You are on page 1of 18

Journal of Cleaner Production 228 (2019) 1264e1281

Contents lists available at ScienceDirect

Journal of Cleaner Production


journal homepage: www.elsevier.com/locate/jclepro

Building information modelling-based framework to contrast


conventional and modular construction methods through selected
sustainability factors
Ahmed WA. Hammad a, *, Ali Akbarnezhad b, Peng Wu c, Xiangyu Wang c, Assed Haddad d
a
Faculty of Built Environment, UNSW Sydney, Australia
b
School of Civil Engineering, University of Sydney, Australia
c
School of Design and Built Environment, Curtin University, Perth, Australia
d
Departamento de Construça ~o Civil, Federal University of Rio de Janeiro, Brazil

a r t i c l e i n f o a b s t r a c t

Article history: In recent years, off-site construction has been significantly hyped as a viable solution for improving the
Received 23 April 2018 sustainability of the construction industry. There is yet an approach to be developed that can utilise
Received in revised form project-specific parameters to quantify the improvement in adopting off-site methods as opposed to
11 April 2019
conventional construction. This paper focuses specifically on modular construction as an off-site
Accepted 14 April 2019
Available online 22 April 2019
production system, where a decision support tool is proposed for contrasting conventional and
modular construction methods based on selected sustainability criteria. The framework relies on
quantifying certain measures of: i) social factors, including safety and noise pollution; ii) environ-
Keywords:
Construction method selection
mental factors, such as energy consumption, U-value of the building envelope and embodied energy;
Modular construction and iii) economic factors including time and cost of construction. Fuzzy logic, equivalent noise sum-
Off-site prefabrication mation and algorithmic mapping are utilised to quantify the sustainable measures adopted. The indices
Sustainable construction utilised to showcase the possible comparison that can be made between construction methods, are up
Embodied energy to the decision maker to decide upon. Realistic case studies, involving the construction of a granny flat
and a school are used to demonstrate the applicability of the developed framework. The modular
construction method was found to perform on average 21%, 52% and 60% better in terms of the
measures adopted for social, environmental and economic costs in contrast with the conventional
approach, for the cases considered.
© 2019 Published by Elsevier Ltd.

1. Introduction quarter of 2016, the total contribution of the construction sector to


the GDP was assessed to be at 7.6% (Trading Economics, 2017).
Due to its large consumption of energy and materials, the These numbers are not expected to decrease anytime soon, with
building and construction industry is a major contributor to sus- the constant demand for residential projects and non-residential
tainability challenges. The sustainable development of the built construction works (Albelwi et al., 2017). Due to its economic
environment in response to evolving demands of today's world is a importance and large market share, along with its resource, energy
well-recognised goal in the construction and building industry. This and carbon intensive operations, the construction sector has sub-
is imperative particularly given that buildings comprise the ma- stantial potential for improvement in terms of sustainability (UNEP,
jority of the urban composure of cities worldwide (Thomas, 2007). 2009).
Karausmann et al. in a report highlighted that the construction Among various environmental impacts of the construction and
sector is considered to be the largest consumer of materials building industry, energy use and carbon emissions have received
(Krausmann et al., 2009), contributing to 29%e44% of total waste significant attention. This is mainly due to the high global contri-
produced by all sectors worldwide (DEFRA, 2013). In the first bution to carbon emissions and energy use of the industry (Asif,
2016). Buildings are reported to account for 30% of annual green-
house gas emissions across different developed and developing
* Corresponding author. countries (Intergovernmental Panel on Climate Change, 2007).
E-mail address: a.hammad@unsw.edu.au (A.WA. Hammad).

https://doi.org/10.1016/j.jclepro.2019.04.150
0959-6526/© 2019 Published by Elsevier Ltd.
A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1265

Already rated amongst the biggest per capita contributors to GHG 2. Literature review
emission worldwide, Australia is facing growing challenges in
limiting the increasing amount of energy use and emissions due to Modular construction is characterised by having the highest
its growing population and the corresponding increasing demand level of prefabrication, with around 80e90% of the project manu-
for infrastructure and services (DCCEE, 2012). In Australia, the en- factured in a controlled environment (Alistair G.F. Gibb, 1999). Once
ergy consumption of buildings and their associated carbon foot- the modules are complete, they are transported to the construction
print is expected to rise by about 24% over the next couple of years site where they are positioned in place.
(Acil Allen Consulting, 2015). In the US, the built environment ac- The overall sustainability advantages of modular construction
counts for around 36% of total carbon emissions in the country (UN compared to on-site conventional construction have been discussed
Environment and International Energy Agency, 2017) while in in previous studies. These include shorter construction times
Canada the built environment accounts for 33% and 50% of energy (Bernstein et al., 2011), enhanced safety of workers (Smith, 2011),
and natural resource consumption respectively (Industry Canada, higher quality control (Pan et al., 2007) and less environmental
2011). In Norway carbon emissions from construction activities breaches compared to conventional methods (Jia Wen et al., 2015).
increased by 4.2% between 2003 and 2007 (Huang and Bohne, Despite the benefits, the market share of modular construction still
2012). In China, the construction industry accounts for over 50% remains below 4% in Australia (Hajkowicz, 2016), while the average
of the total country's energy use (Chang et al., 2010). These of off-site construction across the UK has been reported to be less
resulting figures, indicating the huge impact of the construction than 7% (KPMG, 2016). Such low adoption rates are attributed partly
industry on global energy use and carbon emissions, has led to a to the lack of understanding of the benefits of prefabrication in
growing interest in examining environmental and economic im- general, and modularisation in specific, for a given project (Lu, 2007).
plications of various design and planning decisions within con- To address such a gap, a number of efforts have been made to
struction (Hammad et al., 2018). A sustainable approach to compare conventional in-situ and modular construction methods
construction requires a broader perspective, which not only ac- (Kamali and Hewage, 2016). Efforts have focused on environmental
counts for individual sustainability parameters separately, but also impacts, rather than life cycle sustainability where a combination of
attempts to capture certain aspects of the triple bottom line of economic, environmental and social impacts are assessed (Kamali
sustainability, namely social, economic and environmental di- and Hewage, 2016). Al-Hussein et al. (2009) emphasised the
mensions over the life cycle of a construction project (Jeong et al., distinction between modular and conventional methods in the
2016). construction phase. This was achieved through a comparison of the
A highly advocated sustainable alternative to conventional in- carbon footprint associated with both construction methods.
situ construction is off-site prefabrication construction (Mao Embodied and operational energies, waste, GHG emissions and
et al., 2013). The numerous social, economic and environmental resource consumption of modular and conventional construction
benefits of off-site prefabrication, including improved safety and methods were compared by Kim (2008) using a life-cycle approach.
productivity, and reduced waste highlight its suitability as a Baldwin et al. (2009) investigated waste reduction in high-rise
potentially more sustainable alternative to conventional construc- prefabricated and conventional residential buildings. The authors
tion (Jaillon et al., 2009). As a construction system, off-site pre- concluded that standardisation in design and adoption of prefabri-
fabricated construction is comprised of a process where varying cation enables waste savings to be realised. Chen et al. (2010a, b)
degrees of particular components of a building are manufactured developed a decision-support system which utilises four attributes
and assembled in an off-site factory, and transported to be installed of a project, namely project characteristics, site conditions, market
on site (Bernstein et al., 2011). Given that modular construction is attributes and local regulations, to determine whether the choice of
one of the most efficient off-site construction methods (Kamali and prefabrication for a project is feasible or not. Monahan and Powell
Hewage, 2017), the focus in this study is on utilising modular (2011) proposed a life cycle analysis framework that conducts a
construction as the off-site prefabrication method contrasted partial life cycle assessment (LCA) from cradle to site, to compare the
against conventional construction methods. embodied carbon of modular timber frames systems with traditional
The goal of this paper is to propose an automated framework construction approaches. Aye et al. (2012) compared the embodied
that can aid decision makers in the selection of an appropriate energy associated with steel and timber modular construction
construction method, based on a set of criteria that target social, methods, against conventional building approaches, through the use
economic and environmental aspects of construction. The criteria of LCA. Quale et al. (2012) examined the construction phase of
are up to the decision maker to decide upon; in this article a modular and traditional buildings, in terms of energy consumption,
selected number of factors are modelled to highlight the appli- from cradle to end. Faludi et al. (2012) evaluated the environmental
cability of the framework. Extensions of the proposed framework performance of modular systems without contrasting them against
to other factors of relevance are also demonstrated. By developing conventional methods.
the construction method comparison framework, this paper Analysing the state-of-the-art reveals that most studies focus on
contributes in the areas of sustainable building construction, establishing the environmental advantage of modular construction,
pollution reduction in construction and sustainability assessment without proposing a generalised framework that can incorporate
of construction methods. Developing a decision support system to additional sustainability measures including social and economic
evaluate the sustainability of conventional in-situ and modular factors. The absence of a systematic framework to evaluate the
construction methods would enable decision makers to fully grasp comparative benefits and costs of modular and conventional con-
the distinctions between these construction methods, leading to struction methods (Blismas et al., 2006), particularly in terms of
better informed construction method choices. The method triple bottom line of sustainability (Kamali and Hewage, 2017),
developed in this paper contrasts modular and conventional makes it harder to understand the real benefits and costs of each
construction methods, based on evaluating a set of relevant sus- construction approach. In the absence of systematic assessment
tainability criteria in a digital platform. The paper is organised as methods, most decisions that are made regarding the use of
follows: in Section 2, a review of the relevant literature is pre- modularisation are based on personal preference by clients, simple
sented. Section 3 describes the framework. A realistic case study is cost analysis or anecdotal evidence (Chen et al., 2010a). Such
then adopted to highlight the capability of the developed choices are difficult to quantitatively justify as they can vary
approach. depending on project type, size and complexity.
1266 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

