You are on page 1of 9

International Journal of Project Management 18 (2000) 51±59

www.elsevier.com/locate/ijproman

Construction delay: a quantitative analysis


Ayman H. Al-Momani
Mu'tah University, Civil Engineering Department, Karak, Mu'tah, P.O. Box 7, Jordan

Abstract

Avoiding construction claims and disputes requires an understanding of the contractual terms and causes of claims. The dual
underlying theme of this paper is to investigate the causes of delays on 130 public projects in Jordan and to aid construction
managers in establishing adequate evaluation prior to the contract award using quantitative data. Projects investigated in this
study included residential, oce and administration buildings, school buildings, medical centers and communication facilities.
Results of this study indicates the main causes of delay in construction of public projects relate to designers, user changes,
weather, site conditions, late deliveries, economic conditions and increase in quantity. The presence of these factors have an
impact on the successful completion of the projects at the time contractually speci®ed. The ®ndings suggest that special attention
to factors identi®ed in this study will help industry practitioners in minimising the risk of contract disputes. # 1999 Elsevier
Science Ltd and IPMA. All rights reserved.

Keywords: Construction management; Project planning; Construction delay; Dispute

1. Introduction 1.1. Previous work

A vital section speci®ed in the construction contract A great deal of information concerned with project
is the performance period or time of project execution, delay and overruns may be found in the literature. The
which is established prior to bidding. The successful increased interest in construction overruns is due, in
execution of construction projects and keeping them part, to e€orts by the government to reduce construc-
within estimated cost and the prescribed schedules tion delays. There has been a considerable and contin-
depend on a methodology that requires sound engin- ued interest in the e€ect of construction delays. The
eering judgment.[1] The construction sector is one of information available is diverse and widespread. Many
the vital sectors in the development process of Jordan. construction management books[2±6] have minimum
coverage on construction delays. Al-Momani[7]
The government contributes to the development of the
describe the various elements of cost upon individual
construction industry in several ways. However, there
public projects but does not deal speci®cally with con-
are limitations and even draw backs to these e€orts.
struction delays.
The time required to complete construction of public
Assaf and Al-khalil[8] outline the main causes of
projects is frequently greater than the time speci®ed in delay in large building projects and their relative im-
the contract. These `overruns' or time extensions are portance. They found that 56 causes of delay exist in
granted for many reasons, such as designer changes or Saudi construction projects. According to the contrac-
errors, user changes, weather and late deliveries. tors surveyed the most important delay factors were
Current construction projects are complex e€orts preparation and approval of shop drawings, delays in
requiring the support of the design and construction contractor's progress, payment by owners and design
profession. Therefore, a realistic time for project ex- changes. The architects and engineers view were cash
ecution will decrease the possibility of disputes problems during construction, the relationship between
between state agency and the contractors. subcontractors and the slow decision making process

0263-7863/99/$20.00 # 1999 Elsevier Science Ltd and IPMA. All rights reserved.
PII: S 0 2 6 3 - 7 8 6 3 ( 9 8 ) 0 0 0 6 0 - X
52 A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59

Table 1
Summary of project information

Classi®cation Poor Change Weather Site Late Economic Increase in No Total


design orders condition delivery condition quantity delay

House 4 1 3 1 0 0 2 3 14
Oce 8 5 4 2 1 4 5 5 34
School 10 8 6 5 4 2 3 14 52
Medical centers 6 4 2 0 3 2 1 2 20
Communication facilities 4 2 1 0 2 0 1 0 10
Total 32 20 16 8 10 8 12 24 130

