A project is summarized below with CPM chart and resource requirement for each activity.

Activity Duration Number of Predecessor Activity Duration Number of Predecessor


(Week) Workers (Week) Workers

A 3 2 G 4 2 C
B 6 3 H 2 4 D, E
C 3 4 I 4 4 G, F
D 2 4 A J 4 3 G, F
E 4 4 B K 6 4 H, I
F 8 2 B

i. Draw network diagram and find critical path & project duration
ii. Calculate float time of the non-critical activities
iii. Make activity chart of the project.

Page 1 of 2
2. A project is summarized below with activities, predecessor(s) and resource requirement for each activity.
Activity Predecessor(s) Duration Number of
(Week) Workers
A - 3 2
B - 4 5
C - 3 3
D A 4 3
E B,C 3 2
F B 4 2
G D 3 2
H C 5 3
I G,H 3 4
J D,E 4 3

(i) Calculate Total float and free float time of the non-critical activities.
(ii) Make activity chart of the project.
(iii) Construct a resource-leveling chart to optimize the number of workers and find the required maximum
number of workers.

Page 2 of 2