Automatic extraction of information from digital models such as impact of modular and in-situ construction methods with regards
BIM, and their use to propose an appropriate construction method to each factor of the sustainability dimension is highlighted. As
based on a set of criteria assessing economic, social and environ- shown in Fig. 1, the framework relies on three main input modules
mental considerations is still lacking. As highlighted in the above to obtain the information required for the sustainability assess-
reviewed studies, the focus has been traditionally placed on envi- ment. These include: i) input data from BIM, which embeds se-
ronmental impact proxies, rather than a combination of economic, mantic information regarding the design that is desired to be
environmental and social impacts that need to be collectively achieved in each construction method; ii) a schedule that links
analysed to achieve sustainability in construction. Within the activities involved in each construction method; and iii) a mapping
environmental measure, studies tend to focus mostly on emissions set composed of materials, crew and equipment that are utilised in
or energy, to compare the impact of different construction each construction method.
methods. This is even though each dimension of sustainability is The available information is then compiled and passed on to an
composed of a multitude of measures that need to be combined in algorithm that establishes a direct link between each element in
order to realise the impacts of the dimension being assessed. In the the BIM file and the set of activities making up the respective
next section, a method that accounts for the three dimensional construction method. The two most imperative factors when it
scales of sustainability when contrasting modular and conventional comes to social considerations impacting modular construction are
construction approaches, is presented (Blismas et al., 2006). noise pollution and enhanced safety of workers (Chen et al., 2010a).
As a result, for the social analysis, an assessment of noise pollution
that is related to disturbance caused to the community is con-
3. Method
ducted. The safety level associated with each construction method
is also compared.
In construction, importance is traditionally given to factors that
When it comes to the environmental pillar of sustainability,
impact the cost associated with the project (Pasquire and Connolly,
embodied and operational energy are of high relevance in con-
2002). Recently, there has also been an interest in utilising social
struction (Monahan and Powell, 2011). The environmental analysis
and environmental measures to assess decisions adopted. As a
conducted in the framework, referred to as an energy analysis,
result, a method was developed herein for construction method
considers the effect of each construction method on the embodied
selection that combines economic, social and environmental con-
energy of the building as well as the U-value of the envelope. The U-
siderations, while ensuring that the evaluation of these factors is an
value is taken to be a measure of thermal effectiveness of the
accurate representation. The method is expected to allow decision
building due to its impact om the operational energy load of the
makers to make better informed decisions when it comes to con-
building. For economic factors, the most relevant are time and cost,
struction method selection, and to help them satisfy requirements
as these are largely influential in the decision-making involved in
set by regulators on certain sustainability factors. Fig. 1 displays the
the AEC industry (Pasquire and Connolly, 2002). The economic
main steps undertaken in the developed framework to compare the
analysis focusses on computing and comparing the monetary cost
sustainability performance of modular and conventional con-
and the time taken for completing all activities associated with the
struction methods. The social, environmental and economic factors
contrasted construction methods. The next sections elaborate more
considered in the framework have been selected by considering the
on the input, algorithm and sustainability analysis conducted.
main impact categories for construction projects, as determined in
the literature reviewed above. A quantitative basis for analysing the

Fig. 1. Framework to compare conventional and modular methods.


A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1267

3.1. Input data  The set L, which links each element in the BIM file to an activity
of the precedence network for each construction method
The input required in the developed framework is composed of  The set M, which links each element in the BIM file to a material
three major components. The first component is the BIM file that m2M. Set M represents the set of all materials that are utilised
contains all the elements that are required within the project. Each in both construction methods
construction method will contain specific building elements. The  The set C, which links each element in the BIM file to a crew
importance of including the BIM files is due to the need to extract c2C. Set C represents the set of all crew (equipment and
information on the element properties and materials from which personnel) required for each activity of each construction
these elements are composed. The element properties will enable method.
establishing a link with the schedule of activities and the cost  X is the set of all links formed between activities i and crew c
associated with the construction method analysed. Utilising  The set Ad corresponds to the set of all activities involved in a
element properties also enables the analysis of the embodied en- given construction method d
ergy and U-value associated with the building generated by each
construction method. The creation of links between the elements in BIM and the
The second input component is a precedence network that precedence network is achieved through a matching algorithm
highlights the activities that take place during the construction developed in Dynamo (Autodesk, 2017). Dynamo is an open source
operations for each contrasted method. Information such as the visual programming tool that enables algorithmic design in Revit, a
activity duration and the resource requirements for each activity BIM software (“Autodesk Inc.,” 2018). Since each element that is
can be derived from the precedence network. Such information can included in the BIM file is associated with a unique ID and prop-
then be processed further to calculate productivity levels, noise erties that reflect its type, a link between each of the elements and
pollution and cost requirements that are associated with each ac- the libraries produced by Algorithm 1 (i.e. algorithm output) can be
tivity. Information from the BIM files enables the creation of a direct established.
link between the elements and the activities that are undertaken in The research presented herein aims to present the main con-
each construction method. cepts underlying an automated framework for recommending
The third component of the input is comprised of a Mapping Set appropriate construction methods to adopt, based on a set of fac-
that contains 2 different libraries. Each library is concerned with tors that are proxy measures of the three main pillars of sustain-
mapping one of three parameters to the activities of the precedence ability. Additional factors for each sustainability parameter can be
network, including the material, crew and equipment. To achieve a further investigated through slight modification of the code in Fig. 2
link between the elements within the BIM file and the activities in to allow for inclusion of more factors in the decision-making pro-
the precedence network, additional information that maps the ma- cess. In the following section, the analysis conducted to evaluate
terial types, crew size and equipment to each activity is required; each construction method based on the three dimensions of sus-
such is the purpose of developing the Mapping Set. The first library tainability are discussed.
within the Mapping Set associates the materials utilised throughout
the project with a given activity from the precedence network. The 4. Sustainability analysis for construction method
second library links one or more of the crews required during the
construction process with an activity on the precedence network; The approach utilised in this study is based on quantifying the
determining the size of the crew is based on the requirement of factors reflecting each sustainability pillar that can be adopted in
human resources and equipment that are necessary to complete the decision-making process. Risk assessment via risk distribution
the respective activity. and fuzzy logic (Islam et al., 2017), is used to assess the safety
measure in the social analysis; noise-level measurement is used for
noise pollution assessment (Standards Australia, 2010a, b);
3.2. Sustainability assessment algorithm embodied and operational energy quantification is achieved via use
of cradle-to-grave assessment and U-value calculation respectively
All components of the input are passed on to an algorithm which (Hammad et al., 2018); while for the economic parameter, factors
parses the information and creates an association between the el- such as time and cost are quantified based on the utilisation of
ements of BIM and the two main parameters that are assigned schedules, productivity databases and cost indices (Kaming et al.,
within the Mapping Sets, namely the materials and crew required 1997). The next sections highlight the quantification methods in
for each activity in each construction method. The link between the detail for each sustainability parameter targeted. It is important to
Mapping Sets, the BIM file and the precedence network, and the note that with slight modification, a weighted approach is possible
pseudo-code of the algorithm, is schematically elaborated in Fig. 2. in the developed method, where the decision maker can associate
The developed algorithm is labelled as Algorithm 1. higher weights with factors that influence their construction
Algorithm 1 starts by looping through all elements in the BIM method selection decisions the most.
model, making use of the element ID property in BIM (Eastman,
2008). Looping through the activities of the precedence network 4.1. Factors for social analysis
and through the parameters making up the Mapping Sets, the al-
gorithm creates a link between the elements of the BIM file and In order to analyse the social impacts of the construction
between the activities, materials, crew and equipment. The linking methods being examined, two surrogate measures are adopted,
of resources, including crew, equipment and material is subject to Fig. 3. The first measure captures the safety aspect associated with
both the availability of the respective resource and the demand for each activity involved in each construction method. This is based on
resources, as specified in the precedence relationship of the activity historical data which can be accumulated from past projects. In
network diagram input. Algorithm 1 contains a condition that order to calculate the safety level linked with each construction
adopts concepts from resource levelling in order to account for the method, an accumulated measure that accounts for risk distribu-
requirement of each activity in terms of resource demand. tion of the activities, the probability of occurrence of an accident
Overall, the output that is produced by Algorithm 1 is given as and its corresponding consequence level is used. An a priori map-
follows. ping is created where each activity is linked to a i) number of
1268 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

Fig. 2. Algorithm 1, which links BIM with activities and this creates mapping sets.

Fig. 3. Framework for conducting social analysis.

possible hazards; and ii) the consequence level associated.


