You are on page 1of 4

BEST PRACTICE GUIDES FOR IN-SITU CONCRETE FRAME BUILDINGS ...

... FROM THE EUROPEAN


CONCRETE BUILDING PROJECT
Early striking and
improved backpropping
for efficient flat slab construction

Introduction
The European Concrete Building
Project is a joint initiative aimed at
improving the performance of the
concrete frame industry.

The principal partners in the world’s


most ambitious concrete research
programme are:

British Cement Association


Building Research Establishment
Construct – the Concrete Structures
Group
Reinforced Concrete Council
Department of the Environment, Figure 1: Table forms at Cardington
Transport and the Regions

The programme involves the This Guide provides new and improved recommendations
construction of a series of full-sized for striking formwork and gives new procedures
concrete structures in the Large
Building Test Facility at Cardington, for backpropping reinforced in-situ concrete flat slabs
where they are being subjected to (less than 350 mm thick).
comprehensive testing of the building
process and of their performance.
Key messages
With support from the DETR and the Early* striking of formwork and improved backpropping procedures increase
Engineering and Physical Sciences construction efficiency by:
Research Council, the first of these
buildings, a seven-storey in-situ flat • Allowing early access to the supporting floors by following trades.
slab concrete frame, was completed • Enabling greater re-use of formwork.
in 1998. The results of investigations
into all aspects of the frame • Reducing the quantity of formwork and falsework required.
construction process are summarised *Early in this context is defined as concrete less than three days old.
in this series of Best Practice Guides.

These Guides are aimed at all Best practice


those involved in the process of Optimise formwork use by:
procurement, design and construction
of in-situ concrete frames. They • Determining backpropping loads during construction using empirical methods for simple
should stimulate fundamental change repetitive structures and a three-dimensional approach for special structures.
in this process in order to yield
significant improvements in the cost,
• Determining required striking concrete strength from serviceability criteria.
delivery time and quality • Determining early concrete strength in-situ, using pull-out inserts. (See companion
of these structures. Best Practice Guide, Early age strength assessment of concrete on site.)
• Striking formwork in an agreed sequence after consideration of concrete pouring sequence.
• Controlling the loads on newly struck slabs until they have gained the required strength.

CONSTRUCT
concrete structures group
www.bca.org.uk www.bre.co.uk www.construct.org.uk www.rcc-info.org.uk www.detr.gov.uk 1
Introduction Table 2: Sequence of striking flat slabs

The use, installation and striking of


• Obtain approval to strike
falsework and backpropping* is a vitally
important part of the safe and economic • Check the safety precautions REINFORCED
construction of in-situ concrete • Strike according to guidance given below CONCRETE SLAB
and as illustrated.
structures. In order to strike a slab, the
◊ Strike reinforced concrete slabs in two stages:
concrete must be strong enough to
1. Ease all the supports
avoid failure or undue cracking and
2. Starting at midspan, remove supports POST-TENSIONED
deformation of the slab. Recent research CONCRETE SLAB
working towards columns and walls.
during the construction of the European
◊ Post-tensioned slabs will tend to lift off
Concrete Building Project (ECBP) in-situ the formwork on tensioning, but use
building at Cardington has led to a new method for rc above.
REINFORCED
understanding of the construction ◊ On large slab areas, comprising internal CONCRETE
process. It is now possible to make and edge panels, strike internal CANTILEVER
bays first, followed by edge and corner bays.
savings in construction time and on
◊ Where soffit form is part of cantilever,
temporary works equipment while start removal from tip and work towards
maintaining site safety and the wall, beam or columns. POST-TENSIONED
performance of the constructed flat slab ◊ Post-tensioned cantilever slabs may have CONCRETE
special striking requirements due to CANTILEVER
frame. This Guide summarises the new
deflection of adjacent spans.
recommendations for formwork striking
and slab backpropping. For a detailed
analysis and a worked example
see Guide to flat slab formwork
and falsework (Ref. 1).
Figure 2: Diagrammatic representation of backpropping

*Backpropping is defined as
propping installed at levels below
the slab supporting the falsework. One level Two levels
of propping Load of propping
It is done to distribute the load
applied to the uppermost slab
to suitable supports, such as Slab to be cast
lower slabs or foundations Falsework wp
Supporting slab (1)

Planning the striking Backprops wb1


Lower slab (2)
sequence
Backprops (when fitted) wb2
The striking of formwork and falsework
Lower slab (3)
from a slab needs careful consideration.
The constructor is responsible for
carrying out the striking process safely.
It is the responsibility of the Temporary
Works Co-ordinator (TWC) to manage
the risks in early striking. This will
Table 3: Load distribution by backpropping
include preparing detailed procedures
and method statements, which should
be approved by the safety officer and Location Load No backprops One level of Two levels of
Permanent Works Designer (PWD). backprops backprops

