KONTROL BALOK I-J


a Perhitungan Lendutan
Δ = βa M L2
E Ic
2
Beban Mati Q dl : 4957,00 kg/m
Md = 1/8 q l 2
= 1/8 4957 6 2 = 22306,50 kg/m2
Beban Hidup Q ll : 250 kg/m2
Ml = 1/4 P l
2
= 1/4 250 5 = 312,50 kg/m
M = Md + Ml
2
= 22306,50 + 312,50 = 22619,00 kg/m

E = 4700 fc'
2
= 4700 35 = 27805,57 Mpa = 27805574980,568 N/m
Ic = 1/12 b h 3
= 1/12 300 500 3
4 4
= 3125000000,0 mm = 0,003125000 m
2
Δ = βa M L
E Ic
= 5 x 22619,00 x 6,00 2
48 27805574980,568 x 0,0031250
= 0,1042 x 814284,00 = 0,00097616 m = 0,0976 cm
86892421,81
- L = 600
= = 3,33333 cm
∆ 180 180
-
Δ ≤ = 0,0976 ≤ 3,333 cm

b Perhitungan Lebar Retak
3
w = ( 11 β ƒs dc A ) x 10 -6
β = SKSNI menetapkan nilai = 1,2
ƒs = 0,6 fy
= 0,6 420 = 252 Mpa
dc = Jarak titik berat tulangan utama sampai keserat tarik terluar
= Selimut + Ø tl.utama / 2
= 40 + 22 / 2 = 51 mm
A = Penampang potongan tarik efektif
2 dc b
=
n
2 51 300
= = 4371,43 mm 2
7
w = Lebar retak dalam mm x 10 -6
3
w = ( 11 β ƒs dc A ) x 10 -6
3
= ( 11 1,2 252 51 4371,4286 ) x 10 -6
= ( 3326,4 x 61 ) x 10 -6
= 0,20169989 mm = 0,02017 cm ≤ 0,04 cm
c Kontrol Geser
Vu = 1/2 Qu l
= 1/2 6348,40 6 = 190452,00 N
Gaya yang disumbangkan oleh beton
Vc = ( √ fc' / 6 ) x b d
= (√ 30 / 6 ) x 300 441
= 2,236068 x 132300 = 295831,7934 N
Kondisi perencanaan memerlukan tulangan geser minimum karena :
1/2 Vc ≤ Vu ≤ Vc
147915,9 ≤ 190452,00 ≤ 295831,7934 N
Penulangan geser dalam daerah sepanjang jarak tumpuan
Vc yang digunakan = 147915,90 N
Vu
Vs = - Vc
Ø
190452,00
= - 147915,90 = 169504,10 N
0,6
d 441
S = → = = 110,25 mm
4 4
Dipakai jarak (S max ) 100 mm
Av = bw x S
3 x fy
= 300 x 100 = 23,81 mm 2
3 x 420
2
Dipakai sengkang Ø 8 - 100 → As = 50,286 mm
Penulangan geser dalam daerah sepanjang jarak lapangan
d 441
S = → = = 220,5 mm
2 2
Dipakai jarak (S max ) 200 mm
Dipakai sengkang Ø 8 - 200
VII. KONTROL BALOK A-B
a Perhitungan Lendutan
M L2
Δ = βa
E Ic
2
Beban Mati Q dl : 3098,00 kg/m
Md = 1/8 q l 2
= 1/8 3098 6 2 = 13941,00 kg/m2
Beban Hidup Q ll : 250 kg/m2
Ml = 1/4 P l
2
= 1/4 250 6 = 375,00 kg/m
M = Md + Ml
2
= 13941,00 + 375,00 = 14316,00 kg/m

E = 4700 fc'
2
= 4700 35 = 27805,57 Mpa = 27805574980,568 N/m
Ic = 1/12 b h 3
= 1/12 300 400 3
= 1600000000,0 mm 4 = 0,001600000 m4
2
M L
Δ = βa
E Ic
= 5 x 14316,00 x 6,00 2
48 27805574980,568 x 0,0016000
= 0,1042 x 515376,00 = 0,0012067 m = 0,1207 cm
44488919,97
- L = 600
= = 3,33333 cm
∆ 180 180
-
Δ ≤ = 0,1207 ≤ 3,333 cm