The risk distributions for each activity are generated using fuzzy ð5
logic, through a trapezoidal function adapted from (Chen and Vi ¼ xi mi ðxÞ ci2A (1)
Hwang, 1992), Table 1. The risk exposure level is set as xε½0; 5. A
0
de-fuzzification function, which relies on the centroid method
(Zimmermann, 2013), is then used to estimate the value of risk The higher the risk measure Vi , the more exposed are the
exposure, Vi , based on the fuzzy set defined in Table 1, via the use of workers involved to injury in the activity. The process is repeated
Eq. (1) for each activity, iεA: for all activities involved in each construction method.
It is important to note that the definitions presented in Table 1
will be based on the perception of the contractor hired on each
Table 1 project; the levels can be modified to suit operation requirements
Fuzzy set definition for social analysis.
specific to the project at hand. The overall method will remain the
Impact Interpretation Trapezoidal function mðxÞ same as that described herein.
Critical Very high impact (4, 4.5, 5, 5) A second surrogate measure of the social cost for construction
Serious High Impact (3, 3.75, 3.75, 4.5) projects is the noise pollution emitted from the construction pro-
Moderate Moderate Impact (1.5, 2.5, 2.5, 3.5) cess (Hammad et al., 2016). In this study, the noise level is
Minor Small Impact (0.5, 1.25, 1.25, 2) measured in accordance with the Australian standards for noise
Negligible No substantive impact (0, 0, 0.5, 1)
calculation of construction activities (Standards Australia, 2010a).
A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1269

The process is again depicted in Fig. 3. As an initial step, the mass and U-value of the building (Aksamija, 2013; Ficco et al.,
equivalent average level, LAeqi is determined for each activity i2A 2015). Theoretically speaking, any material adopted in conven-
involved in each construction method. The duration of each activity tional construction can still be utilised on buildings constructed
is a required input to calculate noise pollution, which depends on through the modular construction method. In reality, modular
the productivity of the crew performing the activity, and can manufacturing firms restrict themselves to certain material types
therefore vary from one contractor to another. With this in mind, in order to ensure enhanced production rates (Lawson et al., 2011).
the durations are calculated based on contractor's historical pro- This study reflects this current practice by associating common
ductivity values or based on productivity values reported in avail- material types with both construction methods.
able cost databases such as RSMeans (RSMeans, 2017). Adjustments Given its considerably higher influence on energy efficiency, in
that account for the size, shape, barriers and acoustic properties of terms of thermal transmittance of the building, compared to other
the region surrounding the environment in which the construction factors, the U-value of the building's envelope (external walls and
activities are taking place are taken into consideration in calcu- roof) is used as a surrogate measure to characterise the relative
lating the noise pollution. Eq. (2) is then used to combine the effects effect of conventional and modular construction methods on the
of all these factors into a single measure of noise over the assessed energy efficiency of the building (Ficco et al., 2015; Robinson et al.,
period, T, namely the equivalent A-weighted sound level LAeqT;i for 2017).
each activity: A 2-dimensional approach, based on the parallel method, is
used to analyse the U-value of the structures’ envelopes. This
1 X approach is adopted because the wall elements are composed of
LAeqT;i ¼ 10log10 te;i 100:1Le;i ci2A (2)
T more than a single layer, with each layer comprised of a different
e2E
material (Advanced Buildings, 2010), hence creating a discrepancy
where, te represents the time of operation of noise-producing in the conductance of the layer. Such instances require the use of a
equipment eεE involved in each activity and Le;i denotes the weighted average of thermal transmittances and so the average
equivalent sound level of equipment involved in the operation of transmittances of heat flow travel paths through the concerned
each activity. layer is utilised.

4.2. Factors for environmental analysis 4.2.2. Embodied energy


The choice of modular construction method over conventional
The energy analysis embedded in the developed framework to construction method leads to considerable differences in the con-
contrast conventional and modular construction methods, is based struction operations involved and is therefore expected to result in
on quantifying the energy requirements during the operation and variations in the embodied energy of the building. In this study, the
assembly/construction phase of the building. This is achieved cradle to gate embodied energy is used as a surrogate measure of
through adopting relevant surrogate measures, including thermal environmental impacts. The cradle to service embodied energy can
efficiency and embodied energy. Fig. 4 highlights the overview of be calculated by adding the cradle to gate embodied energy of the
the factors considered in the energy analysis. material to the energy utilised during the construction process
(Akbarnezhad and Xiao, 2017).
4.2.1. Energy efficiency
The choice of conventional vs modular construction methods 4.2.2.1. Construction energy. The amount of energy expended dur-
can potentially influence the operational energy load of the build- ing the construction process for each construction method is
ing through differences in the materials used in the structure and examined by estimating the amount of diesel and electricity
the exterior envelope, which in turn lead to differences in thermal consumed by construction equipment throughout the construction

Fig. 4. Energy analysis comprised of calculating operational and embodied energy.


1270 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

phases (this includes transportation of material to site). Eq. (3) is adopted to account for uncertainty in terms of possible delays, and
adopted to obtain the energy requirement during the construction hence compute the duration of each activity. For conventional
phase for each activity iεA: construction methods, the main source of delay is considered to be
X the weather (Abd El-Razek et al., 2008), whereas for modular
CEi ¼ t e fe ðiÞ ci2A (3) construction, delays occur mostly due to machine breakdown (Zhai
e2E et al., 2015). A set of scenarios are utilised to reflect probabilities
associated with events resulting in delay for both methods. In this
where CE denotes the total construction energy for each activity framework, this is achieved through one of two alternative
involved, in MJ, t e is the time of operation of the equipment asso- methods: i) historical data that are relevant to the individual firm/
ciated with activity i, as obtained from the mapping produced by entity utilising the construction method; and ii) sampling from an
the algorithm, fe ðiÞ is a generalised function for each equipment exponential distribution which is commonly accepted in the liter-
utilised, which describes the energy requirement of equipment ature as accounting for risk (Balakrishnan, 1996). The precedence
involved in activity i. networks of each construction method are used as the basis for
determining the time of completion.
4.2.2.2. Cradle to gate embodied energy. The cradle to gate Factors modelled in the framework that can influence the time
embodied energy accounts for the energy required to extract, and cost expended in each construction method include the crew
manufacture, construct and transport materials between different size (involving workers and equipment), and material required
processing facilities and to the construction site. The embodied (Kaming et al., 1997); both are impacted by the activities associated
energy factors can be obtained from inventories such as (Hammond with each construction method.
and Jones 2008). The following equation is used to estimate the For each construction method, the input data, comprised of a
embodied energy associated with each construction method, Eq. priori mapping sets as described earlier, are embedded into the BIM
(4): model via Algorithm 1. One or more materials become linked to
X each element of the BIM file, using the element ID property in BIM.
CG ¼ EEi;m Qi;m (4) The required crew and equipment are linked to the elements within
ði;mÞ2W BIM via a combination of mapping sets and the element IDs. The
algorithm is then linked to a rates database in order to compute the
where CG denotes the total cradle to gate energy, W is the set of time and cost associated with each construction method. The time
links formed between activities i and material m, as determined by associated with each construction method, dεY is derived using the
Algorithm 1 of Fig. 2, EEi;m refers to the embodied energy (in MJ/kg) following equation, Eq. (5):
associated with material m belonging to activity i, while Qi;m is the
quantity of material m linked to activity i. c
X X X Q i;m
timed ¼ þ OTd cd2Y (5)
P ci;m
4.3. Factors for economic analysis i2Ad c2C: m2M
ði;cÞ2X ði;mÞ2W
Fig. 5 shows the method adopted in this study to perform the
economic analysis. Two measures that are critical to the economic where the set A0 d corresponds to the set of all activities involved in a
assessment of the contrasted construction methods are the time given construction method d, and X 0 is the set of all links formed
c
and the associated monetary costs (Ozcelik, 2016). A fuzzy logic between activities i and crew c. The variable Q i;m represents the
approach, like the one presented above (see Eq. (1) and Table 1), is quantity of material of type m associated with activity i that will

Fig. 5. Framework for conducting economic analysis.


A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1271

require crew c to be assigned to it. The variable P ci;m represents the since there exists five overall families in this example, the total
productivity of crew c assigned to deal with material m associated number of possible combinations for elements making up the
with activity i. OTd denotes the turnaround time between the project is given as 25 ¼ 32. As a result, 32 values for scf , indicating
breaking of ground and occupancy of the building constructed the score associated with each family, and summed over all the
using each of the construction methods. elements making up a design combination, are computed and
Set X is formed as follows: contrasted.
n o The lower portion of Fig. 6B considers the impact of the joint
X ¼ ði; cÞ : i2Ad ; dεY; c2C; db : ðb; iÞ2L∧ðb; cÞ2C interaction of elements on the resulting aesthetics of the building,
denoted as isf ;f 0 , where f and f ’ are two separate elements from
While the set W is formed as follows: different families. This joint impact is modelled via the use of a
W ¼ fði; mÞ : i2Ad ; dεY; m2M; db : ðb; iÞ2L∧ðb; mÞ2Mg with b preference matrix, where the Coherence, Complexity, Legibility and
being the building element extracted from the BIM file. Mystery of the resulting design due to joint contribution of selected
All the above sets are generated via use of the Algorithm 1. elements from each family, are assessed (Kaplan and Kaplan, 1989).
The cost of each construction method is derived using the The resulting matrix contains 10 rows and columns for each
following equation, Eq. (6): element within the family, labelled from f1 to f10, as displayed in
X X X Fig. 6B. Again, the scores given in the matrix are based on a Likert
costd ¼ km c
i;d þ ki;d (6) scale, and are summed up to give the second term of the equation
PP
i2A c2C: m2M used to calculate the aesthetics parameter, isf ;f 0 .
ði;cÞ2X ði;mÞ2W In Fig. 6C, the computation of the waste levelf 0 f parameter, shown

