Professional Documents
Culture Documents
Code of Practice
for New Constructions
and Refurbishments
The intention of this Code of Practice is to highlight the vital factors regarding
planning and execution of work by the use of protective coatings in aggressive
tank environments. Valuable, and in theory sufficient, information regarding this
can be found in the technical data sheets for the products to be used. However, it
has been found required to present some more background information to secure
that the personnel involved understand and practise the requirements set forth in
tank projects.
Furthermore, most coating failures are the result of simple omissions and
application errors. Coating successes, on the other hand, are the result of
thorough planning and skilled craftsmanship.
Following these guidelines will help the smooth running of any coating project.
However, because local conditions differ around the world, discussion with
Jotun’s local Technical Sales Support department is recommended on any
contentious subjects.
Foreword 2
Contents 3
1 Scope and field of application 4
2 General 5
2.1 The Painting Contractor 5 Click on Chapter/Sub-chapter in Contents to
2.2 The Coating Advisor 5 go to relevant page.
2.3 The Owner’s representative 5 To return to Contents page click on bottom
2.4 The Contractor (shipyard or construction company) 5 left heading ‘General Tank Coating Code of
2.5 Jotun Technical Sales Support department 5 Practice.’
2.6 Rules for cooperation 5
2.7 Planning 6
2.8 Pre-project meeting 6
2.9 Follow-up meetings 6
3 Tank condition prior to work start-up 7
4 Scaffolding 8
4.1 General 8
4.2 Access 8
4.3 Dismantling and removal 8
5 Basic work sequence for tank coating 9
5.1 New constructions 9
5.2 Refurbishment 10
6 Surface preparation 11
6.1 General 11
6.2 Pre-blasting welds (for tanks in block sections) 11
6.3 Steel preparation work 11
6.4 Degreasing and cleaning 12
6.4.1 General recommendations 12
6.4.2 Washing procedures 12
6.5 Abrasive blast cleaning 13
6.5.1 Ambient conditions, ventilation and protection from rain 13
6.5.2 Abrasives 13
6.5.3 Air supply 14
6.5.4 Removal of dust and abrasives 14
6.6 Steel surface assessment prior to coating application 14
6.7 Boiler suits etc 15
7 Coating application 16
7.1 General 16
7.2 Film thickness, types and number of coats 16
7.3 Ambient conditions 17
7.4 Ventilation and dehumidification 17
8 Health and Safety 19
8.1 General 19
8.2 Safety preparations 19
8.3 Scaffolding safety 19
8.4 Elimination of ignition sources 20
8.5 Management of solvent vapour concentration 21
8.5.1 General advice 21
8.5.2 Ventilation and air exchange 21
8.5.3 Finding the required ventilation rate 22
8.5.4 Monitoring the ventilation system 24
This Code of Practice deals with various aspects related to protection of steel,
exposed to aggressive water or cargo of different kinds, by use of specialized
coatings. It lays down a set of rules required to obtain optimal service life of
coatings in corrosive environments. The document treats tanks both at the new
building / block stage and at the refurbishment stage.
This Code of Practice is intended both for marine, offshore and land based
tanks. The principles are the same, although choice of products and practical
arrangements may differ.
Requirements that are found in each product’s technical or safety data sheet are
not included in the present document.
The Painting Contractor is the party employed to carry out the part of the
project that includes surface preparation and application of the coating system.
The Painting Contractor selected for surface preparation and application of the
coating system should be an organisation approved by Owner, Contractor (i.e.
the company constructing the tank) and Jotun.
Planning must cover all phases of the coating operation and its intention shall be
to secure the correct quality of work and a safe working environment. A detailed
work plan should include the scheduling of all operations to be carried out
before, during and after application of the coating system. The work plan should
be available to the Coating Advisor prior to the start of any work related to the
coating operation.
The Coating Advisor and/or other Jotun Representatives shall use this meeting to
ensure that the other parties are familiar with the products to be used, the coating
specification, safety data sheets etc. Furthermore, responsibilities are to be
stressed, i.e. possible consequences of any non-conformances, and the Painting
Contractor’s obligation to follow up his own work during the whole operation,
including compliance with Jotun’s specifications.
Before starting the work it is essential that the tanks are in a suitable condition.
All vulnerable fittings should be masked off with a suitable protective material to
avoid possible damage.
All hot work within the tank and at its outside must be completed before grit
blasting takes place (in order to avoid formation of mill scale and weld fumes,
which is not easily removed by grit blasting).
4.1 General
A suitable and safe system for temporary scaffolding is to be provided. The
construction shall permit easy cleaning operations. It should be possible to
conveniently ‘turn’ all boards so that grit and dust can be easily removed.
