You are on page 1of 5

Engineering Structures, Vol. 18, No. 11, pp.

837-841, 1996
Copyright © 1996 Published by Elsevier Science Ltd
Printed in Great Britain. All rights reserved
0141-0296(95)00162-X 0141-0296/96 $15.00 + 0.00
ELSEVIER

Design and construction of a


concrete floating berth
P. Starr and D. A. Wainwright
Rendel Palmer and Tritton Ltd, 61 Southwark Street, London SE1 1SA, UK

A covered floating berth for submarines is described and the paper


deals in particular with the unique use of concrete in a floating
85,000t twin-hulled post-tensioned structure. The design pro-
cedures and the construction of the hull with particular reference
to the post-tensioning is described in detail. Copyright © 1996
Published by Elsevier Science Ltd.

Keywords:concrete floating berth, design and construction

Introduction Design

This paper describes the design and construction of a


covered floating jetty for the new Vanguard class submar- Description
ines for the Royal Nawd Armaments Depot at Coulport in The large size, cost and construction time constraints ruled
Scotland which is now completed. Heavy craneage and sup- out the use of special concretes.
port services will be provided to the vessels whilst moored Therefore post-tensioned and reinforced concrete with a
at the berth. A floating structure was chosen because the minimum cube strength of 50 N mm -2 at 28 days was used
water depth of 70 m and the sea-bed rock at a slope of 40 ° with a specification aimed at achieving high density and
would have made a cortventional piled structure extremely watertightness.
expensive. However, the floating solution posed additional Figure 3 shows details of part of the structure. The longi-
problems arising from the motions caused by wind, waves tudinal bulkheads are placed symmetrically to coincide with
and tides. the eccentric superstructure columns. Transverse bulkheads
The jetty comprises twin concrete pontoons, each 200 m are provided at 30 m centres with further internal dia-
long by 25 m wide, separated by 30 m of water having a phragms at 15 m centres to match the superstructure col-
draught of 8.5 m and freeboard of 3.5 m. See Figure 1 for umns and support the bottom slab. An intermediate deck is
provided along each side to buttress the outer walls. Con-
a plan of the facility and Figure 2 for a typical cross-sec-
tinuous service passageways are provided. Local shear
tion. The displacement is 85,000 t. At one end the pontoons
stresses were the major parameter in determining wall and
are connected by a rigid box link similar in construction to
slab thickness. The base is between 500 and 700 mm thick
the pontoons. At the opposite end, the pontoons are linked
and the outer and inner walls generally 350 and 300 mm
by an underwater tubular steel brace which allows vessels
thick, respectively. The deck is 350 mm thick with support-
with a draught of up to 13 m to enter the berth. The super- ing beams at 1.5 m centres.
structure over the berth is 60 m wide, a maximum of 45 m With these sizes of walls and the need to provide
high and composed of aluminium clad steelwork. Two reinforcement to both faces for crack control and transverse
internal overhead travelling cranes and a two-leaf vertical bending there is only room for uni-direcfional post-ten-
lift vessel access door are provided. A float-in steel caisson sioning. This was incorporated longitudinally in the base,
gate, the same depth as the pontoons, closes the entrance walls and top deck for the full length of the two pontoons
to the berth. The jetty is permanently moored to the shore and designed to resist the longitudinal bending and tor-
by articulating 2.5 m diameter tubular steel booms and pro- sional stresses. Transverse post-tensioning was considered,
vided with two 10 m wide steel box girder bridges to cater but rejected because of insufficient depth in the deck slab
for a maximum tidal range of about 5 m. Steel reinforced and congestion that would have been caused by the steel in
rubber shear blocks at the shore ends of the mooring system the anchorages. However, post-tensioning was incorporated
provide flexibility and considerably reduce mooring loads across the link end (see Figure 4) where the deck slab was
compared to a rigid system. increased in depth to allow the longitudinal post-tensioning
This paper is chiefly concerned with the use of concrete to cross over the transverse post-tensioning at the two link
for the pontoons which provide all the buoyancy necessary end comers. Temporary holes were left in the deck slabs
to support the facility. to allow access for the stressing jacks. The column bases