b Perhitungan Lebar Retak
3
w = ( 11 β ƒs dc A ) x 10 -6
β = SKSNI menetapkan nilai = 1,2
ƒs = 0,6 fy
= 0,6 420 = 252 Mpa
dc = Jarak titik berat tulangan utama sampai keserat tarik terluar
= Selimut + Ø tl.utama / 2
= 40 + 22 / 2 = 51 mm
A = Penampang potongan tarik efektif
2 dc b
=
n
2 51 300
= = 4371,43 mm 2
7
w = Lebar retak dalam mm x 10 -6
3
w = ( 11 β ƒs dc A ) x 10 -6
3
= ( 11 1,2 252 51 4371,4286 ) x 10 -6
= ( 3326,4 x 61 ) x 10 -6
= 0,20169989 mm = 0,02017 cm ≤ 0,04 cm
c Kontrol Geser
Vu = 1/2 Qu l
= 1/2 4117,60 6 = 123528,00 N
Gaya yang disumbangkan oleh beton
Vc = ( √ fc' / 6 ) x b d
= (√ 30 / 6 ) x 300 341
= 2,236068 x 102300 = 228749,7541 N
Kondisi perencanaan memerlukan tulangan geser minimum karena :
1/2 Vc ≤ Vu ≤ Vc
114374,88 ≤ 123528,00 ≤ 228749,7541 N
Penulangan geser dalam daerah sepanjang jarak tumpuan
Vc yang digunakan = 114374,88 N
Vu
Vs = - Vc
Ø
123528,00
= - 114374,88 = 91505,12 N
0,6
d 341
S = → = = 85,25 mm
4 4
Dipakai jarak (S max ) 75 mm
Av = bw x S
3 x fy
2
= 300 x 75 = 17,86 mm
3 x 420
2
Dipakai sengkang Ø 8 - 100 → As = 50,286 mm
Penulangan geser dalam daerah sepanjang jarak lapangan
d 341
S = → = = 170,5 mm
2 2
Dipakai jarak (S max ) 150 mm
Dipakai sengkang Ø 8 - 200
VII. KONTROL BALOK A-I
a Perhitungan Lendutan
M L2
Δ = βa
E Ic
2
Beban Mati Q dl : 2934,00 kg/m
Md = 1/8 q l 2
= 1/8 2934 5 2 = 9168,75 kg/m2
Beban Hidup Q ll : 250 kg/m2
Ml = 1/4 P l
2
= 1/4 250 5 = 312,50 kg/m
M = Md + Ml
2
= 9168,75 + 312,50 = 9481,25 kg/m

E = 4700 fc'
2
= 4700 35 = 27805,57 Mpa = 27805574980,568 N/m
Ic = 1/12 b h 3
= 1/12 300 500 3
= 3125000000,0 mm 4 = 0,003125000 m
4

2
M L
Δ = βa
E Ic
= 5 x 9481,25 x 5,00 2
48 27805574980,568 x 0,0031250
= 0,1042 x 237031,25 = 0,00028415 m = 0,0284 cm
86892421,81
- L = 500
= = 2,77778 cm
∆ 180 180
-
Δ ≤ = 0,0284 ≤ 2,778 cm

b Perhitungan Lebar Retak
3
w = ( 11 β ƒs dc A ) x 10 -6
β = SKSNI menetapkan nilai = 1,2
ƒs = 0,6 fy
= 0,6 420 = 252 Mpa
dc = Jarak titik berat tulangan utama sampai keserat tarik terluar
= Selimut + Ø tl.utama / 2
= 40 + 19 / 2 = 49,5 mm
A = Penampang potongan tarik efektif
2 dc b
=
n
2 49,5 300
= = 4242,86 mm 2
7
w = Lebar retak dalam mm x 10 -6
3
w = ( 11 β ƒs dc A ) x 10 -6
3
= ( 11 1,2 252 50 4242,8571 ) x 10 -6
= ( 3326,4 x 59 ) x 10 -6
= 0,19772534 mm = 0,01977 cm ≤ 0,04 cm
c Kontrol Geser
Vu = 1/2 Qu l
= 1/2 3920,80 5 = 98020,00 N
Gaya yang disumbangkan oleh beton
Vc = ( √ fc' / 6 ) x b d
= (√ 30 / 6 ) x 300 442,5
= 2,236068 x 132750 = 296838,024 N
Kondisi perencanaan memerlukan tulangan geser minimum karena :
1/2 Vc ≤ Vu ≤ Vc
148419,01 ≤ 98020,00 ≤ 296838,024 N
Penulangan geser dalam daerah sepanjang jarak tumpuan
Vc yang digunakan = 148419,01 N
Vu
Vs = - Vc
Ø
98020,00
= - 148419,01 = 14947,65 N
0,6
d 442,5
S = → = = 110,625 mm
4 4
Dipakai jarak (S max ) 100 mm
Av = bw x S
3 x fy
2
= 300 x 100 = 23,81 mm
3 x 420
2
Dipakai sengkang Ø 8 - 100 → As = 50,286 mm
Penulangan geser dalam daerah sepanjang jarak lapangan
d 442,5
S = → = = 221,25 mm
2 2
Dipakai jarak (S max ) 200 mm
Dipakai sengkang Ø 8 - 200
VII. KONTROL BALOK B - J
a Perhitungan Lendutan
M L2
Δ = βa
E Ic
2
Beban Mati Q dl : 4484,00 kg/m
Md = 1/8 q l 2
= 1/8 4484 5 2 = 14012,50 kg/m2
Beban Hidup Q ll : 250 kg/m2
Ml = 1/4 P l
2
= 1/4 250 5 = 312,50 kg/m
M = Md + Ml
2
= 14012,50 + 312,50 = 14325,00 kg/m

