Professional Documents
Culture Documents
Lecture # 19
(Permeability through Stratified Soils)
by
Dr. Muhammad Irfan
CEO, Birudo Engineers
Visiting Faculty, FAST NUCES Lahore
Email: mirfan1@msn.com
Lecture Handouts: https://bit.ly/30VJDtB
1
Equivalent Hydraulic Conductivity of Stratified Soils
Permeability Parallel to Stratification
Velocity of flow ‘v’ → different for all layers
Hydraulic gradient ‘i’ → same for each layer
Taking third dimension (i.e. into the plane of paper) as unity
q = v⋅ A q = v ⋅ (1 ⋅ H ) q = kH ⋅ i ⋅ H
q = k H 1 ⋅ i ⋅ H1 + k H 2 ⋅ i ⋅ H 2 + k H 3 ⋅ i ⋅ H 3 +
+ k Hn ⋅ i ⋅ H n
k H ⋅ i ⋅ H = k H 1 ⋅ i ⋅ H1 + k H 2 ⋅ i ⋅ H 2 + k H 3 ⋅ i ⋅ H 3 +
+ k Hn ⋅ i ⋅ H n
k H 1 ⋅ H1 + k H 2 ⋅ H 2 + k H 3 ⋅ H 3 + + k Hn ⋅ H n
kH =
H
2
Equivalent Hydraulic Conductivity of Stratified Soils
Permeability Perpendicular to Stratification
Velocity of flow ‘v’ and discharge ‘q’ → same through each layer
Hydraulic gradient ‘i’ and head loss ‘h’ → different through each layer
h
h = h1 + h2 + h3 + hn i=
H
h = i1 ⋅ H1 + i2 ⋅ H 2 + i3 ⋅ H 3 + in ⋅ H n (1)
kv = average permeability perpendicular to
stratification
v = kv ⋅ i
Also,
v v v
i1 = i2 = i3 =
kv1 kv 2 kv 3
Replacing in eq. (1) H
kV =
v ⋅ H v ⋅ H1 v ⋅ H 2 v ⋅ H 3 v ⋅ Hn H1 H 2 H 3 H
= + + ++ + + ++ n
kV kV 1 kV 2 kV 3 kVn kV 1 kV 2 kV 3 kVn
3
Practice Problem #6 (contd…)
k H 1 ⋅ H1 + k H 2 ⋅ H 2 + k H 3 ⋅ H 3 + + k Hn ⋅ H n
kH =
H
H
kV =
H1 H 2 H 3 H
+ + ++ n
kV 1 kV 2 kV 3 kVn
4
Practice Problem #6 (contd…)
5
Practice Problem #6 (contd…)
6
Practice Problem #7
On close investigation of a sample it was found to
be in three layers 20mm, 60mm, and 40mm. The
permeability of these layers are 3x10-3mm/sec,
5x10-4mm/sec, and 17x10-4mm/sec respectively.
Find kH and kV, and the ratio kH/kV.
H
k ⋅ H + k ⋅ H + k H 3 ⋅ H 3 + + k Hn ⋅ H n kV =
kH = H1 1 H 2 2 H1 H 2 H 3 H
H + + ++ n
kV 1 kV 2 kV 3 kVn
𝐾𝐾𝐻𝐻
= 1.65
𝐾𝐾𝑉𝑉
8
Practice Problem #8
9
Practice Problem #8
10
SIGNIFICANCE OF SEEPAGE STUDIES
Failure of Teton Dam
Newly completed Teton Dam as it appeared in mid May 1976, as the
reservoir was filling at the rate of 3 feet per day.
The rate of filling is usually limited to no more than 1 foot per day.
11
TETON DAM FAILURE Idaho, USA
Leakage was initially noted around 7:00 AM on Saturday June 5, 1976. This
view shows a dozer being sent down to fill in the hole at elevation 5200
around 10:45 AM.
June 5, 1976
10:45 am
12
TETON DAM FAILURE Idaho, USA
The dozer is lost in the expanding hole, around 11:20 AM on June 5th.
Note turbid nature of outflow along the abutment.
June 5, 1976
11:20 am
13
TETON DAM FAILURE Idaho, USA
Rapidly deteriorating situation as it appeared around 11:30 AM. A massive
hole has developed in the downstream face of the embankment and is
migrating upward.
June 5, 1976
11:30 am
14
TETON DAM FAILURE Idaho, USA
The hole continues to enlarge and rise toward the crest of the right abutment.
This is about 11:50 AM.
June 5, 1976
11:50 am
15
TETON DAM FAILURE Idaho, USA
Dam crest beginning to breach at 11:55 AM on Saturday June 5, 1976. Note
increasing discharge.
June 5, 1976
11:55 am
16
TETON DAM FAILURE Idaho, USA
Maximum flood discharge emanating from gap in dam’s right abutment, just after noon
on June 5th , 1976.
June 5, 1976
After noon
17
TETON DAM FAILURE Idaho, USA
Present day situation
18
OROVILLE DAM California, USA
Potential risks
While the main 770 ft (230 m) dam is not
threatened, if the erosion on either spillway
reaches the top, it would cause the weir or
gate (respectively) to collapse, causing a large
uncontrolled water release and life-
threatening floods
23
OROVILLE DAM FAILURE California, USA
CONCLUDED
25