Professional Documents
Culture Documents
As Per Plan
Demolition and Restoration 0.12 0.12
I ₱ 8,736.00 0.24%
Works
Actual
As Per Plan
0.319 0.191
II Excavation Works ₱ 18,200.00 0.51%
Actual
As Per Plan
0.167 0.223
III Embankment ₱ 14,098.00 0.39%
Actual
As Per Plan
1.431 3.339 3.339 3.339 3.339 3.339 3.339 3.339
IV Concrete Works ₱ 1,575,290.70 43.89%
Actual
As Per Plan
0.932 0.932 0.932
V Masonry Works ₱ 358,636.27 9.99%
Actual
As Per Plan
0.294 0.412 0.412 0.412 0.412 0.412 0.412
VI Formworks ₱ 183,837.60 5.12%
Actual
As Per Plan
VII Roof & Roof Framing Works ₱ 385,666.65 10.74%
Actual
As Per Plan
VIII Ceiling Works ₱ 183,787.65 5.12%
Actual
As Per Plan
IX Doors And Windows ₱ 214,118.64 5.97%
Actual
As Per Plan
X Tile Works ₱ 44,398.80 1.24%
Actual
As Per Plan
0.372 0.186
XI Electrical Works ₱ 187,066.13 5.21%
Actual
As Per Plan
0.423 0.212
XII Plumbing Works ₱ 98,848.35 2.75%
Actual
As Per Plan
XIII Painting Works ₱ 181,550.40 5.06%
Actual
As Per Plan
Steel Works (Railing &
XIV ₱ 94,906.35 2.64%
Window Grills)
Actual
As Per Plan
0.15
XV Project Billboard ₱ 5,320.13 0.15%
Actual
As Per Plan
0.42
XVI Temporary Facilities ₱ 15,000.00 0.42%
Actual
As Per Plan
Occupational Safety and 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024
XVII ₱ 20,000.00 0.56%
Health Program
Actual
₱ 3,589,461.67 100.00%
% MONTHLY 0.714 1.894 4.0154 3.9984 3.7754 4.5704 5.1058 4.7078 4.7078
SCHEDULE/AS PLAN
% ACCUMULATIVE 0.714 2.608 6.6234 10.6218 14.3972 18.9676 24.0734 28.7812 33.489
% MONTHLY
ACTUAL
% ACCUMULATIVE
DECEMBER JANUARY FEBRUARY MARCH
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M T W TH F S SU M
WK.10 WK.11 WK.12 WK.13 WK.14 WK.15 WK.16 WK.17 WK.18 WK.19 WK.20 WK.21 WK.22 WK.23
0.846 1.269
0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.024 0.003
4.7078 6.2978 4.7078 4.9578 6.4558 5.3834 2.7044 2.438 3.373 7.682 6.89 6.259 3.175 1.289 0.185
38.1968 44.4946 49.2024 54.1602 60.616 65.9994 68.7038 71.1418 74.5148 82.1968 89.0868 95.3458 98.5208 99.8098 100.00
Project: Construction of Two-Storey Four-Classroom School Building
Location: San Juan Elementary School, Ramos, Tarlac
Date Started: October 14, 2019.
Project Duration: 162 C.D.
₱ 3,589,461.67 100.00%
% MONTHLY
SCHEDULE/AS PLAN
% ACCUMULATIVE
% MONTHLY
ACTUAL
% ACCUMULATIVE
OCTOBER
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
M T W TH F S SU M T W TH F S SU M T
% WT. AS OF THIS WK.1 WK.2 WK.3
DATE
As Per Plan
0.12 0.12
Actual
As Per Plan
0.319 0.191
Actual
As Per Plan
0.167
Actual
As Per Plan
1.431 3.339
Actual
As Per Plan
Actual
As Per Plan
0.294
Actual
As Per Plan
Actual
As Per Plan
Actual
As Per Plan
Actual
Actual
As Per Plan
Actual
As Per Plan
Actual
As Per Plan
Actual
As Per Plan
Actual
As Per Plan
Actual
As Per Plan
0.15
Actual
As Per Plan
0.42
Actual
As Per Plan
0.024 0.024 0.024
Actual
0.191
0.167 0.223
0.423
0.423 0.212
0.846
0.932 0.666
1.195 1.195
1.99
1.303
0.406 1.422
1.748
1.269
1.422 0.812
0.24
0.51
0.39
43.89
9.99
5.12
10.74
0.341 5.12
5.97
0.276 1.24
5.21
1.269 2.75
2.64
0.15
0.42
& WEEKLY 4.56 10.80 8.64 17.38 12.19 12.19 12.19 13.07 4.34
SCHEDULED
% CUMMULATIVE 4.56 15.36 24.01 41.39 53.58 65.77 77.96 91.03 95.38
ACCOMPLISHMENT
% WEEKLY 4.33 10.67 3.36 12.24 9.46 20.16 14.83 15.90 4.39
ACTUAL
% CUMMULATIVE 4.33 15.00 18.36 30.59 40.05 60.21 75.04 90.94 95.33
No. of Days to Complete Project : 68 CD
Prepared by :
Date of Start : 25-Oct-19
JESUS L. HIPOLITO
HIMULICO CONSTRUCTION & SUPPLY CORP.
Contractor
WEEKLY SCHEDULE
10
0.40
0.40
4.22
4.22
0.05
4.62
100.00
4.67
100.00