Professional Documents
Culture Documents
837-841, 1996
Copyright © 1996 Published by Elsevier Science Ltd
Printed in Great Britain. All rights reserved
0141-0296(95)00162-X 0141-0296/96 $15.00 + 0.00
ELSEVIER
Introduction Design
837
838 Concrete floating berth: P. Starr and D. A. Wainwright
FACILITY
NORTH
ENCLOSURE BUILDING
/ 'i _ALTERNATIVECAISSON
200m ,, / G A T E MOORING
OUTER BERTH
.UNDERWATER BRACE
-?$.0
, r - - r6'~.-~,~ . . . . . . . . . . . . . -~T -CAISSON
GATE
I | i,':ll'_':i J l N CLOSED POSITION
BOm ,' // P;]!i
i ~-L.'.~: - so. o
", 30mJ COVERED BERTH ~,~:~!
-SO0
I I~-CAISSON GATE MOORED
,~,~1 I IN OPEN POSITION
_.1.
-25.0
60t
ti ~oo .~// ~,,~o_ .~// L=lil
I ,o~ .I
,~.Y su,','oR, .RE.
Figure I Plan
61 .Sm
OOCKINO TROLLEY
RAILS--..__
NOORIN0 80014
LEVEL
":l- ! = ~ ~ ~ 1
¢N
,..
1-
DRAUOHT
e4
PONTOON PONTOON
'-
25m I 30m I -
25m
Figure 2 Cross-section
Concrete floating berth: P. Starr and D. A. Wainwright 839
LEVEL& BILGE
T
•
.,=
BALLAST TA
-I
|
IOm
25m
• • e • •
ill
• •
BALLAST TANK
• • •
7.5 m
' li
• • •
J_
1
Figure3 Cross-section ot: outer pontoon
16.0 m(~
t,t
'S 3m _:_ 5',~m _ ; _ 7-Sm
T -I m
LEVEL I MAIN
r- • • • • If DECK
i
!
i
o
f,.j ILEVEL2 PASSAGE
SERVICE
BEAM
LEVEL 3 MACHINE
t OECK
LEVEL/, BILGE
f
and mooring booms were bolted to the concrete hull by ditions were modelled using springs and restrained free-
post-tensioned Macalloy bars. doms to represent mooring boom articulation and vertical
springs to represent buoyancy stiffness. Static loadings
Analysis were applied to represent wave, wind, dead, ballast and pre-
The finite element membrane method was chosen to ana- stress forces. Different combinations of live load were used
lyze the global loading because of its flexibility in allowing to represent maximum hogging, sagging, torsion and rack-
a detailed model of the link end to be used with a relatively ing at key sections. Following the initial finite element
coarse model of the straight pontoon sections. Support con- membrane analysis, adjustments were made to the post-ten-
840 Concrete floating berth: P. Starr and D. A. Wainwright
sioning to achieve the most economic and effective use of top of the duct. The grout used in the trial and throughout
the prestress. construction was an ordinary portland cement grout with
The transverse loading of individual panels and loaded 0.36 W/C ratio and Cormix SP4 superplasticiser 1% by
areas of the structure arising from water and plant loads weight of cement.
were analysed by local framework analysis and the results
combined with the direct and shear stresses obtained from
the global analysis to check concrete stresses and reinforce Construction
the members. Special attention was paid to areas of high
external load such as column bases, mooring boom connec- General
tions and bridge supports. The chosen thickness of the con- Construction of the jetty started in 1989 in a dry dock in
crete sections was confirmed and no shear reinforcement the Firth of Clyde. It was fully pre-tensioned and brought as
was required except as conventional stirrups in the deck near final completion as possible including superstructure,
beams and column bases. cladding and crane erection all in the dry dock. The dock
A major aim was durability of the concrete structure was then flooded, the facility moored and the dock entrance
requiring minimum maintenance and to achieve water- dredged out. The dock was deep enough to keep the jetty
tightness. The specification was designed to produce high floating at all states of the tide. With a suitable calm
density concrete with a minimum 28 day cube strength of weather window forecast and the facility fitted with a tem-
50 N mm -2 using quality controlled methods of mixing and porary brace across the open end, it was towed a distance
placing. 30% pulverized fuel ash was incorporated. Cover of 40 kilometres to its final position at Coulport. There, the
to external reinforcement and ballast tanks is 50 mm with underwater brace was fitted and the mooring booms and
75 mm in the splash zone and 30 mm for internal surfaces. bridges finally connected up.
Waterstops were incorporated in all construction joints. Construction of the concrete hull was started at the link
end and progressed by stages along each pontoon arm
towards the open end. Reinforcement was in four layers
Post-tensioning in each wall, generally at 150 mm spacing, bar sizes were
As already noted the pontoons were post-tensioned longi- generally between 20 and 32 mm. Galvanized steel ducts
tudinally and transversely across the link at the closed end for the post-tensioning were fixed between the normal
of the berth. The stresses required by the design after allow- reinforcement of walls and slabs before casting. The ducts
ance for losses were 6 N mm -2 in the outer pontoon, intended for housing the 19 strand tendons were 110 mm
9 N mm -2 in the top, 3 N mm -2 in the bottom of the inner diameter, whereas those for the 27 strand tendons were
pontoon and 4 N mm -2 across the link end. This was achi- 140 mm diameter. These are larger in diameter than the
eved mainly by use of 19 strand cables with 27 strand ten- normal recommended to ease threading and to facilitate
dons being used in the more highly stressed areas. 7-wire, grouting of the unusually long tendons. During construc-
15.7 mm super grade strand with low relaxation was used tion, congestion of the steel reinforcement was experienced,
with the VSL pre-stressing system. In total, there were 258 particularly at wall intersections, blister junctions and
tendons which varied in length between 60 and 190 m. The around openings and it was often necessary to locally repo-
tendon ducts were positioned at the centre lines of walls sition and adapt reinforcement.
and slabs to avoid eccentricities in the applied stress, and
most tendons were aligned to be straight except at anchor- Post-tensioning
ages. All ducts were cleaned before installation of the tendons.