The PWD’s role is to provide design On slab On slab In props On slab In props
information so that the construction New slab being cast total 100% 100% 100%
methods do not adversely affect the Falsework/formwork wp 100% 100% 100%
performance of the structure. On supporting slab (1) 100% wp 70% wp 65% wp
All technical and managerial staff
must be fully aware of the implications In backprops wb1 30% wp 35% wp
of the methods and procedures adopted. On lower slab (2) 30% wp 23% wp
Flow charts for striking and back- In backprops wb2 12% wp
propping procedures are given in Ref. 1. On lower slab (3) 12% wp

Construction load Notes


1. Assumes lower and supporting floors have been struck, have taken up their deflected
considerations shape and are carrying their self-weight
In multi-storey in-situ concrete 2. Floor loading from imposed loads and self-weight is not considered
construction, the critical loading 3. The strength of particular slabs to carry applied loads will have to be
condition for a slab is not necessarily considered separately
when it is struck and becomes self- 4. All floors are suspended floors
5. Figure 2 gives location of loads wp, wb1, and wb2

2
supporting but often when it is called Before striking However, the nature of the structure
upon to support the weight of a freshly The TWC will have assessed construction may dictate the procedure adopted
cast slab above. imposed loads when determining the (see Table 2). The TWD, in co-
required strength for striking but this operation with the PWD, should
Before concreting operations must be checked, by site inspection, stipulate the method and procedure
To cast the new slab, the supporting against actual loading. Consideration for the removal of the formwork.
slab immediately below should have must be given to the timing of the
sufficient capacity to carry the loads loading of the struck slab, especially After striking
imposed on it during construction. where flying or tableform systems As the concrete gains strength with
The loads on the supporting slab are: are quickly moved onto it. maturity and approaches design
strength, the construction load can
• Self-weight of supporting slab
(at 24 kN/m3). be increased. Early striking will allow
Determining the required maximum re-use of formwork
• Any construction load on the concrete strength for striking and falsework, and clearance of the
supporting slab. supporting floor and any lower levels
The recommended method is based
• Total construction load of the new of backpropping. The procedure should
on serviceability considerations, as in
slab, i.e. make allowance for loading regimes
practice these are critical. The basis
after early striking. It is good practice
◊ weight of concrete in new slab plus of this determination is fully detailed
once a floor is struck to install
◊ the self-weight of the temporary in ECBP research report BR394
backpropping beneath it at the earliest
works plus (Ref. 2)
opportunity; this will then help
◊ construction live load on new slab. The required strength of a concrete slab distribution of subsequent loads.
for striking depends on:
If the supporting slab has sufficient
capacity to carry the loads imposed, • Characteristic design service load. Deflection of slabs
backpropping is not required. If it does
not then backpropping is required (see
• Construction load. subjected to early striking
‘Design of backpropping’ on page 3). • Characteristic concrete design Deflection of concrete sections is
strength. closely linked to the extent of cracking
Before they are loaded, the concrete • Actual concrete characteristic and the degree to which the cracking
strength required in backpropped strength at the time of striking. capacity of the section is exceeded.
supporting slabs should be calculated Research at ECBP has shown that,
using the determinations in Table 1. The formula for calculating the required
provided the strength of the concrete
It should be noted that w will be much early striking strength is given by
at time of striking meets Determination 2
higher than for the new slab Determination 2 in Table 1. This gives
in Table 1, there is no significant effect
(see Table 3.) Determination 1 might the characteristic strength of concrete
on the total deflection.
be critical and this temporary condition fc required for early striking. It is
recommended that a minimum live Ongoing research on long-term
might need to become a design load
construction load of 0.75 kN/m2 be (3000 days) deflection indicates that,
case agreed with the PWD.
used for the slab. This load should compared with striking at 7 days,
be added to the slab self-weight to striking at 24 hours increases long-term
Table 1: Determination of strength
calculate w. An alternative graphical deflection by 25% and, at 3 days, by
required for early striking of flat slabs
method of obtaining fc is given in Ref. 1. 15%. ECBP slabs struck at 19 hours
remain within design limits.
These formulae apply for flat slabs Measurement of early age Traditionally, UK design codes have
300 mm thick or less
concrete strength placed limits on the ratio of span to
effective depth. These have led to an
Determination 1 For early striking, the in-situ strength
acceptable serviceability condition for
of the concrete should be determined.
most flat slab structures without
w The Best Practice Guide Early age
≤ 1.0 necessarily addressing current needs
wser assessment of concrete on site
for early-age loading. However, it can
recommends the Lok test or similar
be generally assumed that early striking
as it tests the actual cast concrete. The
Determination 2 will not significantly affect total
area to be struck should be determined
deflection This is considered further
w 1.67 in advance and the location of the most
( in Section 6.3 of Ref. 1.
fc ≥ fcu ( wser
critical concrete (usually the least
mature) should be established
and tested. The average result of four Design of backpropping
where or more tests is used to estimate the The requirement for backpropping
wser is the total unfactored design existing characteristic strength (fc) and its installation is not strictly part
service load, kN/m2 in Determination 2 for the area to of striking formwork. It has been
w is the total unfactored be struck. included in this Guide as the recent
construction load on the slab research at Cardington (Ref. 2) has
considered, kN/m2
Striking sequence changed previous understanding
fc is the required characteristic and re-emphasised the importance
concrete strength to be able The order of striking soffit formwork
of backpropping in efficient flat
to strike the flat slab, N/mm2 is important. For early striking, the
slab construction.
sequence should follow the order
fcu is the characteristic strength
in which the concrete was poured.
of the concrete,N/mm2

