1 submitals stage :
1- Project's Contract & BOQ, 2- Compliance to Project's Contract, Once, prior to Commencement of
1.1 Approval of shop drawing Approved submittal Activity and for Each Subsequent
N/A C H N/A
Project's Specifications for water Specifications, Design Drawings, and
proofing 07130, 3- Relevant Codes and Modification for Drawings or any
1.2 Approval of M.O.S Relevant Codes & Standards Approved submittal N/A C H N/A
Standards, 4- Manufacturer Change of Varios Materials
Manufacturers / Suppliers
Approval of material (cementitious Recommendation 5-RFP no1rev01
1.3 Approved submittal N/A C H N/A
material)
2 Materials Receiving Stage :
1- Project's Contract & BOQ, 2- 1- Compliance to Approved Samples and
Project's Specifications for water source, 2- Various Materials to be received on
Inspection of Delivered approved proofing 07130, 3- Relevant Codes and it’s original Packaging and Pallets must be
2.1
Tagged, 3- All Supporting Documents (data Approved M.I.R Prior to start work R I H N/A
material. Standards, 4- Manufacturer
sheet, origin certificate, Quality Certificates,
Recommendation 5-RFP no1rev01
test results) ( If Applicable ) & Delivery Notes
3 Inspections Stage :
3.1 Training The Staff conforms to specification & ATC policy Photos & Attendance on going N/A C N/A N/A
Conforms to specification -method
3.1 Surface Preparation statement - Manufacturer Inspection request on going R I H N/A
Recommendation
1- Project's Contract & BOQ, 2-
Project's Specifications for water Conforms to specification -method
3.2 apply 1st coat cementitious insulation proofing 07130, 3- Relevant Codes statement - Manufacturer Inspection request on going R I H N/A
and Standards, 4- Manufacturer Recommendation
Recommendation
Conforms to specification -method
3.3 apply 2nd coat cementitious insulation statement - Manufacturer Inspection request on going R I H N/A
Recommendation