E = 4700 fc'
2
= 4700 35 = 27805,57 Mpa = 27805574980,568 N/m
Ic = 1/12 b h 3
= 1/12 300 500 3
= 3125000000,0 mm 4 = 0,003125000 m
4

2
M L
Δ = βa
E Ic
= 5 x 14325,00 x 5,00 2
48 27805574980,568 x 0,0031250
= 0,1042 x 358125,00 = 0,00042932 m = 0,0429 cm
86892421,81
- L = 500
= = 2,77778 cm
∆ 180 180
-
Δ ≤ = 0,0429 ≤ 2,778 cm

b Perhitungan Lebar Retak
3
w = ( 11 β ƒs dc A ) x 10 -6
β = SKSNI menetapkan nilai = 1,2
ƒs = 0,6 fy
= 0,6 420 = 252 Mpa
dc = Jarak titik berat tulangan utama sampai keserat tarik terluar
= Selimut + Ø tl.utama / 2
= 40 + 19 / 2 = 49,5 mm
A = Penampang potongan tarik efektif
2 dc b
=
n
2 49,5 300
= = 4242,86 mm 2
7
w = Lebar retak dalam mm x 10 -6
3
w = ( 11 β ƒs dc A ) x 10 -6
3
= ( 11 1,2 252 50 4242,8571 ) x 10 -6
= ( 3326,4 x 59 ) x 10 -6
= 0,19772534 mm = 0,01977 cm ≤ 0,04 cm
c Kontrol Geser
Vu = 1/2 Qu l
= 1/2 5780,80 5 = 144520,00 N
Gaya yang disumbangkan oleh beton
Vc = ( √ fc' / 6 ) x b d
= (√ 30 / 6 ) x 300 442,5
= 2,236068 x 132750 = 296838,024 N
Kondisi perencanaan memerlukan tulangan geser minimum karena :
1/2 Vc ≤ Vu ≤ Vc
148419,01 ≤ 144520,00 ≤ 296838,024 N
Penulangan geser dalam daerah sepanjang jarak tumpuan
Vc yang digunakan = 148419,01 N
Vu
Vs = - Vc
Ø
144520,00
= - 148419,01 = 92447,65 N
0,6
d 442,5
S = → = = 110,625 mm
4 4
Dipakai jarak (S max ) 100 mm
Av = bw x S
3 x fy
2
= 300 x 100 = 23,81 mm
3 x 420
2
Dipakai sengkang Ø 8 - 100 → As = 50,286 mm
Penulangan geser dalam daerah sepanjang jarak lapangan
d 442,5
S = → = = 221,25 mm
2 2
Dipakai jarak (S max ) 200 mm
Dipakai sengkang Ø 8 - 200
VII. KONTROL BALOK A'-B'
a Perhitungan Lendutan
M L2
Δ = βa
E Ic
2
Beban Mati Q dl : 938,00 kg/m
Md = 1/8 q l 2
= 1/8 938 6 2 = 4221,00 kg/m2
Beban Hidup Q ll : 100 kg/m2
Ml = 1/4 P l
2
= 1/4 100 6 = 150,00 kg/m
M = Md + Ml
2
= 4221,00 + 150,00 = 4371,00 kg/m

E = 4700 fc'
2
= 4700 35 = 27805,57 Mpa = 27805574980,568 N/m
Ic = 1/12 b h 3
= 1/12 250 400 3
= 1333333333,3 mm 4 = 0,001333333 m
4

2
M L
Δ = βa
E Ic
= 5 x 4371,00 x 6,00 2
48 27805574980,568 x 0,0013333
= 0,1042 x 157356,00 = 0,00044212 m = 0,0442 cm
37074099,97
- L = 600
= = 3,33333 cm
∆ 180 180
-
Δ ≤ = 0,0442 ≤ 3,333 cm

