Accomplishment: (described briefly tasks done for past 3 days)
1. Give instruction to workers (re priority fo works). 2. Install formworks, rebars for precast panels (3 panels) @ PH1-Unit 8. 2. Poured 3 panels @ PH1-Unit 8 (Monday) 3. Erected 1 panel,6 panels (adt’l due to revision of door & window opening)@PH2. 5. Visited Makoto project last Nov.08, 2011 pm. 6. Checked & identify balance of works from PH1,PH2,Roof Deck & Viewing deck. 7. Supervised casting & erection of remaining panels @ PH. 8. Checked sub-con masonry works. 9. Poured 6 panels @ PH 2-Unit 8. 10. Estimate & submit tiles requirements for concrete water tank to Zenith. 11. Checked emails on Lotus notes.
Problems encountered & steps taken to solve it:
(briefly state problem and how you solve it) 1. 2.
Lessons learned: 1. 2.
To do the next 3 days:
1. Supervise erection of poured precast panels @ PH 1&2-unit 8 2. Supervise casting of remaining precast panels @ PH 1&2- unit 8 3. Reconcile Specserv re PH 1&2 viewing deck & balcony areas for water proofing. 4. Meet with STG in charge re: schedule of their scope. 5. make the 3day report and email to FEB cc’d KPB.
Pending works, given by who and schedule.
1. Making SRF for penthouse water proofing. -- Zenith