in the bottom row of Fig. 6A, is demonstrated. The framework of


where km c
i;d and ki;d refer to the cost of material procurement of ac- Fig. 1 is extended such that the material waste dataset, shown in
tivity i belonging to construction method d, and the cost of crew c Fig. 6C, is added. Algorithm 1 of Fig. 2 needs to be slightly adjusted to
assigned to activity i belonging to construction method d, account for the mapping between the material waste database and:
respectively. i) the activities set L; and 2) material set M. The total material
The productivity associated with each activity, as a function of consumed by activity l, cml , is derived from the BIM file using Al-
time and monetary cost, can be calculated once the materials and gorithm 1, and this is then multiplied by the waste rate, wm , for each
crew size are linked with the elements of BIM. It is important to material involved. When summed over all materials associated
note that both time and cost of the two construction methods with each activity, the result is the total waste produced by the
PP
contrasted depend directly on the precedence network adopted in assessed construction method, wm cml .
m l
each method. It is important to note that the proposed framework relies on
quantifying the impacts that each assessed construction method
5. Framework extension will have on the sustainability factors embedded in the framework.
Any qualitative factor that is desired to be embedded needs to
The framework and Algorithm 1, presented in Figs. 1 and 2 somehow be quantified (see for instance quantification of aes-
respectively, can be extended to encompass a broader number of thetics in Fig. 6B, and quantification of waste level in Fig. 6C).
sustainability factors, subject to the availability of associated da-
tabases to allow for quantifying the respective factors. In order to 6. Case study
demonstrate how the extension can be made possible, an example
is presented in Fig. 6. The aesthetics of a given building is of interest, Two case studies are examined to demonstrate the applicability
as a social factor, along with the total level of waste produced, as an of the developed framework. The first case study, Case A, is related
environmental factor (See upper and bottom rows in Fig. 6A). The to the construction of a granny flat in Sydney, Australia. The floor
supporting database column in Fig. 6A indicates the additional in- plan of the design of the granny flat is displayed in Fig. 7A. The
formation that needs to be inserted in the framework of Fig. 1, while second case study, Case B, is a public school, comprised of a 3-storey
the Link Creation column highlights the minor adjustment that building, located in the Central Coast, Australia (Fig. 7B). The choice
needs to be carried out on Algorithm 1 presented in Fig. 2. All of the case projects is made as both project types lend themselves
symbols and notations adopted are the same as the ones defined effectively to the construction methods being contrasted. Projects
above; new notation will be defined herein. similar to both case studies have been previously built in Australia
Starting with the aesthetics parameter, Fig. 6B gives the pro- using both construction methods. The aim in the analysis presented
cedure that would be adopted to quantify the attractiveness of the is to display the validity of the developed framework in comparing
building design. A total of five building component families are construction methods across the dimensions of sustainability
utilised in the example to assess the aesthetics parameter in a modelled in this study, and in the selection of a method that is
building design, namely Façade, Windows, Walls, Ceilings and appropriate across all measures assessed.
Columns. For brevity purposes only two elements for each family
are displayed for each construction method assessed in Fig. 6B. 6.1. Project description
After extracting the relevant supporting databases, comprised of
families of the project from the BIM file, and as indicated in the top The total floor area of Case A is 63m2 (8:7 m x 7:2 m). Each storey
portion in Fig. 6A, the quantification of the attractiveness level in Case B has a floor area of 740 m2 , with each storey height set at
associated with an element that composes the building project 4m. When adopting modular construction, the granny flat is
ensues. This quantification can be achieved via a survey conducted designed from 2 modules; each module is 3:6 m x 8:7 m. For the
on a representative sample of relevance to the decision-making school, a total of 54 modules are designed corresponding to 7 main
process; the survey in the example presented is based on a Likert school departments, each with 4 classes; each module is designed
scale from 1 to 7, where a value of 7 is given to the element of to have a length dimension of 3:6 m and a width of 4:2 m. Table 2
highest attractiveness. The top portion of Fig. 6B indicates the value reports the material quantities associated with each building, as
of attractiveness beneath each element considered in bold. Since a quarried from their respective BIM files.
total of two elements are considered for each family group, and The structural design of both case studies satisfy the Australian
1272 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

Fig. 6. Example of how framework can be extended to cover additional factors: A) logical steps to adopt B) example of social computation C) example of environmental
computation.
A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1273

Fig. 7. Floor plans of case studies considered Case A) granny flat; Case B) school.

National Construction Code (Australian Institute of Building, 2016) maker's requirements; the adopted division in this study is only for
and the Australian standards for Concrete: AS3600, (Standards demonstration purposes.
Australia, 2009), Steel: AS4100, (Standards Australia, 1998), Timber: The linked library created via Algorithm 1, which associates the
AS 1720.1 (Standards Australia, 2010b) and Masonry: AS3700 construction activities of each construction method, with the ma-
(Standards Australia, 2011). The structural design of the modular terial database and the crews required, is displayed in Table 3.
components in modular construction also satisfy the Australian It is important to note that the data in Table 3 is designed to
Cold-formed Steel Standard: AS 4600 (Standards Australia, 2005). reflect common building practices in Australia for both construc-
The brevity of the discussion presented herein is maintained by tion methods being contrasted. The developed framework can be
doing the following: utilised in regions outside Australia where varying equipment and
materials are handled, with minimal adjustments required. Mate-
i) The building elements within the BIM file are grouped into 4 rial consumption will be impacted by the productivity of workers;
major categories, namely Foundations, Flooring Structures, in this study, the productivity rates specified in RS Means
Frame and Roof. (RSMeans, 2017) are adopted. The framework can be expanded to
ii) The stages of the work schedule for both construction methods account for other sustainability factors that have not been reported
are defined so that the most influential activities are included in in this study, via the integration of suitable libraries in Algorithm 1.
the analysis, Fig. 8. Differences exist between the stages within a
given construction method. For conventional construction, 6.2. Structural design considerations
when the granny flat is constructed (Fig. 8A), Stage 1 relates to
site preparation and foundation construction, Stage 2 is associ- The floor system in Case A is assumed to be non-roof load area,
ated with the slab on grade construction, Stage 3 is the brick since the walls are not load bearing. For Case B, the floor system is
work and framing required for external building envelope, along assumed to be roof load area since the floors are supporting the
with interior partitions, while Stage 4 is related to the roof and combined roof, wall and floor loads within the structure. A struc-
internal finishes. tural system of portal beams and columns is non-existent in the
granny flat when modular construction is adopted since the
For the school, where conventional construction is adopted structure dead loads are not significant. In terms of the school
(Fig. 8B), Stage 1 relates to site preparation and foundation again, design, the modules are supported via a steel frame consisting of
Stage 2 relates to ground floor construction and 1st floor columns, 200 mm  90 mm Parallel Flange Channel (PFC) beams and portal
Stage 3 is associated with the 2nd floor construction, while Stage 4 beams, along with 75 mm  75 mm square hollow section (SHS)
defines the period for construction of the top level forming the roof columns.
structure of the building, along with the internal finishes
associated.
In the case of modular construction (Fig. 8C), Stage 1 is the 6.3. Sustainability analysis
excavation work required on-site, the rolling of cold-formed steel
and the welding of the building chassis. Stage 2 involves the as- In this section, the sustainable analysis conducted on the case
sembly of the frame using the cold-formed steel. Stage 3 is the studies is described. The collected data from both Case A and Case B
transportation of the hot rolled steel and assembled cold-formed pertains to the analysis that is required to be performed within the
steel to the assembly points. Stage 4 involves the assembly of ele- developed framework. As such, the data was grouped according to
ments into modules. Services, including the mechanical and the sustainability dimension considered.
plumbing rough-ins along with the finishes are considered in Stage A precise explanation of the analysis conducted for each of the
5. sustainability parameters is given in the following subsections.
Note that the above division of stages for each construction
method can be organised into as many stages to suit the decision 6.3.1. Social analysis
The results of the social analysis are targeted towards
1274 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

quantifying the workers injury risks along with the noise disrup-

Roof Battens ¼ 140 m

Roof battens ¼ 692 m


tion caused by both construction methods. The injury risk analysis

Insulation ¼ 19.5 m3

Roof sheet ¼ 740 m2


Roof battens ¼ 51 m
Insulation ¼ 140 m3

Insulation ¼ 555 m3
Roof joists ¼ 163 m

Roof sheet ¼ 64 m2

Roof frame 75 mm
Concrete ¼ 108 m3 Concrete ¼ 222 m3

Insulation ¼ 33 m3
Roof tiles ¼ 65 m2

light steel ¼ 30 m
is conducted via adoption of fuzzy set theory after consultation

Flashing ¼ 210 m
Screed ¼ 444 m3

Flashing ¼ 30 m
with the contractors involved on each case study, while the noise
pollution during the construction process is calculated based on
common noise levels of equipment utilised in the construction of
Roof

both case studies. This is detailed below.

6.4. Injury risks


Concrete ¼ 135 m3 Steel ¼ 11 t

Table 4 displays the injury risks, in terms of hazards to workers,


associated with the activities in each construction method, while
Stair

n/a

n/a

Fig. 9 displays a chart highlighting the average safety hazards


associated with each activity in each construction method for both

200PFC ¼ 144 m
140PFC ¼ 288 m
cases considered. The values in Fig. 9 are obtained through the de-
Beam System

Steel ¼ 14.5 t

fuzzification approach highlighted earlier (see Eq. (1)).