of the owner. The owners agree that the design errors, public projects constructed in di€erent regions of
labor shortages and inadequate labor skills are import- Jordan during the period of 1990±97. The data was
ant delay factors. Hancher and Rowings,[1] for example, found in contract ®les of several state agencies. Data
provide a concise summary of the methodologies used collected were of 5 kinds of public projects: residential
by transportation agencies to establish the contract dur- houses of public ®gures, oce and administrative
ation used for highway construction projects, and also buildings, school buildings, medical centers and com-
provides a schedule guide for ®eld engineers during con- munication facilities. The performance and construc-
struction. Similarly, Chalabi and Camp[10] conducted a tion of these projects were recognised as being
review on project delays in developing countries during unsatisfactory to many ocials, and assented to the
planning and construction stages. In their study they study in order to have hard evidence as to the nature
found that the delay and cost overruns of construction of the problems. This study will summarise the results
projects are dependent entirely on the very early stages of this research based on actual construction times ex-
of the project. Fereig and Qaddumi[11] in their study on perienced by public projects. The data collection was
the construction experience of the Arabian Gulf demon- to investigate the reasons related to construction delay
strate the various components of the planning, control- and overruns:
ling and productivity on construction delay. Their
. Planned duration of contract;
primary purpose is to alert the reader to the deviation
. Actual completion date;
from the project plans.
Wilson[9] examined the role of the owner and archi- Table 2
tect/engineer's roles in the prevention and resolution of Descriptive statistics of the public projects
construction claims. Wilson also summarised the
causes of construction claims which include: extra Number of Duration
work, project delays and acceleration, lack of manage-
Project categories projects
ment, limited site access and change in work schedule. Planned Actual
Despite the necessity for such research, little work
has been described in the literature concerning public
projects, specially in Jordan. The previously proposed max. 450 832
factors contributing to construction delay were fre-
min. 75 66
quently observed in public projects. The actual fre- House 14 mean 221.4 297.2
quency and magnitude of these factors is not known, SD 102.3 192.9
which has proven to be a serious and very expensive Oce and administrative buildings 34 max. 750 751
problem to Jordan's construction industry. min. 100 67
mean 354.6 442.2
SD 120.0 152.9
1.2. Research design and objectives School buildings 52 max. 660 928
min. 150 225
mean 395.4 467.5
The objective of this study is to determine the causes
SD 129.7 141.1
and the level of time extension of public projects and Medical centers 20 max. 720 904
to aid construction managers in establishing adequate min. 90 193
evaluation prior to the contract award using quantitat- mean 313.5 444.5
ive data. The key task is to design research so that the SD 162.6 231.7
Communication facilities 12 max. 360 410
information obtained permits the assessment of their
min. 195 230
impact. Therefore, the best approach to assessing these mean 268.2 308.2
potentials is to adopt randomly selected samples. The SD 58.0 59.9
sampling population was established by selecting 130
A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59 53

Fig. 1. Causes of delay.


54 A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59

Fig. 2. Scatter plot of actual time Y versus planned time X for general model of public projects.

. Design changes; poor design, change orders, weather, site conditions,


. Disputes; late delivery, economic conditions and increase in
. Noti®cation of extra work; quantity. A breakdown of the projects by these par-
. Date of notice to proceed; ameters is graphically illustrated in Fig. 1. The overall
. Delay encountered during construction; delays were in 106 out of 130 (81.5%) projects. The
. Con¯ict of the drawings and speci®cations; main causes for delays were poor design in 32 projects
. Time extensions; (24.6%), while the second cause was the change orders
. Late delivery of materials and equipment. in 20 projects (15.4%). The site conditions and the
economic conditions were the least cause of delay and
were found in 8 projects.

2. Discussions 2.1. Planned and actual duration

The data were entered into Excel 5 where all analy- The mean actual duration for all public projects was
sis and diagrams were developed. The ®rst step was to 426.6 days, and a standard deviation of 137 days.
explore the parameters as to causes of delay. To this While the planned duration for the same projects was
e€ect, parameters were de®ned and constructed in 343.1 days in mean, with a standard deviation of 137.4
Table 1 for public projects. These restrictions create a days. The mean, maximum, minimum and standard
sample with 130 projects. The table provide frequen- deviation for the planned and actual time were com-
cies for each parameter in ®ve di€erent construction puted as shown in Table 2 for ®ve project classi®-
categories. Many projects were delayed for many cations. It can be noticed that the actual time for each
reasons. All extensions to the planned schedule were type of project vary considerably. This is illustrated by
considered as delays. The major causes identi®ed were: large di€erences between the means of the planned and
A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59 55

Fig. 3. Scatter plot of actual time versus planned time of the housing model.