All tendons were anchored inside the hull to avoid any This involved rodding, where a wooden dolly was pulled
corrosion problems. The stressing was stopped-off in three through the duct to locate any blockages. Occasionally,
stages 15 m apart near the ends of the pontoons and in two when a blockage could not be removed by the dolly, a
stages at the link end in order to avoid abrupt changes in reaming tool was used. Following rodding the ducts were
the concrete stresses. Reinforced anchor blocks were con- flushed using high velocity water until a sample of water
structed at each end of each tendon in order to resist burst- from the flushing was reasonably clear.
ing stresses and transfer the load to the structure. These Originally it was planned that all tendons were to be
blocks were either 'in-line' or 'blister' blocks, depending installed in the duct by pushing. This involves 'firing' indi-
on the clearance requirements for the stressing jacks. The vidual strands into the ducts by a hydraulic pusher. A cat-
tendons in the main deck and external walls and the bilge flap circuit breaker at the far end automatically stopped the
slab were curved out locally at each end into 'blister' pushing when the strand reached the far end. However, due
blocks, whereas the tendons located in internal walls were to the intense timetable the sub-contractor decided to both
usually in-line blocks involving a temporary opening in the push and winch tendons. Winched tendons were prefabri-
wall for jacking. 'Blister' blocks were used when access cated in a remote area of the site by 'firing' strands into a
difficulties prevented this. straight duct to the required length and cast-welding one
The tendons were fully grouted to prevent destressing end of the tendon. These strand bundles were then pulled
in the event of collision damage and to improve corrosion through the ducts using a winch.
resistance. A separate full-scale trial, 155 m long, involving Once the tendons had been installed they were stressed
three full length tendons was used to test the stressing pro- in a pre-agreed sequence to ensure an even distribution of
cedures and, in particular, the grouting and grout vent-spac- stresses throughout the structure at every stage. Each end
ing. Vents at 30 m gave similar results to vents at 6 m and of the tendon was 'blocked and wedged' and then the jack
therefore a 30 m spacing was adopted. Sections of the trial was seated on the anchor block. For safety, before stressing
were broken out to check the adequacy of grouting which commenced all personnel not involved in the stressing were
was excellent, with full penetration of grout into the tendon removed from the cell and warning signs were erected at
and only an insignificant small lens of air remaining at the both ends of the tendon. It had originally been intended to
Concrete floating berth: P. Starr and D. A. Wainwright 841
jack both ends of all tendons. However, extensions meas- vent it was tied off, and operatives progressed to the next
ured compared to calculated values were such that minimal vent. Success of the grouting during the operation was
'wobble' friction was experienced. Therefore large numbers monitored by observing the pump pressure and gauging the
of later stressed tendon,; were jacked from one end only. progress of the grout along the duct. High pressures or long
The jacks used during post-tensioning stressed all the waits for grout at the vents were indicative of a blockage
strands simultaneously which speeded up the stressing or a leakage. Standby plant was available to flush the grout
operation but restricted manoeuverability. The jacks varied from out of the ducts should these set-backs occur.
in weight between 0.4 and 2.3 t making it necessary to route As each duct was fully grouted, the pressure of the grout
plan the movements using holding bolts and frames with in the duct was maintained at 5 bar for 2 min to ensure the
lifting tackle to position and hold the jacks. The smaller duct was full and the tendon interstices penetrated.
jacks had a stroke length of 100mm and the largest
200 ram. The longer the stroke, the heavier the machine,
and generally a compromise was sought between speed of Conclusions
stressing and ease of jack manoeuverability. This was a large complex job with a dense array of
The theoretical exten,;ion of each tendon was calculated reinforcement and cast-in ducts within narrow walls and
prior to stressing and this was used to compare against the slabs. Placing and compaction of 27,000 m 3 of concrete
actual extensions achieved during stressing as a means of around 8500 t. of reinforcement required great care and
monitoring. Throughout the operation the force in the ten- attention using a combination of internal and external
don was recorded using measurements of the pressure in vibration. When the hull was first floated there was no leak-
the jack by means of two calibrated pressure gauges. At age, which is a tribute to all concerned and bodes well for
every 50 bars the extension of the tendon was measured the future development of high strength concretes. The
and recorded. Equal increments indicated an even extension completed facility has been handed over to the client.
and also that there was no blockage, slippage, sticking or
other problem.
Problems with strand scoring were encountered, but Appendix: Principal parties concerned with
when this resulted in wires snapping the required tendon concrete hull
stress was achieved by stressing at the other end. Only three Client: Ministry of Defence
out of the 258 tendons ,;tressed had extensions outside the Project management PSA Projects Ltd
specified range. Design and supervision: Rendel Palmer and Tritton
Project coordinators: Wimpey Major Projects
Grouting Main contractors: Costain/Taylor Woodrow joint
The progress of the grout pumped into the duct through venture
one end was traced by means of vent pipes located along Post-tensioning sub- Balvac Whitley Moran
each duct at 30 m spacing. When grout flowed through a contractor: