You are on page 1of 24

Soil Mechanics [CV-231]

BSc Civil Engineering – 4th Semester

Lecture # 19
(Permeability through Stratified Soils)
by
Dr. Muhammad Irfan
CEO, Birudo Engineers
Visiting Faculty, FAST NUCES Lahore
Email: mirfan1@msn.com
Lecture Handouts: https://bit.ly/30VJDtB
1
Equivalent Hydraulic Conductivity of Stratified Soils
Permeability Parallel to Stratification
 Velocity of flow ‘v’ → different for all layers
 Hydraulic gradient ‘i’ → same for each layer
Taking third dimension (i.e. into the plane of paper) as unity

q = v⋅ A q = v ⋅ (1 ⋅ H ) q = kH ⋅ i ⋅ H

Total flow → sum of flows though each layer

q = k H 1 ⋅ i ⋅ H1 + k H 2 ⋅ i ⋅ H 2 + k H 3 ⋅ i ⋅ H 3 +
 + k Hn ⋅ i ⋅ H n
k H ⋅ i ⋅ H = k H 1 ⋅ i ⋅ H1 + k H 2 ⋅ i ⋅ H 2 + k H 3 ⋅ i ⋅ H 3 +
 + k Hn ⋅ i ⋅ H n

k H 1 ⋅ H1 + k H 2 ⋅ H 2 + k H 3 ⋅ H 3 +  + k Hn ⋅ H n
kH =
H

2
Equivalent Hydraulic Conductivity of Stratified Soils
Permeability Perpendicular to Stratification
 Velocity of flow ‘v’ and discharge ‘q’ → same through each layer
 Hydraulic gradient ‘i’ and head loss ‘h’ → different through each layer
h
h = h1 + h2 + h3 +  hn i=
H
h = i1 ⋅ H1 + i2 ⋅ H 2 + i3 ⋅ H 3 +  in ⋅ H n  (1)
kv = average permeability perpendicular to
stratification

v = kv ⋅ i
Also,
v v v
i1 = i2 = i3 =
kv1 kv 2 kv 3
Replacing in eq. (1) H
kV =
v ⋅ H v ⋅ H1 v ⋅ H 2 v ⋅ H 3 v ⋅ Hn H1 H 2 H 3 H
= + + ++ + + ++ n
kV kV 1 kV 2 kV 3 kVn kV 1 kV 2 kV 3 kVn
3
Practice Problem #6 (contd…)

k H 1 ⋅ H1 + k H 2 ⋅ H 2 + k H 3 ⋅ H 3 +  + k Hn ⋅ H n
kH =
H

H
kV =
H1 H 2 H 3 H
+ + ++ n
kV 1 kV 2 kV 3 kVn

4
Practice Problem #6 (contd…)

5
Practice Problem #6 (contd…)

6
Practice Problem #7
On close investigation of a sample it was found to
be in three layers 20mm, 60mm, and 40mm. The
permeability of these layers are 3x10-3mm/sec,
5x10-4mm/sec, and 17x10-4mm/sec respectively.
Find kH and kV, and the ratio kH/kV.
H
k ⋅ H + k ⋅ H + k H 3 ⋅ H 3 +  + k Hn ⋅ H n kV =
kH = H1 1 H 2 2 H1 H 2 H 3 H
H + + ++ n
kV 1 kV 2 kV 3 kVn

𝐾𝐾𝐻𝐻
= 1.65
𝐾𝐾𝑉𝑉
8
Practice Problem #8

9
Practice Problem #8

10
SIGNIFICANCE OF SEEPAGE STUDIES
Failure of Teton Dam
Newly completed Teton Dam as it appeared in mid May 1976, as the
reservoir was filling at the rate of 3 feet per day.
The rate of filling is usually limited to no more than 1 foot per day.

Mid May 1976


Newly completed Teton Dam

11
TETON DAM FAILURE Idaho, USA
Leakage was initially noted around 7:00 AM on Saturday June 5, 1976. This
view shows a dozer being sent down to fill in the hole at elevation 5200
around 10:45 AM.

June 5, 1976
10:45 am

12
TETON DAM FAILURE Idaho, USA
The dozer is lost in the expanding hole, around 11:20 AM on June 5th.
Note turbid nature of outflow along the abutment.

June 5, 1976
11:20 am

13
TETON DAM FAILURE Idaho, USA
Rapidly deteriorating situation as it appeared around 11:30 AM. A massive
hole has developed in the downstream face of the embankment and is
migrating upward.

June 5, 1976
11:30 am

14
TETON DAM FAILURE Idaho, USA
The hole continues to enlarge and rise toward the crest of the right abutment.
This is about 11:50 AM.

June 5, 1976
11:50 am

15
TETON DAM FAILURE Idaho, USA
Dam crest beginning to breach at 11:55 AM on Saturday June 5, 1976. Note
increasing discharge.

June 5, 1976
11:55 am

16
TETON DAM FAILURE Idaho, USA
Maximum flood discharge emanating from gap in dam’s right abutment, just after noon
on June 5th , 1976.

June 5, 1976
After noon

17
TETON DAM FAILURE Idaho, USA
Present day situation

18
OROVILLE DAM California, USA

Oriville Dam – Normal Operations


 The lake level is controlled using the main
spillway gate, which releases water down the
concrete spillway to get to the river below.
 The emergency spillway, which has a 30 ft
(9 m) high concrete wall at the top of a hill, is
unused.
19
OROVILLE DAM California, USA

Oriville Dam – Normal Operations 2005: Upgrade proposal rejected


 The lake level is controlled using the main Despite concerns that the emergency spillway
spillway gate, which releases water down the is vulnerable to erosion, a $100 million
concrete spillway to get to the river below. request by community groups to upgrade it to
 The emergency spillway, which has a 30 ft
(9 m) high concrete wall at the top of a hill, is
a concrete-lined auxiliary spillway is rejected
unused. by the federal regulators
20
OROVILLE DAM FAILURE California, USA

7-Feb-2017: Main spillway fails 11-Feb-2017: Emergency spillway used


Craters appear in the main spillway. To avoid Water flows over the emergency spillway
increasing the damage to the spillway, water causing erosion and damage. This is by
releases are slowed allowing the lake to rise. design and prevents water going over the top
of the main dam. However the ground erodes
faster than expected.
21
OROVILLE DAM FAILURE California, USA

13-Feb-2017: Repairs made Potential risks


Rocks and concrete (1) are placed under the While the main 770 ft (230 m) dam is not
emergency spillway weir to repair erosion damage threatened, if the erosion on either spillway
(2). The release of water into the main spillway is reaches the top, it would cause the weir or
increased, to lower the lake in preparation for more
rain. This erodes the adjacent hillside considerably,
gate (respectively) to collapse, causing a large
generating a debris dam (3) that blocks the river and uncontrolled water release and life-
forces the closure of the hydroelectric plant. threatening floods
22
OROVILLE DAM FAILURE California, USA

Potential risks
While the main 770 ft (230 m) dam is not
threatened, if the erosion on either spillway
reaches the top, it would cause the weir or
gate (respectively) to collapse, causing a large
uncontrolled water release and life-
threatening floods
23
OROVILLE DAM FAILURE California, USA

March 2011 7-Feb-2017 27-Feb-2017


Damage to the main spillway began as a crater in the middle (center) and eventually resulted in a
separate channel eroded to the side (right). At left, the main spillway is shown in March 2011 while at
its maximum discharge rate. 24
REFERENCE MATERIAL
Principles of Geotechnical Engineering – (7th Edition)
Braja M. Das
Chapter #7 & 8

CONCLUDED

25

You might also like