Background
A review of the scope identifies three deliverables:
• Technical Specification
• Delivery Plan
• Bid Document
Assignment
1. With your OzBuild project open click on the button to open the WBS
Window.
2. Click in the WBS field header until the sort indicator is displayed as three
horizontal bars, as displayed in the picture below. The WBS will now be
displayed hierarchically now:
3. Select the Project WBS Node press the Ins key or right-click and select Add
to add the WBS Node. Then continue to add three WBS Nodes for the three
Phases above.
4. If the WBS Nodes are not indented click the WBS Code heading as
described in paragraph 2, until they are indented.
5. Use the arrows on the Move toolbar to put them in the correct order and
indent.
6. Your answer should be displayed like the following picture: