal, the zero bypass configu-

1212 Journal of the Air Pollution Control Association

You might also like