Scaffolding tubes are to be capped at open ends using wooden or hard rubber
stoppers. Taping the ends is not recommended.
4.2 Access
The scaffolds must provide free access to all surfaces to be treated without
having to move planks or erect temporary ladders. It must also provide adequate
working space and support for the maximum numbers of workers. The scaffold
design must not hinder ventilation in any way.
The order is important. If, for instance, blast cleaning is done prior to washing,
the contaminants will be smeared into the surface, and the subsequent washing
will probably not remove them adequately.
For ships where the ballast tanks are constructed as integral parts of block
sections, coating work will take place both at the block stage and at the assembly
stage. Hence, one may find it required to repeat some of the steps above.
For all new building projects it may be difficult to obtain a satisfactory steel
surface roughness at all places. In particular, the erection joint welding seams
and plate edges that have been made by flame cutting may not have the desired
roughness. If possible, manual grinding should be undertaken if no other means
are acceptable.
As soon as possible after the surface pre treatment, the first coat of paint should
be applied all over the tank. In this way one avoids that bare steel areas are left
uncoated for prolonged times, possibly resulting in contamination and rusting.
After a first coat the normal procedure will be to apply two stripe coats, each in a
contrasting colour, before the next full coat.
For a tank coating job the tank may be split is sections, where the work is
finished section wise. A typical situation may be that the upper part of the tank
is being coated while leaving the lower part untreated or partly coated and
protected by a temporary shield.
5.2 Refurbishment
For refurbishment blast cleaning may not be permitted, and water jetting with or
without abrasives may be an alternative. In this case it must be ensured that the
water is sufficiently clean, and the pressure at the nozzle high enough to ensure
an adequate cleaning result. A thorough water removal (as well as removal
of the abrasives, if employed) and drying must be made as soon as the water
jetting is finished, in order to avoid flash rust. A drawback associated with water
jetting is that it does not produce roughness. Insufficient steel work at the new
building stage may thus have consequences for the coating work at subsequent
refurbishment jobs.
As can be concluded from the considerations above, wet abrasive blasting will
be efficient both with regard to removing dirt and salts, produce roughness and
maintain a good working environment (without the blast cleaning dust problem),
all in one operation. However, the practical arrangements required in order to
remove wet grit from a tank may prevent widespread use of the wet abrasive
blasting method.
The existing tank coating must be assessed with regard to type and present
condition. Its compatibility with the new system must be verified. Care should
also be taken to obtain a smooth overlap between the old coating and bare steel
areas resulting from paint damage. It may be necessary to sweep blast or in other
ways roughen the surface, as well as cleaning it.
6.1 General
The cleanliness and surface roughness shall be assessed according to the ISO
8501 and 8503-2 standards, respectively, unless otherwise specified in the
technical data sheets.
Some coatings may be applied onto surfaces that are cleaned by way of Water
Jetting or Wet Abrasive Blast Cleaning. For these surfaces reference is made to
SSPC-VIS 4 / NACE VIS 7 and SSPC-VIS 5 / NACE VIS 9, respectively.
For a tank where a previous coating is not being removed (e.g. a shop primer,
or at refurbishment), special care must be taken not to damage this coating. On
the other hand, the old coating must be made thoroughly clean. Fresh water
washing, when required also with solvent borne or water borne detergents should
be employed as required. Similarly, sweep blasting or other means of creating a
rough surface may be required to obtain sufficient adhesion.
Likewise, sweep blasting must be done when an old glossy and hard coating,
typically a coal tar epoxy coating, is to be re-coated. Instead of sweep blasting
sand paper (or emery paper) may be employed in order to obtain sufficient
surface roughness of old paint.
Undercuts and surface indentations with a depth exceeding 0.8 mm and a width
less than its depth should be repaired by welding and grinding. Weld blowholes
shall be repaired by welding and grinding.
Air driven tools for steel repair and cleaning are commonly oil lubricated, and
oil may come out of the exhaust pipe within the tank. Special care should be
taken to avoid this. Any oil contamination must be thoroughly removed by use of
a suitable solvent after steel repair and smoothing / cleaning work.
If the steel repair work will not be succeeded by blast cleaning, steps should be
taken to produce some roughness at this stage. Grinding roundels, fibre discs
with particles (‘Scotch-Brite Clean N Strip’ wheels, or equivalents) and sand
paper should be considered. Wire brushes should be avoided, as the wires will
tend to polish the steel surface rather than create roughness.
Degreasing and cleaning shall be carried out prior to grit blasting in order to
prevent contamination of the steel during blasting. Both organic (grease and
oil) and inorganic (particularly salts) contaminations should be removed before
blast cleaning. If blasting is done prior to cleaning; grease, oil, salt and dirt may
be smeared into the roughened steel surface thus making subsequent cleaning
difficult and time consuming. For this reason it is, in case of refurbishment jobs,
important to break any intact blisters before washing is performed, so that the
blister contents may be removed.