837
838 Concrete floating berth: P. Starr and D. A. Wainwright
FACILITY
NORTH
ENCLOSURE BUILDING
/ 'i _ALTERNATIVECAISSON
200m ,, / G A T E MOORING
OUTER BERTH
.UNDERWATER BRACE

-?$.0
, r - - r6'~.-~,~ . . . . . . . . . . . . . -~T -CAISSON
GATE
I | i,':ll'_':i J l N CLOSED POSITION
BOm ,' // P;]!i
i ~-L.'.~: - so. o
", 30mJ COVERED BERTH ~,~:~!
-SO0
I I~-CAISSON GATE MOORED
,~,~1 I IN OPEN POSITION
_.1.

-25.0

60t
ti ~oo .~// ~,,~o_ .~// L=lil

..... ~ J ~i~ L~oo,,.o , , o o . t ! ~ r " ' ~

I ,o~ .I
,~.Y su,','oR, .RE.
Figure I Plan

61 .Sm

OVERHEAD TRAVELL IN4 GRANE

OVERHEAD TRAVELLING CRANE


SHORE LOCK
SIDE E SIDE
o
('N

OOCKINO TROLLEY
RAILS--..__
NOORIN0 80014

LEVEL

":l- ! = ~ ~ ~ 1
¢N
,..
1-
DRAUOHT
e4

PONTOON PONTOON

'-
25m I 30m I -
25m

Figure 2 Cross-section
Concrete floating berth: P. Starr and D. A. Wainwright 839

LE~I MAIND I ~ ( ~ FALL


T ;. • ,. , ; ,

SERVICE PASSAGEWAYS " "


PT A ~ 3E DRAINAGE PORT
~=OST-TENSIONEO TENDONS
.V .Vq:P,
'_'~" II r 1/. LAYERS OF STEEL BAR 'J DRAINAGEPORT/ I*1- ¢.:,:
REINFORCEMENT NOT SHOWNI
300ram
.o,i- i-
LEVEL3
OETCK BEAM
.............. 1200- 1 ,~o,,,,,,
1 , ! t °

LEVEL& BILGE
T

.,=
BALLAST TA

-I
|

IOm

25m
• • e • •

ill
• •
BALLAST TANK

• • •

7.5 m
' li
• • •

J_
1
Figure3 Cross-section ot: outer pontoon

16.0 m(~
t,t
'S 3m _:_ 5',~m _ ; _ 7-Sm

T -I m
LEVEL I MAIN
r- • • • • If DECK

i
!
i
o
f,.j ILEVEL2 PASSAGE
SERVICE

BEAM

LEVEL 3 MACHINE
t OECK

LEVEL/, BILGE
f

Figure4 Cross-section of link end

and mooring booms were bolted to the concrete hull by ditions were modelled using springs and restrained free-
post-tensioned Macalloy bars. doms to represent mooring boom articulation and vertical
springs to represent buoyancy stiffness. Static loadings
Analysis were applied to represent wave, wind, dead, ballast and pre-
The finite element membrane method was chosen to ana- stress forces. Different combinations of live load were used
lyze the global loading because of its flexibility in allowing to represent maximum hogging, sagging, torsion and rack-
a detailed model of the link end to be used with a relatively ing at key sections. Following the initial finite element
coarse model of the straight pontoon sections. Support con- membrane analysis, adjustments were made to the post-ten-
840 Concrete floating berth: P. Starr and D. A. Wainwright

