3-Day Report: (Nov 2-5, 2011)

Accomplishment: (described briefly tasks done for past 3 days)


1. Install formworks, rebars for precast panels (3 panels) @ roof deck.
2. Poured 3 panels @ roof deck
3. Erected 3 panels @ roof deck, 9 panels @ penthouse 1 & 2.
4. Erected 7 (1.8m x 0.90m) panels for the revised window & door
opening @ PH 1.
5. Visited Makoto project last Nov. 4, 2011 pm.
6. Estimate / emailed formworks request for makoto project.
7. Emailed the formworks monthly meeting minutes.
8. Checked sub-con masonry works.

Problems encountered & steps taken to solve it:


(briefly state problem and how you solve it)
1.
2.

Lessons learned:
1.
2.

To do the next 3 days:


1. Supervise erection of poured precast panels @ PH 1&2-unit 8 & 7
2. Supervise casting of remaining precast panels @ PH 1&2- unit 8
3. Site visit makoto expansion project.
4. Follow up LBS iron works for their sample board for PH railings.
5. make the 3day report and email to FEB cc’d KPB.

Pending works, given by who and schedule.


1. Quantify water tank (overhead) inside surface area for tiles. -
(RFE)
2.