3-Day Report: (Nov 10-12, 2011)

Accomplishment: (described briefly tasks done for past 3 days)


1. Give instruction to workers (re priority fo works).
2. Install formworks, rebars for precast panels (last set) @ PH1-Unit 8.
2. Reconcile water proofing area for PH 2 balcony.
3. Emailed sir bal the qty of formworks for PIPC 12 cistern tank..
5. Supervised erection of poured precast panels @ PH 1&2-unit 8.
6. Supervised casting of remaining precast panels @ PH 1&2- unit 8.

Problems encountered & steps taken to solve it:


(briefly state problem and how you solve it)
1.
2.

Lessons learned:
1.
2.

To do the next 3 days:


1. Attend safety orientation @ MEPZ 1
3. Meeting with PIPC 12 personnel re scope of works for PIPC 12 project
(cistern
Tank)
4. Supervise the remaining balance of work for PH 1 - Roof Deck.
5. make the 3day report and email to FEB cc’d KPB.

Pending works, given by who and schedule.


1. Making SRF for penthouse water proofing. – Zenith
2. Submit revised schedule for the remaining balance of work for PH1 –
RD. - Zenith
3. Make cost comparison for masonry plastering between conventional
mixing vs
mixing mortar with masonry enhancer. ----- KPB