Professional Documents
Culture Documents
2 Pre- DC1 (Master Planning Approval) QF Approved Master Plan Final MP Approval
• File No.
• Copy of Approved Site Plan
• Site Plan showing the location of the plot
3 MMUP Qatar General Cleaning Project (QGCP) • Drawings showing waste disposal and collecting strategy Final CD Approval
• Waste management report
• List of contents
• Cover letter
• Application to be filled
• Approval letter of Stage-1
Qatar Civil Defence Department (Fire Alarm, Fire Fighting, ACMV) Interim DD
8 • Fire Protection drawings with calculations Drawing
– Stage 2 Workshop
• Fire Detection and Alarm drawings
• Mechanical Ventilation with Calculations
• Master Site Plan – Electrical
• Electrical Site Plan with coordinates
• Substation Plans & Sections
9 Kahramaa - Electricity -Network Planning Section Final SD Approval
• HV Schematic
• Load Summary for each Transformer
• Total Maximum Demand
Final SD Approval
• Electrical Site Plan showing the location of substations
+
10 Kahramaa - Electricity - Civil Section • Detailed Substation Plan showing all levels, clearances,
Milestone 7
trenches, doors etc.
Approval
Final SD Approval
+
11 Kahramaa Electrical Protection Approval Protection Drawings
Milestone 8
Approval
• Approved Electrical Site Plan
• Approved Substation Plan
Final SD Approval
• All MV Schematics
12 Kahramaa - Electricity - Installation Section + Milestone 9
• Main Cables/Bus Duct routing from MV Panel to other floors.
Approval
• MV Room details and Bus Riser details
• SMDB & DB Details
• Water Site Plan showing tie in point from water mains, water
meter, storage tank, water meter cabinet details, chamber and
Final SD Approval
general notes.
13 Kahramaa - Water + Milestone 7
• Water demand calculation
Approval
• Water schematic
• All floor layouts
• Qtel Site Plan showing the location of nearest QTel manhole,
incoming QTel cable routing & way up to QTel room.
14 Qtel • Drawing showing QTel room location and room size with Final SD Approval
legends and notes.
• Digital Site Plan
• Application to be filled.
• Drainage Site Plan showing connection between MH#1 to
Government manhole, drainage holding tank, storm water
holding tank & general notes.
16 Ashghal - Drainage • Drainage holding tanks & storm water holding tank details. Final SD Approval
• Schedule of manhole
• Drainage & Storm water calculations
• Schematics
• All floor layouts
• Application to be filled.
• Traffic Impact Study.
17 Ashghal - Road Approval (Civil Section) Final SD Approval
• Road Design layout.
• Related Design drawings
• Copy of the Approved Master Plan
• Land Documents
• Transportation Master Plan
Milestone 15
18 Transportation and Infrastructure Planning Department (TIPD) • Traffic Impact study
Approval
• Traffic Modeling (upon request)
• Geotechnical review report
• Cover Letter
• Land Documents
• Environmental Impact assessment (EIA) report
• Environmental Management Plan
19 Ministry of Environment (MoE) - Technical Affair Department Final SD Approval
• Scope of Work report
• Term of References
• Application form to be filled
Page 1of 2
Qatar Doha APPENDIX J
Page 2of 2