(0.3  0.6)

As can be seen from Fig. 9, for both the case studies, the results
indicate a considerably lower risk of injury in modular construc-
n/a

Light gauge steel frame n/a

tion, compared to conventional construction. For Case A, the ac-


Vapour barrier ¼ 96 m2

tivities associated with modular construction are on average 25%


Insulation Type 1 ¼ 96

10 mm CFC ¼ 4000 m2
Plasterboard ¼ 96 m2

10 mm CFC ¼ 400 m3

less hazardous to workers compared to those of conventional


6 mm internal PVC
Masonry ¼ 270 m3 450  450 ¼ 40 þ 40þ40 ¼ 120 columns Insulation Type 4
Timber ¼ 96 m2

construction. For Case B, modular construction is 40% less hazard-


Vapour barrier

Plasterboard ¼
studs ¼ 10.3 m

lining ¼ 72 m2
Internal Walls

Steel ¼ 286 m
90 mm Light

ous, suggesting an increase in benefits of modular construction in


terms of safety risk mitigation with an increase in the size of the
project. This high safety level associated with modular construction
m2

is attributed to the controlled environment in which the activities


are conducted, permitting for better risk identification and miti-
gation (Lawson et al., 2011).
The results show that for a given construction method, Case A is
always associated with a lower risk level, in comparison to Case B.
Reinforced concrete columns

The construction process involved in a large project, such as the one


*PFC: Parallel Flange Channel; CFC: Compressed fibre cement; SHS: Square Hollow Section; PVC: Polyvinyl chloride.

in Case B, is likely to be associated with more activities that are


prone to a greater level of risk due to the shear amount of work
75  75 SHS ¼ 312 m
Formwork ¼ 900 m3

involved. For conventional construction, Case A is 36% less risky


compared to Case B, while for modular construction, the risk
Steel ¼ 12 t

associated with Case A is 19% lower relative to that associated with


Columns

Case B.
Insulation ¼ 990 m3 98 m3
n/a

n/a

6.5. Noise
Bricks ¼ 220 m3

75SHS ¼ 216 m
Bricks ¼ 25 m3
External Walls

To determine the noise pollution associated with each con-


Steel ¼ 556 m
75 mm Light

90 mm Light
110PFC ¼ 48

Steel ¼ 56 m

struction method, the resultant LAeq at 10 m for equipment


involved in the corresponding methods are obtained from common
construction noise databases and standards (Standards Australia,
2010a). These are given in Table 5.
It is important to note that the noise calculation is performed on
Flooring Structure (plus

Purlin C181 ¼ 2673 m

the actual construction site; in the case of modular construction,


Formwork ¼ 200 m2 Formwork ¼ 2525 m2

C115 Purlin ¼ 115 m


chassis for modular)

Concrete ¼ 444 m3

this will be the location where the building is erected, and not the
Formwork ¼ 7 m2
Concrete ¼ 36 m3

380PFC ¼ 810 m
Formwork ¼ 1.5 m2 400 PFC ¼ 52 m

400 PFC ¼ 52 m
200PFC ¼ 63 m

factory in which the modules are produced. The durations in Table 5


Formwork ¼ 2.5 m2 Steel ¼ 0.7 t

Steel ¼ 31 t

are a representative of the average working hours of the respective


Material associated with each construction method.

equipment involved in the activities of each construction method,


as specified by the contractors involved in Case A and Case B. Total
noise pollution is calculated over a duration of 8 h (i.e. T ¼ 8 in Eq.
Formwork ¼ 87 m2

(2)).
Bitumen ¼ 740 m2

Concrete ¼ 0.6 m3
Concrete ¼ 45 m3

Concrete ¼ 25 m3
Bitumen ¼ 13 m2

Bitumen ¼ 93 m2
Concrete ¼ 1 m3

Bitumen ¼ 6 m2

When calculating the resultant noise levels using Eq. (2), a fixed
Steel ¼ 0.130 t

Steel ¼ 0.642 t
Steel ¼ 3.85 t

Steel ¼ 0.04 t
Construction Case Foundation

distance of 30 m is assumed between the noise sources and the


closest sensitive receiver external to the project (i.e. school or
hospital). A total of 4 receivers are assumed to be located on each
side of the site in which construction is taking place.
The results of Fig. 10 show a noticeable reduction in the
Conventional A

A
B

magnitude of the highest level of noise at sensitive receivers


through adoption of modular construction in place of conventional
Modular
Method

construction (72 dB (A) vs 78 dB (A)). This can be attributed to the


Table 2

fact that in conventional construction a majority of construction


work is performed onsite, whereas most of the activities involved in
A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1275

Fig. 8. Construction stages in A) conventional granny flat; B) conventional school; C) modular construction.

modular construction are performed off-site, with minimal work contrasted construction methods are due to variances in the ma-
required on site. Due to completion of most modular construction terials used for the external envelope in both building methods. In
activities in enclosed off-site factories, noise disruption on-site due cases where the choice of modular construction does not result in
to modular construction is expected to be less than that generated changes in the type of the material used for the exterior walls, no or
by conventional methods. Project size contributes to the total noise minimal differences in terms of operational energy implications are
produced during the construction process. This is evident from expected between modular and conventional construction.
Fig. 10 in that the average noise levels in Case A are always lower
than those in Case B irrespective of the construction method
adopted. 6.7. Construction energy

The energy utilised by each construction method for construc-


6.5.1. Environmental analysis
tion of Case A and Case B at each stage, is given in Table 7. As can be
In this section, the details of the environmental analysis con-
seen, across all stages of construction (see Fig. 8), adopting modular
ducted on the case studies are described.
construction reduces construction energy by 56% and 31% for Case A
and Case B, respectively.
6.6. Energy efficiency The energy rates calculated in Table 7 are obtained based on fuel
and electricity consumption rates of equipment listed in Table 3, as
Table 6 shows the U-values associated with both construction obtained from RS Means. The rates are then multiplied by the
methods. As can be seen, the U-values of the walls and roofs for the duration of the project, obtained from the project schedule, to get
conventional construction method in both buildings are lower than the overall amount of energy use in with the construction phase of
those associated with buildings constructed using modular con- each construction method. Within conventional construction op-
struction. This is due to the higher thermal efficiency of both the erations, diesel consumption was highest during the excavation
bricks and the roof tiles adopted in the wall composition and roofs and concrete pouring stages. The concrete pump adopted in the
of the conventional building respectively, in comparison to the projects consumes 1.1 L of diesel for every 1 m3 of concrete deliv-
building envelope materials adopted in the modular construction ered. It is important to note that these rates may vary depending on
method. The difference is not that significant; the U-values of the the size and amount of work involved in the project case being
modular-constructed building can be modified to match con- examined. In terms of modular construction, electricity use was
structions using the conventional method through use of insulating highest for the cold forming process and during the handling of
material with a higher R-value (Su, 2017). It should be noted that materials and building elements within the factory, via the over-
the differences observed in the U-values resulting from the head cranes.
1276 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

Table 3
Library generated via Algorithm 1.

Construction Activities Construction Material Equipment Human Resources


Method

Conventional Excavation Backfill Hydraulic excavator; Compactor excavator Operator


Brick Laying (exterior wall) Brick Grout pump 1-3 Bricklayer
Formwork Timber Crane (tower or mobile); Club hammer; electric 1-3 Carpenter; 1 Equipment
Saw; drill operator
Concreting Concrete; Steel On-site crane; concrete pump; concrete mixer; gas 1-3 Cement finisher; 1e3
engine vibrator; disc cutter Labourer; 1e3 Rodman
Wall framing (interior) Timber; Fibre-glass insulation Crane (tower or mobile) 1-3 Carpenter; 1 Equipment
operator
Floor framing Timber Crane (tower or mobile) 1-2 Carpenter; 1 Equipment
operator
Roof framing Timber; Fibre-glass insulation Crane (tower or mobile) 1-3 Carpenter; 1e3 Roofer; 1
Equipment operator
Mechanical and electrical rough Electrical wiring, PVC pipes; Metal e 1-3 Plumber; 1e3 Labourer
in and services ducts
Interior Finishes Plasterboard; Paint; Tiles e 1-3 Painter; 1e3 Tiler; 1e3
Carpenter
Modular Set up perimeter chassis for Steel, Paint Paint sprayer; Welder, Gas Engine; Sandblaster 1-2 Welder; 1e2 Steel painter; 1
building e3 Labourer
Floor framing Cold-formed Steel Cold-rolling machine; Overhead crane; Club 1-3 Carpenter; 1e3 Labourer
hammer; Drill
Wall framing Cold-formed Steel; Fibre-glass Cold-rolling machine; Overhead crane; Club 1-3 Carpenter; 1e3 Labourer
insulation hammer; Drill
Roof framing Cold-formed Steel; steel mesh; Cold-rolling machine; Overhead crane; Club 1-3 Carpenter; 1e3 Roofer; 1e3
Fibre-glass insulation hammer; Drill Labourer
Mechanical and electrical rough Electrical wiring, PVC pipes; Metal e 1-3 Plumber; 1e2 Labourer
in and services ducts
Interior Finishes Plasterboard; Paint; Tiles; PVC e 1-3 Painter; 1e3 Tiler; 1e3
lining Carpenter
Set up Foundations Concrete, Steel Concrete pump; Concrete mixer; Gas engine 1-3 Labourer
vibrator
Transport modules to site e 13.5 m Flatbed truck 1 Operator; 1e3 Labourer
Assemble building e Crane (mobile or tower) 1 Operator; 1e3 Labourer

Table 4
Injury risk to workers associated with each activity in each construction method.