actual times and the high values of standard deviation. 3. Tests and results
For instance, the mean planned time for school build-
ings varied from 395.4 days to an actual of 467.5 days, Simple linear regression develops an equation that
while the oce and adminstrative buildings varied describes the relationship between two variables. In
from 354.6 planned days to 442.2 actual days. The im- this case the equation takes the form of:
plication is therefore, that on average during the
Y ˆ b0 ‡ b1 X ‡ e
sample period, the planned and actual duration was
upward sloping. Standard deviation are reported In this model Y is the dependent variable, the par-
which suggest that the variance of the actual time is ameters, b0 and b1 are the coecients which are
considerably greater than that of the planned time, unknown and are to be estimated. X is the indepen-
with the variance of the actual time being approxi- dent variable, and e is a random error which is the
mately 29 444.67 days and the variance of the planned amount of variation in Y not accounted for by the lin-
time being approximately 18 894 days. ear relationship. The theoretical models are derived
A mathematical structure was studied by di€erent and explained in the following.
functions that ®ts the data, which indicated that the For a comparison of the actual and planned time
simple linear regression appears to be appropriate distribution, the equation developed for overall public
for this type of problem. The speci®cation of our projects is:
model is determined by one independent variable
Y ˆ 82:87 ‡ 1:0016x
which signi®cantly explained variations in the re-
sponse variable. Correlation coecients were used
for screening the variables. Several statistical tests R2 ˆ 0:64
were conducted. Each of these was performed at
99% con®dence level. It was assumed that both the D:W: ˆ 1:58 R ˆ 0:80 S:E: ˆ 102:8 F ÿ value …1†
actual and planned times distributions were normal
and independently distributed. ˆ 231:25
56 A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59

Fig. 4. Scatter plot of actual time versus planned time of the oce building model.

The correlation coecient for this relationship is tion managers and practitioners rather than selection
0.80 indicating that the distribution of planned time of the general model. The ®tted equations are as fol-
mirrors the actual time with a high degree of accuracy. lows:
The calculated F is 231.25, the higher absolute value
of the F-statistics reported may re¯ect the observation 3.1. Housing project
that are powerful predictors of the measured data.
Therefore, true linearity exists in the developed model. Y ˆ 59:05 ‡ 1:6X
Comparing sample means to test the agreement
between the two distribution was employed. In this R ˆ 0:853 R2 ˆ 073 S:E: ˆ 104:62 F ÿ value
case the t-statistic is 9.28 which is much larger than t-
value of 1.97, giving further proof of the agreement ˆ 32:19 …2†
between the two distributions. The general model is
valuable in that it provides a universal model of
phenomena and would primarily be of interest to con- 3.2. Oce and administration building
struction ocials. The predictive equation has been
developed as an aggregate model for actual construc- Y ˆ 95:4 ‡ 0:97X
tion time of a public projects.
In this setting, more speci®c models such as Eqs. R ˆ 0:76 R2 ˆ 0:59 S:E: ˆ 99:49 F ÿ value ˆ 45:94 …3†
(2)±(6) were developed, which exhibited a reasonable
®t to the data. Figures 2±7 give a graphical view of
how well the charts relate the actual time by project 3.3. School projects
type to the planned time. Speci®c models are prefer-
able and would be of particular interest to construc- Y ˆ 162:05 ‡ 0:77X
A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59 57

Fig. 5. Scatter plot of actual time versus planned time of the school buildings model.

R ˆ 0:71 R2 ˆ 0:51 S:E: ˆ 99:36 F ÿ value ˆ 51:97 …4† ofthe estimated equations are reasonable, given that
the R 2 for Eq. (1) through Eq. (6) are of a acceptable
3.4. Medical centers value and the corresponding F-ratios indicate very
good model identi®cations and satisfy the diagnostic
criteria. These equations can be used by engineers,
Y ˆ 46:9 ‡ 1:3X
planners and construction managers working in gov-
ernmental agencies to estimate the actual time for con-
R ˆ 0:89 R2 ˆ 0:79 S:E: ˆ 108:4 F ÿ value ˆ 68:71 …5† struction before awarding contract.

3.5. Communication facilities 4. Limitation and suggestion for further research

Y ˆ 85 ‡ 0:84X While this study is among the ®rst to provide a full


test of cause and determinants of construction delay, it
R ˆ 0:86 R2 ˆ 074 S:E: ˆ 29:27 F ÿ value ˆ 22:73 …6† is not without limitations. Several shortcomings in the
data can be identi®ed such as the actual cost of con-
The regression coecients are all signi®cantly di€er- struction and construction experience of the contrac-
ent from zero and the expected sign and relationship tors. The inclusion of the construction experience of
between the variables is linear. Each of the tests con- the contractors as a predictor within the model under-
ducted proved that, the developed equations are stat- lines the importance of this extension of the analysis
istically signi®cant at the 99% level as indicated by the into the internal information of the ®rms. But this fac-
t-values and appear to explain a high per cent of the tor can be introduced only when the focus of study is
variability and able to predict changes in the actual moved from the construction industry to the construc-
time. Other relevant regression statistics are shown tion ®rms. Such change of focus is not without dicul-
below the estimates. Overall, the explanatory power ties. The collection of the company speci®c data is
58 A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59

