Professional Documents
Culture Documents
Singapore SMCES
Important Design
Considerations in Basement
and Foundation Works –
A Case History of City’s
Tallest Building
27 September 2014
International
Plaza
Features of Development
• 64 Storeys mixed-used Tower
(Residential + Offices)
• 20 Storeys Hotel Tower
• 3 Levels of basement (18m deep) 290m
MRT Basement
Station
Floor Plan – Basements
B3 B1
B2 L1
3D View - Basements
Design Software
• ETABS Structural Analysis Package
• SAFE Concrete Slab Analysis
• RAPT Post Tension Beam Analysis
• Mega Floor Composite Slab Design
• Total 20
Boreholes
Ground Investigation
• 20 rotary drilled boreholes
• In-situ Testing
- SPT
- Pressuremeter testing
- Falling head permeability tests
• Laboratory Testing
- Classification tests
- Triaxial testing (UU & CU)
- UCS & PLT
Testing Schedule & Criteria
Subsoil Geological Profile
Foundation
Pile-Raft Foundation
Stiff Soil
L = 30m
66m
MRT Station
ERSS Wall
Bored Piles
• Wall Deflection
• BM
• SF
• Slab Forces
What are the Geotechnical Design Contribution?
• ERSS Analysis • Plaxis 2-D
• Pile-Raft Settlement Analysis • Plaxis 3-D + SAFE
• Pile Design • Excel Spreadsheet
• Deformation Analysis • Plaxis 3-D
• Damage Assessment • Plaxis 3-D + Oasys
PLAXIS 3-D Modeling
Layers Side view
4
3
Analysis results
- Vertical stress
SAFE modeling
SAFE Model
• Raft (Slab)
• Pile spring ( Reaction / Pile Head
Settlement)
• Soil spring ( Effective stress / Soil
settlement below raft)
• Uplift (not considered)
Comparison of settlement contour (Tower)
(Each pile with individual spring)
400 kPa
564 kPa
Comparison of settlement contour (Hotel)
(Each pile with individual spring)
250 kPa
384 kPa
Comparison of settlement contour (Tower)
(Spring values based on zoning)
540 kPa
400 kPa
Comparison of settlement contour (Hotel)
(Spring values based on zoning)
250 kPa
435 kPa
Independent SAFE Study
• Raft Modeled as slab
• Piles Modeled as columns with spring at toe
• Pile Spring Based on pile capacity (allowable compressive stress and
allowable settlement 15mm)
• Soil Spring From geotechnical analysis results (Allowable bearing pressure /
actual soil settlement)
SAFE Views
Comparison of settlement contour (Tower)
SAFE Plaxis 3D
Comparison of settlement contour (Hotel)
SAFE Plaxis 3D
Comparison of soil pressure (Tower)
460 kPa
400 kPa
SAFE Plaxis 3D
Comparison of soil pressure (Hotel)
250 kPa
395 kPa
SAFE Plaxis 3D
Side-by-side comparison of pile reaction along x-direction
(Tower)
Side-by-side comparison of pile settlement along x-direction
(Tower)
Side-by-side comparison of pile stiffness along x-direction
(Tower)
Load Distribution
• SAFE (independent spring) • 70% : 30%
• SAFE (from Plaxis 3D) • 65% : 35%
• Plaxis 3-D • 62% : 38%
26mm 13mm
15mm 21mm
Tower Hotel
(26-13)/11200 = (21-15)/6550 =
1:861 <1:500 (OK) 1:1091 <1:500 (OK)
What are the Geotechnical Design Contribution?
• ERSS Analysis • Plaxis 2-D
• Pile-Raft Settlement Analysis • Plaxis 3-D + SAFE
• Pile Design • Excel Spreadsheet
• Deformation Analysis • Plaxis 3-D
• Damage Assessment • Plaxis 3-D + Oasys
Bored Pile Design
• Pile design carried out in accordance with SS CP4:2003
• Working load on each pile checked against pile structural capacity as well as
geotechnical capacity
• Assumed design parameters to be verified by “Ultimated Pile Load Tests”
What are the Geotechnical Design Contribution?
• ERSS Analysis • Plaxis 2-D
• Pile-Raft Settlement Analysis • Plaxis 3-D + SAFE
• Pile Design • Excel Spreadsheet
• Deformation Analysis • Plaxis 3-D
• Damage Assessment • Plaxis 3-D + Oasys
Why 3-D. . .???
• Due to complex soil-structure and structure-existing structure interactions
• Sequential excavation zones proposed by Contractor was expected to significantly
impact on predicted movements around a non-regular basement
• Simpler analyses software was not deemed appropriate for estimation of the
resulting wall deflections and movement of soils surrounding the new basement.
• 3D modeling was employed in a number of different ways for the project:
To investigate the effect of proposed excavation sequence
To investigate soil structure interactions (for both the new structure and existing
MRT box)
3-D Modelling
• Model size 300m x 80m
• About 83, 620 nodes
• Hardening Soil Model
• Drained Analysis
• Pheratic Water Level
• Tower loadings
• arkers
3-D Modelling
• Point loads for Columns
• Line loads for Wall
Loads
• Surface Loads for Area
Loads)
3-D Modelling
Embedded piles
3-D Modelling
What are the Geotechnical Design Contribution?
• ERSS Analysis • Plaxis 2-D
• Pile-Raft Settlement Analysis • Plaxis 3-D + SAFE
• Pile Design • Excel Spreadsheet
• Deformation Analysis • Plaxis 3-D
• Damage Assessment • Plaxis 3-D + Oasys
Damage Assessment
• Shallow Foundation
• Preliminary Check: settlement
<10mm or rotation<1/500
• Secondary Check: Burland’s
Chart method
• Differential settlement: <1/500
Damage Assessment
In-wall Inclino
In-soil Inclino
IW+PZ+WS
IS+PZ+WS
BS
Tiltmeter
GS
VT
Monitoring Instruments_Excavation
• Excavation Instruments
- Inclinometers (In-wall & In-soil)
- Piezometers
- Water Standpipes
• Building Instruments
- Building settlement markers
- Tiltmeter
- Vibration transducer
• Ground Instruments
- Settlement markers
Monitoring Frequency
Long Term Monitoring
• To monitor the followings in long term condition
• Settlement of tower
• Bearing pressure of the soil underneath the raft
• Uplift pressure built up at the base of raft
• Monitoring Instruments
• Building Settlement Markers Tower Settlement
• Flat Cells & Strain Gauge Load distribution of raft & pile
• Piezometers
Long Term Monitoring
• Settlement of Tower • Settlement Markers
• Load distribution of Pile-Raft • Flat Cells + Strain Gauge
• Uplift pore pressure built up • Piezometers
beneath the raft
Monitoring for Office Tower
Settlement Monitoring for Office Tower
Conclusion . . .
• Pile-raft is an innovative and economical solution, effective control over
differential settlement and reduce soil bearing pressure
• Performance of ERSS well within the predicted values
• Pore pressure drop during basement excavation due to stress release as well as the
drained behaviour of Jurong Formation
• No significant settlement due to pore pressure drop.
Site Photos