Construction Method Activities Case A Case B

Conventional Excavation (3, 3.75, 3.75, 4.5) (4, 4.5, 5, 5)


Brick Laying (exterior wall) (0.5, 1.25, 1.25, 2) (1.5, 2.5, 2.5, 3.5)
Formwork (0.5, 1.25, 1.25, 2) (1.5, 2.5, 2.5, 3.5)
Concreting (1.5, 2.5, 2.5, 3.5) (3, 3.75, 3.75, 4.5)
Wall framing (interior) (0.5, 1.25, 1.25, 2) (1.5, 2.5, 2.5, 3.5)
Floor framing (1.5, 2.5, 2.5, 3.5) (3, 3.75, 3.75, 4.5)
Roof framing (3, 3.75, 3.75, 4.5) (4, 4.5, 5, 5)
Mechanical and electrical rough in and services (0.5, 1.25, 1.25, 2) (1.5, 2.5, 2.5, 3.5)
Interior Finishes (0.5, 1.25, 1.25, 2) (1.5, 2.5, 2.5, 3.5)

Modular Set up perimeter chassis for building (3, 3.75, 3.75, 4.5) (4, 4.5, 5, 5)
Floor framing (0.5, 1.25, 1.25, 2) (0.5, 1.25, 1.25, 2)
Wall framing (0.5, 1.25, 1.25, 2) (0.5, 1.25, 1.25, 2)
Roof framing (1.5, 2.5, 2.5, 3.5) (1.5, 2.5, 2.5, 3.5)
Mechanical and electrical rough in and services (0.5, 1.25, 1.25, 2) (0.5, 1.25, 1.25, 2)
Interior Finishes (0.5, 1.25, 1.25, 2) (0.5, 1.25, 1.25, 2)
Set up Foundations (0.5, 1.25, 1.25, 2) (0.5, 1.25, 1.25, 2)
Transport modules to site (3, 3.75, 3.75, 4.5) (3, 3.75, 3.75, 4.5)
Assemble building (0.5, 1.25, 1.25, 2) (3, 3.75, 3.75, 4.5)

6.8. Material embodied energy contributor to the embodied energy of the buildings is steel (on
average at 38% contribution for conventional construction method).
Embodied energy coefficients utilised in this section are adopted This is particularly evident in the conventional construction of Case
from the Inventory of Carbon and Energy (ICE) (Hammond et al., B because the project size is relatively large and hence contains a
2008). large amount of steel reinforcement in the footings, walls and
Fig. 11 provides a comparative display between the embodied columns. For Case B when modular construction is adopted, the
energy in the conventional and modular buildings for both cases. In portal beams and frames that support the overall structure of the
particular, the figure displays the embodied energy for different building are composed of steel, hence contributing to around 17% of
materials utilised in both case studies for the two types of buildings embodied energy. In Case A, since the building is small, there is no
analysed. need for a portal structure to act as a supporting frame and hence
As can be seen, for both cases considered, the greatest the contribution of steel to embodied energy is almost zero.
A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1277

Table 7
Energy utilised during construction process, in MJ.

Stage Conventional Modular

Case A Case B Case A Case B

Stage 1 24 220 23.43 213


Stage 2 57 255 12.96 108
Stage 3 54 251 26.39 203
Stage 4 63 272 11.9 85
Stage 5 e e 11.25 75

Sum 198 998 85.93 684

Fig. 9. De-fuzzification results indicating injury risk level of each construction method.

Table 5
Equipment utilised and associated noise levels.

Construction Method Equipment Noise (LAeq @ 10 m dB(A)) Duration (hrs)

Conventional Disc Cutter 84 5


Club hammer 79 6
Electric Saw 81 5
Drill 92 4
Material Hoist 68 4

Modular Club hammer 79 3


Drill 92 2
Welding 82 5
Electric Saw 81 2

Fig. 10. Average A-weighted equivalent sound level for construction methods analysed.

Concrete, paint and brick are other materials that contribute


considerably to embodied energy of conventional construction,
Table 6 assessed to be at 19%, 13% and 12% respectively for Case A, while for
U-values associated with the building envelope in each method. Case B, the contribution is higher, measured at 20%, 14% and 13%,
respectively.
Construction Method Element Case A Case B
Fig. 12 shows the contribution to the embodied energy of the
Conventional Wall 0.25 0.35 main building elements considered in both building types for both
Roof 0.15 0.14
Modular Wall 0.35 0.35
cases. It is important to note that brick and timber are consumed
Roof 0.25 0.14 mostly by the walls and roof in conventional construction (89% and
1278 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

Fig. 11. Embodied energy in material composition of Case A and Case B.

Fig. 12. Contribution to embodied energy by element type.

71%, respectively), while reinforced concrete constitutes the wall and roof enclosures is higher than if timber were adopted. As a
flooring system (90%). In contrast, the material volume that dom- result, additional benefits, in terms of embodied energy can be
inates the modular construction method is that associated with the realised by adopting timber in place of cold-formed steel. This will
cold-formed steel, representing 67% of total material volume. come at a cost of having to deal with difficulties associated with
The results also reveal that floors contribute the greatest to the timber, including termite issues.
embodied energy in conventional construction, representing 38.5%
and 28.5% for Case A and Case B respectively; in Case B the contri-
bution is slightly lower since the concrete is also used in other el- 6.8.1. Economic analysis
ements such as the columns, beams and foundation. In this section, the time and cost required to complete the
For the modular buildings analysed in the case study, their construction of both building types examined are analysed. It is
structures are comprised of cold-formed steel; hence the use of important to note that in order to perform the cost estimate of each
timber in the modular construction of the two buildings examined construction method, some of the quantities extracted from BIM
is irrelevant. Overall, since for the case studies analysed steel stud (reported in Table 2) have been converted into a unit of measure
walls are adopted, the overall embodied energy associated with the that matches a common unit that aligns with the cost estimates.
Prices adopted are extracted from Cordell and Rawlinson
A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1279

Table 8
Cost of construction methods for Case A and Case B.

Activities Case A Total Cost (AUD$) Case B Total Cost (AUD$)

Conventional Method Excavation 7473.6 90702.17


Brick Laying 17856.2 303442.92
Formwork 2220 90775.2
Concreting 16872 689891.52
Wall framing 2880 122952
Floor framing 0 29037.6
Roof framing 5760 19358.4
Mechanical and electrical rough in and services 1204 21935.16
Interior Finishes 26964 404939.36

S 81,229.8 1,773,034.33

Modular Set up perimeter chassis for building 3588 23465.52


Floor framing 2659.6 47008.43
Wall framing 1725 12622.2
Roof framing 3264 21346.56
Mechanical and electrical rough in and services 1204 21935.16
Interior Finishes 26964 404939.36
Excavation 6920 73165.54
Transport modules to site 1200 15696
Assemble building 720 26846.7

S 48,244.6 647,025.5

Table 9
Productivity of construction methods for Case A and Case B.

Activities Case A Days to completion Case B Days to Completion

Conventional Method Excavation 5.40 30.06


Brick Laying 12.70 99.00
Formwork 3.70 69.40
Concreting 0.74 13.88
Wall framing 16.00 313.33
Floor framing 0.00 74.00
Roof framing 14.40 22.20
Mechanical and electrical rough in and services 3.04 25.43
Interior Finishes 10.00 68.89

S 65.98 716.20

Modular Set up perimeter chassis for building 0.33 1.33


Floor framing 0.18 1.91
Wall framing 0.09 0.42
Roof framing 0.17 0.66
Mechanical and electrical rough in and services 3.04 33.91
Interior Finishes 10.00 91.85
Excavation 5.00 40.08
Transport modules to site 0.50 4.00
Assemble building 2.00 45.61

S 21.31 219.78

(Cordell Commercial/industrial Building Cost Guide, 2017; cost; such an activity is not required in modular construction
Rawlinsons Australian Construction Handbook, 2017); these are method considered in the cases studied.
multiplied with the quantity of material needed during each stage Table 9 shows the productivity of each activity involved in each
of the construction process, as obtained through combining the construction method for both cases. Both on-site construction time
BIM files with the work schedules. The prices adopted also reflect and in-house fabrication time is considered in the analysis. In Case
the design work that is required for each construction method. A, the greatest time is spent on roof construction when conven-
Table 8 shows the costs of both construction methods applied to tional construction is adopted; this time is reduced by 98% by
Case A. As can be seen, the overall cost of the building using the adoption of modular construction. Overall, for Case A, a total time
modular method is 40% less than the cost expended if adopting a saving of 67.7% results when modular construction is adopted
conventional approach (AUD $48,245 vs AUD $81,230). This instead of a conventional approach. For Case B, the greatest time is
disparity between both methods is mostly the result of the spent on wall framing in conventional construction; this is reduced
expensive concrete costing used in the conventional construction by 99% in modular construction. The reason for this significant
approach. saving is due to the automated procedure that is adopted in
For Case B, the modular approach is found to be cheaper, modular factories for producing the framing of buildings. In con-
resulting in 64% less monetary cost compared to conventional ventional construction, the reliance is mostly on manual labour
construction (AUD $647,025.5 vs AUD $1,773,034). Again this is work, hence leading to large amounts of time being spent on in-
mostly due to the expensive concreting activity in conventional dividual activities. Overall, for Case B, a total time saving of 69% can
construction. The brick laying activity contributes 17% of the total be achieved if modular construction is adopted.
1280 A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281