sioning to achieve the most economic and effective use of top of the duct. The grout used in the trial and throughout
the prestress. construction was an ordinary portland cement grout with
The transverse loading of individual panels and loaded 0.36 W/C ratio and Cormix SP4 superplasticiser 1% by
areas of the structure arising from water and plant loads weight of cement.
were analysed by local framework analysis and the results
combined with the direct and shear stresses obtained from
the global analysis to check concrete stresses and reinforce Construction
the members. Special attention was paid to areas of high
external load such as column bases, mooring boom connec- General
tions and bridge supports. The chosen thickness of the con- Construction of the jetty started in 1989 in a dry dock in
crete sections was confirmed and no shear reinforcement the Firth of Clyde. It was fully pre-tensioned and brought as
was required except as conventional stirrups in the deck near final completion as possible including superstructure,
beams and column bases. cladding and crane erection all in the dry dock. The dock
A major aim was durability of the concrete structure was then flooded, the facility moored and the dock entrance
requiring minimum maintenance and to achieve water- dredged out. The dock was deep enough to keep the jetty
tightness. The specification was designed to produce high floating at all states of the tide. With a suitable calm
density concrete with a minimum 28 day cube strength of weather window forecast and the facility fitted with a tem-
50 N mm -2 using quality controlled methods of mixing and porary brace across the open end, it was towed a distance
placing. 30% pulverized fuel ash was incorporated. Cover of 40 kilometres to its final position at Coulport. There, the
to external reinforcement and ballast tanks is 50 mm with underwater brace was fitted and the mooring booms and
75 mm in the splash zone and 30 mm for internal surfaces. bridges finally connected up.
Waterstops were incorporated in all construction joints. Construction of the concrete hull was started at the link
end and progressed by stages along each pontoon arm
towards the open end. Reinforcement was in four layers
Post-tensioning in each wall, generally at 150 mm spacing, bar sizes were
As already noted the pontoons were post-tensioned longi- generally between 20 and 32 mm. Galvanized steel ducts
tudinally and transversely across the link at the closed end for the post-tensioning were fixed between the normal
of the berth. The stresses required by the design after allow- reinforcement of walls and slabs before casting. The ducts
ance for losses were 6 N mm -2 in the outer pontoon, intended for housing the 19 strand tendons were 110 mm
9 N mm -2 in the top, 3 N mm -2 in the bottom of the inner diameter, whereas those for the 27 strand tendons were
pontoon and 4 N mm -2 across the link end. This was achi- 140 mm diameter. These are larger in diameter than the
eved mainly by use of 19 strand cables with 27 strand ten- normal recommended to ease threading and to facilitate
dons being used in the more highly stressed areas. 7-wire, grouting of the unusually long tendons. During construc-
15.7 mm super grade strand with low relaxation was used tion, congestion of the steel reinforcement was experienced,
with the VSL pre-stressing system. In total, there were 258 particularly at wall intersections, blister junctions and
tendons which varied in length between 60 and 190 m. The around openings and it was often necessary to locally repo-
tendon ducts were positioned at the centre lines of walls sition and adapt reinforcement.
and slabs to avoid eccentricities in the applied stress, and
most tendons were aligned to be straight except at anchor- Post-tensioning
ages. All ducts were cleaned before installation of the tendons.
All tendons were anchored inside the hull to avoid any This involved rodding, where a wooden dolly was pulled
corrosion problems. The stressing was stopped-off in three through the duct to locate any blockages. Occasionally,
stages 15 m apart near the ends of the pontoons and in two when a blockage could not be removed by the dolly, a
stages at the link end in order to avoid abrupt changes in reaming tool was used. Following rodding the ducts were
the concrete stresses. Reinforced anchor blocks were con- flushed using high velocity water until a sample of water
structed at each end of each tendon in order to resist burst- from the flushing was reasonably clear.
ing stresses and transfer the load to the structure. These Originally it was planned that all tendons were to be
blocks were either 'in-line' or 'blister' blocks, depending installed in the duct by pushing. This involves 'firing' indi-
on the clearance requirements for the stressing jacks. The vidual strands into the ducts by a hydraulic pusher. A cat-
tendons in the main deck and external walls and the bilge flap circuit breaker at the far end automatically stopped the
slab were curved out locally at each end into 'blister' pushing when the strand reached the far end. However, due
blocks, whereas the tendons located in internal walls were to the intense timetable the sub-contractor decided to both
usually in-line blocks involving a temporary opening in the push and winch tendons. Winched tendons were prefabri-
wall for jacking. 'Blister' blocks were used when access cated in a remote area of the site by 'firing' strands into a
difficulties prevented this. straight duct to the required length and cast-welding one
The tendons were fully grouted to prevent destressing end of the tendon. These strand bundles were then pulled
in the event of collision damage and to improve corrosion through the ducts using a winch.
resistance. A separate full-scale trial, 155 m long, involving Once the tendons had been installed they were stressed
three full length tendons was used to test the stressing pro- in a pre-agreed sequence to ensure an even distribution of
cedures and, in particular, the grouting and grout vent-spac- stresses throughout the structure at every stage. Each end
ing. Vents at 30 m gave similar results to vents at 6 m and of the tendon was 'blocked and wedged' and then the jack
therefore a 30 m spacing was adopted. Sections of the trial was seated on the anchor block. For safety, before stressing
were broken out to check the adequacy of grouting which commenced all personnel not involved in the stressing were
was excellent, with full penetration of grout into the tendon removed from the cell and warning signs were erected at
and only an insignificant small lens of air remaining at the both ends of the tendon. It had originally been intended to
Concrete floating berth: P. Starr and D. A. Wainwright 841