b Perhitungan Lebar Retak
3
w = ( 11 β ƒs dc A ) x 10 -6
β = SKSNI menetapkan nilai = 1,2
ƒs = 0,6 fy
= 0,6 420 = 252 Mpa
dc = Jarak titik berat tulangan utama sampai keserat tarik terluar
= Selimut + Ø tl.utama / 2
= 40 + 19 / 2 = 49,5 mm
A = Penampang potongan tarik efektif
2 dc b
=
n
2 49,5 250
= = 3535,71 mm 2
7
w = Lebar retak dalam mm x 10 -6
3
w = ( 11 β ƒs dc A ) x 10 -6
3
= ( 11 1,2 252 50 3535,7143 ) x 10 -6
= ( 3326,4 x 56 ) x 10 -6
= 0,18606667 mm = 0,01861 cm ≤ 0,04 cm
c Kontrol Geser
Vu = 1/2 Qu l
= 1/2 1285,60 5 = 32140,00 N
Gaya yang disumbangkan oleh beton
Vc = ( √ fc' / 6 ) x b d
= (√ 30 / 6 ) x 250 342,5
= 2,236068 x 85625 = 191463,3206 N
Kondisi perencanaan memerlukan tulangan geser minimum karena :
1/2 Vc ≤ Vu ≤ Vc
95731,66 ≤ 32140,00 ≤ 191463,3206 N
Penulangan geser dalam daerah sepanjang jarak tumpuan
Vc yang digunakan = 95731,66 N
Vu
Vs = - Vc
Ø
32140,00
= - 95731,66 = -42164,99 N
0,6
d 342,5
S = → = = 85,625 mm
4 4
Dipakai jarak (S max ) 75 mm
Av = bw x S
3 x fy
2
= 250 x 75 = 14,88 mm
3 x 420
2
Dipakai sengkang Ø 8 - 100 → As = 50,286 mm
Penulangan geser dalam daerah sepanjang jarak lapangan
d 342,5
S = → = = 171,25 mm
2 2
Dipakai jarak (S max ) 150 mm
Dipakai sengkang Ø 8 - 150
VII. KONTROL BALOK A'-I'
a Perhitungan Lendutan
M L2
Δ = βa
E Ic
2
Beban Mati Q dl : 865,33 kg/m
Md = 1/8 q l 2
= 1/8 865 5 2 = 2704,17 kg/m2
Beban Hidup Q ll : 100 kg/m2
Ml = 1/4 P l
2
= 1/4 100 5 = 125,00 kg/m
M = Md + Ml
2
= 2704,17 + 125,00 = 2829,17 kg/m

E = 4700 fc'
2
= 4700 35 = 27805,57 Mpa = 27805574980,568 N/m
Ic = 1/12 b h 3
= 1/12 250 450 3
= 1898437500,0 mm 4 = 0,001898438 m
4

2
M L
Δ = βa
E Ic
= 5 x 2829,17 x 5,00 2
48 27805574980,568 x 0,0018984
= 0,1042 x 70729,17 = 0,00013957 m = 0,0140 cm
52787146,25
- L = 500
= = 2,77778 cm
∆ 180 180
-
Δ ≤ = 0,0140 ≤ 2,778 cm

b Perhitungan Lebar Retak
3
w = ( 11 β ƒs dc A ) x 10 -6
β = SKSNI menetapkan nilai = 1,2
ƒs = 0,6 fy
= 0,6 420 = 252 Mpa
dc = Jarak titik berat tulangan utama sampai keserat tarik terluar
= Selimut + Ø tl.utama / 2
= 40 + 19 / 2 = 49,5 mm
A = Penampang potongan tarik efektif
2 dc b
=
n
2 49,5 250
= = 3535,71 mm 2
7
w = Lebar retak dalam mm x 10 -6
3
w = ( 11 β ƒs dc A ) x 10 -6
3
= ( 11 1,2 252 50 3535,7143 ) x 10 -6
= ( 3326,4 x 56 ) x 10 -6
= 0,18606667 mm = 0,01861 cm ≤ 0,04 cm
c Kontrol Geser
Vu = 1/2 Qu l
= 1/2 1198,40 5 = 29960,00 N
Gaya yang disumbangkan oleh beton
Vc = ( √ fc' / 6 ) x b d
= (√ 30 / 6 ) x 250 392,5
= 2,236068 x 98125 = 219414,1703 N
Kondisi perencanaan memerlukan tulangan geser minimum karena :
1/2 Vc ≤ Vu ≤ Vc
109707,09 ≤ 29960,00 ≤ 219414,1703 N
Penulangan geser dalam daerah sepanjang jarak tumpuan
Vc yang digunakan = 109707,09 N
Vu
Vs = - Vc
Ø
29960,00
= - 109707,09 = -59773,75 N
0,6
d 392,5
S = → = = 98,125 mm
4 4
Dipakai jarak (S max ) 76 mm
Av = bw x S
3 x fy
2
= 250 x 76 = 15,08 mm
3 x 420
2
Dipakai sengkang Ø 8 - 75 → As = 67,048 mm
Penulangan geser dalam daerah sepanjang jarak lapangan
d 392,5
S = → = = 196,25 mm
2 2
Dipakai jarak (S max ) 150 mm
Dipakai sengkang Ø 8 - 150

You might also like