It is important to note that the cost and productivity calculations 8. Conclusion


for each method assumes that the work is continuous without any
disruptions. For conventional construction, on rainy days, the This paper presented a framework to compare conventional and
project will be delayed since activity needs to halt. This is an issue modular construction methods, based on economic, social and
that modular construction does not face, since the working envi- environmental factors. The framework relies on the integration of
ronment is controlled inside a factory setting. BIM files, along with project schedules, material databases, and
The aim in the analysis presented is to display the validity of the crew compositions, in order to estimate the parameters for each
proposed framework in comparing construction methods across all sustainability factor considered. An algorithm was developed to
dimensions of sustainability modelled in this study, and in the se- provide a link between all databases utilised in the framework. To
lection of a method that is appropriate across all measures test the validity of the developed framework, a case study incor-
assessed. porating two different project-use types was examined. Overall, the
results of the case study indicated that adoption of modular con-
7. Insights and recommendations struction may lead to considerable benefits with regards to all
sustainability measures considered in the developed framework. In
In contrast to traditional approaches presented in the literature particular, adoption of modular construction in Case Project A and
for construction method selection, the developed framework in this Case Project B led to 4% and 8% reduction in maximum noise level,
paper enables the integration of factors that relate to all three pil- 56% and 31% reduction in operational energy use, 53% and 61%
lars of sustainability. The approach amalgamates various sustain- reduction in embodied energy, 25% and 40% reduction in risk of
ability factors, with reliance on a digital platform integrated with injury, and 40% and 63% reduction in costs of the project, respec-
automated algorithms to quantify the criteria enforced. Compared tively, when compared to adoption of conventional construction. In
to the literature, the approach developed herein incorporates line with previous research work, the reported results indicate that
automated methods. For instance, Kim (2008) utilised a life cycle modular construction has environmental and social advantages in
approach to contrast between conventional and modular con- terms of minimising pollution and risk of injury over the conven-
struction with no emphasis on the utilisation of digital platforms tional construction approach. While the projects considered in this
for information extraction, while focussing on energy and GHG study are representative of small and medium size construction
emissions. Al-Hussein et al. (2009) emphasised carbon dioxide projects, it should be noted that the results of the sustainability
emissions as the major factor for contrasting conventional and analysis reported should not be generalised to other cases.
modular construction methods. Monahan and Powell (2011) The developed approach is aimed at enabling the decision
focussed only on timber structures, whereas the approach herein maker to analyse the various sustainability factors that influence
can be used for any construction structure if suitable material da- decisions associated with the selection of an appropriate con-
tabases are embedded in the algorithm of Fig. 2. struction method. The approach does not always favour a particular
The choice between conventional and modular construction is construction method, and the yielded results would change
dependent on the specific case example examined. Based on the depending on the case examined. The developed framework is
results presented above, the framework indicates that for the case robust enough to allow changes to the databases that comprise the
analysed in this study, the modular construction method was the sustainability parameters. Adjustments can hence be made to the
better alternative in terms of minimising risk injury of workers, framework to suit the operations undergone by the firm/entity
noise pollution generated by the project, and construction energy utilising the framework as a decision support system for con-
utilised. The U-value associated with materials adopted in the struction method selection. There are some limitations of the
conventional construction method for the cases analysed was developed framework. The consideration of only two factors for
lower than that utilised in modular construction. Embodied energy each sustainability parameter, instead of focussing on a range of
was highly dependent on the exact material choice in each con- factors constitutes a limitation. With slight modification of the
struction method. Finally, in terms of the construction costs framework and algorithm presented in Figs. 1 and 2 respectively,
involved, modular construction was found to be cheaper for both additional factors can be modelled and assessed, as was demon-
building types contrasted, compared to costs involved in the con- strated in Fig. 6. Future work will also look at integrating the
ventional construction method. framework with a mathematical optimisation model in order to
As was seen in the examined case study, the use of the frame- design the buildings through dimensioning of elements along with
work can sometimes reveal that modular construction is more cost selection of appropriate material types.
effective to adopt, hence leading to increased adoption rates for
clients that are concerned with the most cost-effective construction
References
method, instead of relying on the conventional construction
approach. It is important to note that cost is project related, and so Abd El-Razek, M.E., Bassioni, H.A., Mobarak, A.M., 2008. Causes of delay in building
the cheapest construction method to select will depend on the case construction projects in Egypt. J. Constr. Eng. Manag. 134, 831e841. https://doi.
being examined. org/10.1061/(ASCE)0733-9364(2008)134:11(831).
Acil Allen Consulting, 2015. COMMERCIAL BUILDING DISCLOSURE. Department of
Utilising the presented approach enables the generation of Industry and Science.
several useful insight to decision makers when it comes to selecting Advanced Buildings, 2010. Building Envelope.
a construction method. For instance, the framework can reveal the Akbarnezhad, A., Xiao, J., 2017. Estimation and minimization of embodied carbon of
buildings: a review. Buildings 7, 5. https://doi.org/10.3390/buildings7010005.
division of energy requirements across the various stages of con- Aksamija, A., 2013. Sustainable Facades: Design Methods for High-Performance
struction for both modular and conventional construction methods. Building Envelopes. John Wiley & Sons.
Since the framework relies on a digital platform, the automation of Al-Hussein, M., Manrique, J.D., Mah, D., 2009. North Ridge CO2 Analysis Report:
Comparison between Modular and On-Site Construction. University of Alberta.
the sustainability assessment can be made easier. The framework
Albelwi, N., Kwan, A., Rezgui, Y., 2017. Using material and energy flow analysis to
can also be easily expanded to cover additional factors in each estimate future energy demand at the city level. Energy procedia. In: Interna-
sustainability parameter being assessed, if databases that capture tional Conference e Alternative and Renewable Energy Quest, AREQ 2017, 1-3
characteristics of interest are made available. This is achieved via February 2017, Spain, vol. 115, pp. 440e450. https://doi.org/10.1016/j.egypro.
2017.05.041.
the integration of a library associated with the sustainability factor Asif, M., 2016. Growth and sustainability trends in the buildings sector in the GCC
desired to be captured within Algorithm 1. region with particular reference to the KSA and UAE. Renew. Sustain. Energy
A.WA. Hammad et al. / Journal of Cleaner Production 228 (2019) 1264e1281 1281

