3-Day Report: (Oct.

27-29, 2011)

Accomplishment: (described briefly tasks done for past 3 days)


1. Install formworks, rebars for precast panels @ PH 1&2 U-08
(13 panels) and plant box @ roof deck.
2. Poured 13 panels for PH 1&2-unit 8 and plant box @ roof
deck
3. Checked sub-con masonry works (CHB filing & plastering)
4. Done editing the minutes of Formworks monthly meeting.

Problems encountered & steps taken to solve it:


(briefly state problem and how you solve it)
1.
2.

Lessons learned:
1.
2.

To do the next 3 days:


1. Supervise erection of poured precast panels @ PH 1&2-unit 8
&7
2. Supervise casting of remaining precast panels @ PH 1&2-
unit 8
3. Site visit makoto expansion project for their first day of
formworks
installation.
4. make the 3day report and email to FEB cc’d KPB.

Pending works, given by who and schedule


1. Email to formworks group the minutes of meeting last
October 18, 2011 on November 4, 2011.