3
BEST PRACTICE GUIDES FOR IN-SITU CONCRETE FRAME BUILDINGS

Determining the Determining This Best Practice Guide is based on


backpropping requirement backpropping load Guide to flat slab formwork
and falsework (Ref. 1).
The construction load is determined The backprop load and hence the
as described on page 2 under ‘Before load in the supporting slabs can be
References
concreting operations’. If the supporting determined by various methods using
slab has sufficient capacity to carry the both two- and three-dimensional 1. PALLETT, P. Guide to flat slab
formwork and falsework, CONSTRUCT,
loads imposed, no backpropping is analysis. These are considered further
Crowthorne. To be published in early
required, but if not then backpropping in Ref. 1. summer, 2001. 120 pp.
is required. The simplest method, to be used 2. BEEBY, A.W. A radical redesign of the
Figure 2 gives a representation for basic repetitive structures, is an in-situ concrete frame process, Task 4:
of typical backprops over different empirical method based on the Early striking of formwork and forces
numbers of floors. percentage of load transferred in two- in backprops, The University of Leeds
dimensional analysis. This is and Building Research Establishment
The number of floors to be backpropped Ltd. Report BR 394, CRC Ltd, London,
depends on the load on the slab reproduced in Table 3, which sets
2000, 106 pp inc 31/2" disk,
immediately below that being cast out the recommendation from ECBP
not exceeding the design service load. research (Ref. 2).
Best Practice Guides in this series
In practice there will be little benefit The three-dimensional approach should • Improving concrete frame construction
in having more than one level of be used for complicated structures, • Concreting for improved speed
backpropping, as can be seen from or where more precise calculations and efficiency
Table 3. The assumptions made in are required. An Excel spreadsheet • Early age strength assessment
arriving at the percentages in Table 3 for this is supplied with Ref. 1. of concrete on site
are outlined below and are explained There is a requirement, summarised • Improving rebar information and supply
in detail in Section 6.5.2 of Ref. 1. by Determination 1 in Table 1, that • Early striking and improved
They are: the design construction load should backpropping for efficient flat
slab construction
• The slabs behave elastically. not exceed the design service load.
On occasion during construction this • Rationalisation of flat slab reinforcement
• An imposed construction operations • Prefabricated punching shear
load is applied at all times. requirement may not be met. This
could occur when the self-weight is reinforcement for flat slabs
• The density of normal-weight a high proportion of the design load. • Approaches to flat slab design
concrete is 24 kN/m3. In these circumstances, the permanent These guides are available for downloading
• The backprops between the floor and temporary works designers should free at www.rcc-info.org.uk/research
slabs and the falsework shoring agree on the procedure to enable a safe
Research partners for this Guide
supporting the soffit formwork are not and economical structure to be built.
This is further considered in Ref. 1. Leeds University
rigid, i.e. they change in length with
Building Research Establishment
load. (Props of different material e.g.
steel and aluminium, MUST NOT Striking of backpropping
be mixed. The percentages given
in Table 3 are for aluminium props. In no circumstances should any
If steel props are used, the load in backpropping be removed until the
the supporting slab may be reduced formwork and falsework to the ‘new’
by 4%.) slab have been struck.
97.505
• The load applied onto the supporting Backpropping should be removed floor First published 2001
slab from the falsework is uniformly by floor in a top-down sequence. Each ISBN 07210 1556 5
distributed and, further, the back- floor’s backpropping should be struck Price group A
propping generates a uniformly in the same sequence as for falsework © BCA, BRE Ltd, Construct, RCC, DETR
distributed support system from (see Table 2). When special striking Published by the British Cement Association
underneath the slab. (This is sequences are required, which differ on behalf of the project partners.
reasonable if the backprops are from those set out above, detailed British Cement Association
spaced at least at one-third points written procedures should be provided Century House
by the TWC for site staff, and the Telford Avenue
along the supporting slab.)
operatives informed. Crowthorne, Berkshire RG45 6YS
• The load transferred through www.bca.org.uk
supporting slabs can be proportioned Backpropping should be installed as For further copies of the Best Practice Guides
pro rata to the stiffness of the slabs soon as possible after the ‘new’ slab ring the Concrete Bookshop on 01344 725704.
considered. The percentages given in has been struck. This will assist in
All advice or information from the British Cement
Table 3 are for slabs of equal stiffness. distributing the loads through the Association is intended for those who will evaluate the
supporting floors for the construction significance and limitations of its contents and take
• The backpropping is installed of the next slab.
responsibility for its use and application. No liability
(including that for negligence) for any loss resulting from
with zero pre-load. (Props are such advice or information is accepted. Readers should
‘finger tight’ to ensure stability note that all BCA publications are subject to revision from
time to time and should therefore ensure that they are in
in the unloaded condition.) possession of the latest version.

• The effects of temperature change


are ignored.

You might also like