Fig. 6. Scatter plot of actual time versus planned time of the medical centers model.

costly compared with that of publicly available data. well understood in the case of public building projects.
However, the quality of future studies concerning com- A survey of 130 projects indicated that poor design
pany speci®c data and managerial perceptions are lar- and negligence of the owner, change orders, weather
gely dependent on the nature of the data that is condition, site condition, late delivery, economic con-
available for analysis. The future emphasis should be ditions, and increase in quantities are the main causes
placed on the collection of the appropriate information of delay. In line with the reviewed research, the present
and this will be the subject of an additional paper. investigation provides con®rmation of the e€ect of
Projectsinvestigated in this study exhibit a delay. In de®ned parameters on construction delays.
practice, this phenomena is expected to continue unless Practically oriented research is vital for proper man-
management actions are taken to control these causes agement of construction projects. Reliable prediction
within the planned element of the design and construc- of construction duration, and then controlling cost
tion works. Thus good practice in planning, coordi- within budget is widely used in decision making and is
nation, and the change of the control procedures of an essential part of successful management. To test
the public institutions needs to be recognised and the this hypothesis, a simple linear model was used to esti-
implications understood. The model still appears ten- mate the relationship between the actual and planned
able, then it may be applied broadly for guidance and time. The major implication of the foregoing have im-
for planning further work and will prove bene®cial in portant rami®cations for understanding the actual time
future projects. of public projects. This has been repeatedly stated to
the outstanding need of construction in Jordan. The
relations obtained have the advantage of relying upon
5. Conclusion the statistical treatment of real data and could without
doubt be improved by considering a larger sample of
Construction delay and overrun is a critical function projects. The researcher believes that the arguments
in construction of public projects. It has been of great and ®ndings presented in this study provide a good
interest to construction researchers but has not been guidance for managerial intervention, and provide
A.H. Al-Momani / International Journal of Project Management 18 (2000) 51±59 59

Fig. 7. Scatter plot of actual time versus planned time of the communication facilities model.

some guidelines and actionable information that man- struction projects in developing countries. CIB Proc, W-65
agers can utilize to manage their projects. 1984;2:273±734.
[11] Fereig S, Qaddumi N. Construction problemsÐArabian Gulf
experience. CIB Proc, W-65 1984;2:753±6.

References
Dr. Ayman H. Al-Momani is an associ-
[1] Hancher DE, Rowings JE. Setting highway construction con- ate professor of civil engineering at
tract duration. Journal of the Construction Division, ASCE Mu'tah University, Jordan. He is also
1981;107(2):169±79. vice dean of engineering and head of
[2] Barrie DS, Paulson BC. Professional Construction chemical engineering department. He
Management. Berkshire, England: McGraw-Hill, 1992. served as a chairman and head of the
[3] Halpin DW, Woodhead RW. Construction Management. New civil engineering department for many
York: John Wiley, 1980. years, and he is in charge of the con-
[4] Harries F, McCa€er R. Modern Construction Management. struction engineering and management
London, England: Blackwell Science, 1995. program, where he contributed to and
[5] Oxley R, Poskit J. Management Techniques Applied to developed postgraduate and under-
Construction Industry. London: Blackwell Science, 1996. graduate courses in construction man-
[6] Filcher R. Principles of Construction Management. Berkshire, agement. He has written widely in the
England: McGraw-Hill, 1992. ®eld and taught courses at Mu'tah
[7] Al-Momani A. Construction cost prediction for public school University, University of Jordan, and University of Applied sciences in
building in Jordan. Construction Management and Economics construction planning and scheduling, construction cost estimating,
1996;14:311±7. construction management, construction methods and equipment,
[8] Assaf SA, Alkhalil M, Al-Hazmi M. Causes of delay in large quality control in construction, engineering economy and operation
building construction projects. Journal of Management in research. He received a BS in civil engineering from Leningrad
Engineering, ASCE 1995;11(2):45±50. university, MS in construction management from Oklahoma Uni-
[9] Wilson RL. Prevention and resolution of construction claims. versity, MS in industrial engineering from Central State University,
Journal of Construction Division 1982;108(CO3):390±405. and a Ph.D. from Oklahoma State University, USA. He is a member
[10] Chalabi FA, Camp D. Causes of delay and overruns of con- of national and international associations.

You might also like