Rev. 55, 1267e1273. https://doi.org/10.1016/j.rser.2015.05.042. global warming potential of building construction using life cycle analysis
Australian Institute of Building, 2016. Volume 1 NCC- National Construction Code. approach: case studies of residential buildings in Iskandar Malaysia. Energy
Autodesk, 2017. Dynamo. Build. 93, 295e302. https://doi.org/10.1016/j.enbuild.2014.12.002.
Autodesk Inc [WWW Document], 2018. Autodesk Revit. http://www.autodesk.com/ Kamali, M., Hewage, K., 2016. Life cycle performance of modular buildings: a critical
products/revit-family/overview. review. Renew. Sustain. Energy Rev. 62, 1171e1183. https://doi.org/10.1016/j.
Aye, L., Ngo, T., Crawford, R.H., Gammampila, R., Mendis, P., 2012. Life cycle rser.2016.05.031.
greenhouse gas emissions and energy analysis of prefabricated reusable Kamali, M., Hewage, K., 2017. Development of performance criteria for sustain-
building modules. Energy Build. 47, 159e168. https://doi.org/10.1016/j.enbuild. ability evaluation of modular versus conventional construction methods.
2011.11.049. J. Clean. Prod. 142, 3592e3606. https://doi.org/10.1016/j.jclepro.2016.10.108.
Balakrishnan, K., 1996. Exponential Distribution: Theory, Methods and Applications. Kaming, P.F., Olomolaiye, P.O., Holt, G.D., Harris, F.C., 1997. Factors influencing
CRC Press, Florida. construction time and cost overruns on high-rise projects in Indonesia. Constr.
Baldwin, A., Poon, C.-S., Shen, L.-Y., Austin, S., Wong, I., 2009. Designing out waste in Manag. Econ. 15, 83e94. https://doi.org/10.1080/014461997373132.
high-rise residential buildings: analysis of precasting methods and traditional Kaplan, R., Kaplan, S., 1989. The Experience of Nature: A Psychological Perspective.
construction. Renew. Energy, Special Issue: Building and Urban Sustainability CUP Archive.
34, 2067e2073. https://doi.org/10.1016/j.renene.2009.02.008. Kim, D., 2008. Preliminary Life Cycle Analysis of Modular and Conventional Housing
Bernstein, H.M., Gudgel, John E., Laquidara-Carr, Donna, 2011. Prefabrication and in Benton Harbor, MI.
Modularization: Increasing Productivity in the Construction Industry. National KPMG, 2016. Smart Construction: How Offsite Manufacturing Can Transform Our
Institute of Standards and Technology. Industry. KPMG.
Blismas, N., Pasquire, C., Gibb, A., 2006. Benefit evaluation for off-site production in Krausmann, F., Gingrich, S., Eisenmenger, N., Erb, K.-H., Haberl, H., Fischer-
construction. Constr. Manag. Econ. 24, 121e130. https://doi.org/10.1080/ Kowalski, M., 2009. Growth in global materials use, GDP and population during
01446190500184444. the 20th century. Ecol. Econ. 68, 2696e2705. https://doi.org/10.1016/j.ecolecon.
Chang, Y., Ries, R.J., Wang, Y., 2010. The embodied energy and environmental 2009.05.007.
emissions of construction projects in China: an economic inputeoutput LCA Lawson, R.M., Ogden, R.G., Bergin, R., 2011. Application of modular construction in
model. Energy Policy, Energy Efficiency Policies and Strategies with regular high-rise buildings. J. Archit. Eng. 18, 148e154.
papers 38, 6597e6603. https://doi.org/10.1016/j.enpol.2010.06.030. Lu, N., 2007. Investigation of Designers' and General Contractors' Perceptions of
Chen, S.-J., Hwang, C.-L., 1992. Fuzzy multiple attribute decision making methods. Offsite Construction Techniques in the United States Construction Industry.
In: Fuzzy Multiple Attribute Decision Making, Lecture Notes in Economics and Diss.
Mathematical Systems. Springer, Berlin, Heidelberg, pp. 289e486. https://doi. Mao, C., Shen, Q., Shen, L., Tang, L., 2013. Comparative study of greenhouse gas
org/10.1007/978-3-642-46768-4_5. emissions between off-site prefabrication and conventional construction
Chen, Y., Okudan, G.E., Riley, D.R., 2010a. Sustainable performance criteria for methods: two case studies of residential projects. Energy Build. 66, 165e176.
construction method selection in concrete buildings. Autom. ConStruct. 19, https://doi.org/10.1016/j.enbuild.2013.07.033.
235e244. https://doi.org/10.1016/j.autcon.2009.10.004. Monahan, J., Powell, J.C., 2011. An embodied carbon and energy analysis of modern
Chen, Y., Okudan, G.E., Riley, D.R., 2010b. Decision support for construction method methods of construction in housing: a case study using a lifecycle assessment
selection in concrete buildings: prefabrication adoption and optimization. framework. Energy Build. 43, 179e188. https://doi.org/10.1016/j.enbuild.2010.
Autom. ConStruct. 19, 665e675. https://doi.org/10.1016/j.autcon.2010.02.011. 09.005.
Cordell Commercial/industrial Building Cost Guide, 2017. Reed Construction Data, Ozcelik, M., 2016. Criteria for the selection of construction method at the ovit
Queensland. mountain tunnel (Turkey). KSCE J. Civ. Eng. 20, 1323e1328. https://doi.org/10.
DCCEE, 2012. Australia's Emissions Projections. Department of Environment, Can- 1007/s12205-015-0055-3.
berra, Australia. Pan, W., Gibb, A.G.F., Dainty, A.R.J., 2007. Perspectives of UK housebuilders on the
DEFRA, 2013. A Rationale for Waste Prevention in England. Department for Envi- use of offsite modern methods of construction. Constr. Manag. Econ. 25,
ronment, Food and Rural Affairs, London, UK. 183e194. https://doi.org/10.1080/01446190600827058.
Eastman, C.M., 2008. BIM Handbook: A Guide to Building Information Modeling for Pasquire, C.L., Connolly, G.E., 2002. Leaner construction through off-site
Owners, Managers, Designers, Engineers and Contractors. John Wiley & Sons. manufacturing. In: Proc. 11th Annual Conference, International Group for
Faludi, J., Lepech, M.D., Loisos, G., 2012. Using life cycle assessment methods to Lean Construction. Presented at the International Group for Lean Construction,
guide architectural decision-making for sustainable prefabricated modular Brazil, pp. 263e266.
buildings. J. Green Build. 7, 151e170. https://doi.org/10.3992/jgb.7.3.151. Quale, J., Eckelman, M.J., Williams, K.W., Sloditskie, G., Zimmerman, J.B., 2012.
Ficco, G., Iannetta, F., Ianniello, E., d'Ambrosio Alfano, F.R., Dell'Isola, M., 2015. U- Construction matters: comparing environmental impacts of building modular
value in situ measurement for energy diagnosis of existing buildings. Energy and conventional homes in the United States. J. Ind. Ecol. 16, 243e253. https://
Build. 104, 108e121. https://doi.org/10.1016/j.enbuild.2015.06.071. doi.org/10.1111/j.1530-9290.2011.00424.x.
Gibb, Alistair G.F., 1999. Off-site Fabrication: Prefabrication, Pre-assembly and Rawlinsons Australian Construction Handbook, 2017. Rawlinsons Publishing.
Modularisation. Wiley. Robinson, A.J., Lesage, F.J., Reilly, A., McGranaghan, G., Byrne, G., O'Hegarty, R.,
Hajkowicz, S., 2016. Prefabricated vs conventional building e which will win out? Kinnane, O., 2017. A new transient method for determining thermal properties
[WWW document]. Sourceable (accessed 10.27.17). https://sourceable.net/ of wall sections. Energy Build. 142, 139e146. https://doi.org/10.1016/j.enbuild.
prefabricated-vs-conventional-building-the-battle-for-the-future/. 2017.02.029.
Hammad, A.W.A., Akbarnezhad, A., Rey, D., 2016. A multi-objective mixed integer RSMeans, 2017. RSMeans Cost Data. John Wiley & Sons.
nonlinear programming model for construction site layout planning to mini- Smith, R.E., 2011. Prefab Architecture: A Guide to Modular Design and Construction.
mise noise pollution and transport costs. Autom. ConStruct. 61, 73e85. https:// John Wiley & Sons.
doi.org/10.1016/j.autcon.2015.10.010. Standards Australia, 1998. AS 4100 - Steel Strucutres.
Hammad, A.W., Akbarnezhad, A., Oldfield, P., 2018. Optimising embodied carbon Standards Australia, 2005. AS/NZS 4600 Cold-Formed Steel Structures.
and U-value in load bearing walls: a mathematical Bi-objective mixed integer Standards Australia, 2009. AS 3600 - Concrete Structures.
programming approach. Energy Build. https://doi.org/10.1016/j.enbuild.2018. Standards Australia, 2010a. Standards Australia 2010, Guide to Noise and Vibration
05.061. Control on Construction, Demolition and Maintenance Sites, AS2436.
Hammond, G., Jones, C., Lowrie, F., Tse, P., 2008. Inventory of Carbon & Energy: ICE. Standards Australia, 2010b. AS 1720.1 Timber Structures - Design Methods.
Sustainable Energy Research Team, Department of Mechanical Engineering, Standards Australia, 2011. AS 3700 - Masonry Structures.
University of Bath Bath. Su, B., 2017. Field studies to investigate winter indoor thermal conditions of me-
Huang, L., Bohne, R.A., 2012. Embodied air emissions in Norway's construction chanically ventilated houses with different R-value building envelopes. Int. J.
sector: input-output analysis. Build. Res. Inf. 40, 581e591. https://doi.org/10. Vent. 16, 308e322. https://doi.org/10.1080/14733315.2016.1252147.
1080/09613218.2012.711993. Thomas, D., 2007. Architecture and the Urban Environment. Routledge.
Industry Canada, 2011. Buildings. Corporate Social Responsibility. Trading Economics, 2017. Australia GDP from Construction 1974-2017 [WWW
Intergovernmental Panel on Climate Change, 2007. IPCC Fourth Assessment Report Document]. URL tradingeconomics.com/australia/gdp-from-construction
(AR4): Climate Change 2007. (accessed 12.1.17).
Islam, M.S., Nepal, M.P., Skitmore, M., Attarzadeh, M., 2017. Current research trends UN Environment and International Energy Agency, 2017. Towards a Zero-Emission,
and application areas of fuzzy and hybrid methods to the risk assessment of Efficient, and Resilient Buildings and Construction Sector, GLOBAL STATUS
construction projects. Adv. Eng. Inf. 33, 112e131. https://doi.org/10.1016/j.aei. REPORT 2017. UN.
2017.06.001. UNEP, 2009. Buildings and Climate Change e a Summary for Decision-Makers.
Jaillon, L., Poon, C.S., Chiang, Y.H., 2009. Quantifying the waste reduction potential United Nations Environmental Programme, Sustainable Buildings and Climate
of using prefabrication in building construction in Hong Kong. Waste Manag. Initiative, Paris, France.
29, 309e320. https://doi.org/10.1016/j.wasman.2008.02.015. Zhai, Y., Zhong, R.Y., Huang, G.Q., 2015. Towards operational hedging for logistics
Jeong, H., Broesicke, O.A., Drew, B., Li, D., Crittenden, J.C., 2016. Life cycle assessment uncertainty management in prefabrication construction. Ifac-pap. 15th IFAC
of low impact development technologies combined with conventional Symposium onInformation Control Problems inManufacturing 48, 1128e1133.
centralized water systems for the City of Atlanta, Georgia. Front. Environ. Sci. https://doi.org/10.1016/j.ifacol.2015.06.235.
Eng. 10, 1. https://doi.org/10.1007/s11783-016-0851-0. Zimmermann, H.-J., 2013. Fuzzy Set TheorydAnd its Applications. Springer Science
Jia Wen, T., Chin Siong, H., Noor, Z.Z., 2015. Assessment of embodied energy and & Business Media.

You might also like