Verification that the steel surface is sufficiently clean should, however, be done
after grit blasting (or water jetting) has taken place. This is in order to ensure
that the blasting / jetting process has not contaminated the surface after the
degreasing and cleaning operations.
Remove oil and grease deposits using scrubbing brushes and a water-based
alkaline degreasing detergent. Repeat this process until water no longer ‘snakes’
or ‘beads’ when poured down the surface. After degreasing, all tank surfaces
must be high-pressure fresh water washed to remove traces of detergent and
contaminations such as acidic weld smoke residues and traces of sea water salts.
These species will, beneath a coating, lead to blistering by an osmotic effect.
Note: Why start cleaning at the bottom, moving upwards? Because this will
make the surface more evenly clean. If one starts at the top the dirt will tend to
accumulate on the lower areas.
Condensation of water onto the steel surface must be avoided during blast
cleaning. Hence the steel temperature must be kept at least 3ºC above the dew
point of air. The relative humidity must be kept sufficiently low throughout
the blasting operation until immediately prior to application of the first coat.
If required, this must be accomplished by way of dehumidification equipment.
Care should be taken to produce a positive pressure inside the tank, so that no
moist air from the outside will get into the tank.
During the grit blasting operation, forced ventilation may be required to give
adequate visibility for the operator. A flexible ventilation system should be used
to get dusty air out, and fresh air in.
In connection with manholes, ladders and tank entrances adequate covering must
be provided to prevent water, dust or other contaminants from entering the work
areas during grit blasting and thereafter.
In the case of wet abrasive blasting the relative humidity requirements become
irrelevant. However, to suppress the tendency to flash rusting, the tank should be
dried to max 85% relative humidity as soon as possible after blasting.
6.5.2 Abrasives
The selected abrasive medium must be compatible with both the surface to be
blast cleaned and the specified coating system. The abrasives shall meet relevant
specifications as per ISO 11124-2 & 3 (metallic abrasives), or ISO 11126-2 to 8
(non-metallic abrasives). Sampling for check should be done according to ISO
11125-1 (metallic) or ISO 11127-1 (non-metallic), and tested according to ISO
11125-2 to 7 or ISO 11127-2 to 7 as appropriate.
Surface preparation shall not be considered complete until the blast cleaned
surface is free of dust and particles that may remain on the surface. Vacuum
cleaning will be required.
This procedure is applicable for the scaffolds as well. Scaffolding planks must
be vacuum cleaned, turned, and vacuum cleaned again. Any ends of tubular parts
of scaffolding that have accidentally been opened shall be vacuum cleaned at the
entrance and then closed with wooden or hard rubber plugs.
For other objects there may be other limits. The NORSOK standard M-501
‘
Surface preparation and protective coating’ specifies max 20 mg/m2 NaCl for
‘
offshore installations and associated facilities’. The NORSOK specification is
limited to new steel constructions. For ‘old’ steel (i.e. refurbishment) one has
experienced that it is difficult to obtain as low salt levels as for new steel, due to
the surface degradation.
Salt determination shall be done by the ISO 8502-6 method using the Bresle
sampling equipment . Bresle sampling and testing should be carried out randomly,
but with an emphasis on places that typically have higher salt levels: flat horizontal
surfaces, corners and the tank floor. The number of tests per tank should be
discussed and agreed in the pre-project meeting. Depending on the size of the tank,
a suitable number of tests could be one test for every 150-300 m².
If the tank is found to have too high surface salt levels, re-washing must be done.
Dust remaining on the steel surface may give poor coating adhesion. The dust
level can be determined by way of ISO 8502-3:1992 ‘Assessment of dust on steel
surfaces prepared for painting (pressure-sensitive tape method)’.
7.1 General
All work in adjacent areas, which may negatively affect the quality of the coating
application, or imply safety hazards, should be completed or stopped before
starting the coating application. It is vitally important that sufficient ventilation,
dehumidification, heating equipment and lighting is provided to meet conditions
as described in the technical data sheets, this Code of Practice, and regulations
given by relevant authorities.
The steel surface conditions must be as described in the previous section, and
following the agreed specifications for the project.
The 1st full coat should be applied before stripe coating so that most of the steel
is coated in its best condition – as soon as possible after grit blasting. Delaying
the first full coat application leads to increased possibility for contamination of
the steel with dirt, dust and human sweat. The 1st stripe coat should have the
same colour as the 2nd full coat.
For ease of inspection – and for ease of application, the 2nd stripe coat should
have the same colour as the 1st full coat. By doing this the 2nd full coat will be
applied to a surface of uniform colour.
