GENERAL
These specifications are intended to cover the construction of the proposed building as shown on
the plans and described in these Specification. These entire works is to be finished in every part with a
first class job to the full intent and meaning of the plans and specification.
SCOPE OF WORK
All concrete works shall be done in accordance with standard SPECIFICATION AND
REINFORCED CONCRETE as adopted by the government in as far as it does not conflict with specified
provisions here for CONCRETE MASONRY and revised proportioning of concrete as specified here
after.
All cement to be used in this construction must be Portland cement of standard brand approved
by the government. All sand and gravel or crushed rock must be free from dirt or organic matter.
HOLLOW BLOCKS
Used 150 x 200 x 400 mm. Non-load bearing hollow blocks for all exterior walls and 100 x 400
mm. hollow blocks for interior partitions as indicated on plans.
FLOOR SLAB
Plain concrete slab finish shall be used for all flooring minimum thickness shall be 100 mm.
TILEWORKS
Bathroom, unless otherwise specified shall be waist coated with glaze the 200X200mm tile on
flooring 300X300mm on bathroom wall. All glazed tile shall be laid on mortal cement mortal 1:3 mixed
and 1/8 inch apart care must be properly filled around the plumbing fixtures fitting the floor drains.
CARPENTRY
All lumber shall be of approved quality on respective type required for the various part of the
work, well-seasoned, thoroughly dried and free from large loose or unsound knots. All woodworks must
be done in fine and high quality workmanship.
Exterior door shall be panel type, with kild dried wood materials. Storage door shall be hollow
core panel and pvc door in T&B with louvers. All doors shall be 1 ¾ thick except for closet which shall
be ¾ thick hand faced with plywood on the putter door side.
PLUMBING:
All plumbing work shall be done in accordance with the general code and the existing and latest
local ordinances. The minimum supply pipe shall be ½ in diameter.
ELECTRICAL:
All electrical items and installations covered by main construction shall conform with existing
and latest local ordinances or Philippines Electrical Code
PAINTING:
a. Wet thoroughly the surfaced to be painted with clean water immediately before
applying paint.
b. Used two (2) coatings to be obtained waterproof and smooth finish surfaced. Do not
apply the coatings (2nd) until 24 to 28 hours after the first coat has been applied.
b. Allow the first coat to dry thoroughly before the second coat is applied.
c. All nail holes cracks and defects shall be put led up smoothly.
Interior wood surfaces may either be painted or varnished as directed. Such surfaces to be
painted or varnishing shall be thoroughly cleaned to be applied to woodwork. It must be smoothly hand-
dressed and wall sand papered. All spaces, knots, shakes, and other defects shall be given a coat of shellac
before any paint is to be applied to woodwork. All painting shall be done on two coatings. No painting
shall be done on two coating continuously at the same time. All colors shall be in accordance with