jack both ends of all tendons. However, extensions meas- vent it was tied off, and operatives progressed to the next
ured compared to calculated values were such that minimal vent. Success of the grouting during the operation was
'wobble' friction was experienced. Therefore large numbers monitored by observing the pump pressure and gauging the
of later stressed tendon,; were jacked from one end only. progress of the grout along the duct. High pressures or long
The jacks used during post-tensioning stressed all the waits for grout at the vents were indicative of a blockage
strands simultaneously which speeded up the stressing or a leakage. Standby plant was available to flush the grout
operation but restricted manoeuverability. The jacks varied from out of the ducts should these set-backs occur.
in weight between 0.4 and 2.3 t making it necessary to route As each duct was fully grouted, the pressure of the grout
plan the movements using holding bolts and frames with in the duct was maintained at 5 bar for 2 min to ensure the
lifting tackle to position and hold the jacks. The smaller duct was full and the tendon interstices penetrated.
jacks had a stroke length of 100mm and the largest
200 ram. The longer the stroke, the heavier the machine,
and generally a compromise was sought between speed of Conclusions
stressing and ease of jack manoeuverability. This was a large complex job with a dense array of
The theoretical exten,;ion of each tendon was calculated reinforcement and cast-in ducts within narrow walls and
prior to stressing and this was used to compare against the slabs. Placing and compaction of 27,000 m 3 of concrete
actual extensions achieved during stressing as a means of around 8500 t. of reinforcement required great care and
monitoring. Throughout the operation the force in the ten- attention using a combination of internal and external
don was recorded using measurements of the pressure in vibration. When the hull was first floated there was no leak-
the jack by means of two calibrated pressure gauges. At age, which is a tribute to all concerned and bodes well for
every 50 bars the extension of the tendon was measured the future development of high strength concretes. The
and recorded. Equal increments indicated an even extension completed facility has been handed over to the client.
and also that there was no blockage, slippage, sticking or
other problem.
Problems with strand scoring were encountered, but Appendix: Principal parties concerned with
when this resulted in wires snapping the required tendon concrete hull
stress was achieved by stressing at the other end. Only three Client: Ministry of Defence
out of the 258 tendons ,;tressed had extensions outside the Project management PSA Projects Ltd
specified range. Design and supervision: Rendel Palmer and Tritton
Project coordinators: Wimpey Major Projects
Grouting Main contractors: Costain/Taylor Woodrow joint
The progress of the grout pumped into the duct through venture
one end was traced by means of vent pipes located along Post-tensioning sub- Balvac Whitley Moran
each duct at 30 m spacing. When grout flowed through a contractor:

You might also like