Professional Documents
Culture Documents
Answer:
RESOURCE LEVELLING:
In project management, resource levelling is defined by A Guide to the Project Management Body of
Knowledge (PMBOK Guide) as "A technique in which start and finish dates are adjusted based on
resource limitation with the goal of balancing demand for resources with the available supply.”
Resource leveling problem could be formulated as an optimization problem. The problem could be
solved by different optimization algorithms such as exact algorithms or meta-heuristic methods.
When performing project planning activities, the manager will attempt to schedule certain tasks
simultaneously. When more resources such as machines or people are needed than are available, or
perhaps a specific person is needed in both tasks, the tasks will have to be rescheduled concurrently
or even sequentially to manage the constraint. Project planning resource leveling is the process of
resolving these conflicts. It can also be used to balance the workload of primary resources over the
course of the project[s], usually at the expense of one of the traditional triple constraints (time, cost,
scope).
CATEGORIES OF RESOURCES:
1. Labor
2. Materials
3. Equipment’s.
Critical path: it is a common type of technique used by project managers when it comes to
resource leveling. The critical path represents for both the longest and shortest time duration paths
in the network diagram to complete the project.
However, apart from the widely used critical path concept, project managers use fast tracking and
crashing if things get out of hand.
Fast tracking: This performs critical path tasks. This buys time. The prominent feature of this
technique is that although the work is completed for the moment, possibility of rework is higher.
Crashing : This refers to assigning resources in addition to existing resources to get work
done faster, associated with additional cost such as labor, equipment, etc.
Let us program activity F to start by its late start day which is day 17.
And activity I to start by day 14.
The resulting resources aggregation histogram will be as follows:
Smoothing/Leveling