When a three-coat system is specified, the last coat should preferably have a
colour different from the 2nd coat, in order to secure that all areas receive the
last coat as well.
8.1 General
Safety is the overriding consideration for all tank coating work, and the
responsible Contractor’s Safety Officer must be made fully aware of all aspects
of the operation, and all potential dangers.
• Explosion or fire
Before the coating work starts, authorised personnel from the Contractor shall
review the work arrangements of the Painting Contractor to ensure that no
procedure that could endanger any person’s health will take place.
The Coating Advisor shall be provided with safety regulations valid for the
Contractor’s plant.
The Contractor and Painting Contractor must be provided with Jotun’s safety
data sheets.
Areas where work is in progress must be clearly identified and sectioned off.
Hazard warnings showing ‘EXPLOSION RISK’ and ‘NO SMOKING’ must be
placed clearly visible around all tank entrances during the coating operation and
shall not be removed before the concentration of flammable vapours is too low to
cause a fire hazard. Such hazard warnings should be placed at 10 metres distance
from the tank entrance(s).
Lights, including hand torches, must be no more than 24-Volt and certified by
the manufacturer as flash proof or suitable for use in a solvent-laden atmosphere.
Personnel working in confined spaces during paint application and curing must
wear rubber-soled shoes.
Mobile telephones and battery operated cameras must not be used inside or near
tanks or ventilation outlets until paint fumes are totally dispersed.
The solvent content of the paint, as well as added thinner, may present limitations
when it comes to the application process, both with regard to fire hazards and the
paint applicators’ health. Any organic solvent-based coating can give off sufficient
solvent vapour to produce an explosive mixture in a tank. This can not be tolerated,
as one can never be 100% sure that a spark or other form of ignition will occur.
The solvent (and thinner) may also produce an atmosphere which is dangerous
to the health of personnel in the tank. Either of these circumstances will dictate a
minimum forced ventilation to be arranged. However, nowadays paint applicators
always use fresh air masks, and are not dependent on the tank atmosphere for
breathing. Therefore, it is the fire and explosion risk that will have to be assessed
and controlled in ballast tank coating projects.
Mixtures of organic solvents (or thinners) and air are explosive in a wide
concentration range; usually from about 1% up to about 10%. These limits are
called the Upper and Lower Explosive Limits, abbreviated as UEL and LEL,
respectively. To eliminate the explosion risk the vapour concentration must
be well below the lower explosive limit all the time. For safety reasons one
generally says that the maximum permissible concentration of solvent or thinner
in the tank atmosphere is one tenth (10%) of the LEL, i.e 0.1%.
Long before the vapour concentration reaches the LEL the atmosphere in a
confined space like a tank will be intolerably unpleasant, with irritating skin
effects and pain to the eyes. These symptoms must be taken as a warning sign
that better ventilation is needed.
For successful removal of solvent fumes, suction from the lower sections of the
tank is required (solvent fumes are heavier than air).
To find the required air quantity we first calculate the total solvent content of the
paints (and thinners) used. It is assumed that all this solvent will evaporate and
contribute to an explosive atmosphere. These solvents must not constitute more
than 0.1% of the air in the tank (10% of the LEL), and in this way the required
air volume is found.
The Required Air Quantity, RAQ, is the amount of air needed for each litre of
paint to ventilate to the required level. Relevant RAQ values are given in the
below standing table. In this table also relevant thinners are listed. To find the
total RAQ the demands from the paint and the added thinner must be added.
The quantity of ventilation required in cubic metres per minute during the
application and drying can be calculated from the formula:
Coatings and thinners listed are not necessarily approved for tank use.
Likewise, there may be approved tank products not listed.
Example: We plan to coat a 650 m3 tank with one coat of Balloxy HB Light 200
µm dry film thickness. The tank has a calculated surface area of 1260 m2. The
paint will be thinned 5% (Thinner no. 17). Application speed is 3.5 litres per
minute. How much fresh air must be blown into the tank per minute to eliminate
the explosion risk? And for how long time? The ambient temperature is 23
degrees C.
An authorised person must check the solvent vapour content before work starts
and at regular intervals (i.e. every two or three hours thereafter) until the tank
coating work is finished. Particular attention must be paid to ‘dead spots’ in
the tank, where high concentrations may occur locally. The maximum allowed
solvent concentration is 0.1% at all times. If the solvent concentration rises
above 0.1%, painting must stop until the vapour concentration is reduced to a
safe level again.
Jotun A/S
P.O. Box 2021,
N-3248 Sandefjord,
Norway
Tel: +47 33 45 70 00
Fax: +47 33 46 46 13
www.jotun.com