Professional Documents
Culture Documents
• Part 2 – Describes Order of Cost Estimate and its contents, sets out rules for
measurement and reporting
•Part 3 – Describes Elemental Cost Planning, defines its constituents and how to
prepare an elemental cost plan
•Appendices
A di
Use of RICS new rules of Measurement: Order of cost
estimating and elemental cost planning
• Represent the essentials of Good Practice
• S
Structured basis for
f measuring building work
VAT Assessment
VAT Assessment
Constituents of an order of cost
Constituent
1 Building Works estimate
2 Main Contractor's preliminaries estimate
3 Sub‐total [(3)=(1)+(2)]
Floor Area Method 4 Main Contractor's overheads and profit
Building Works estimate = 5 Works cost estimate [(5)=(3)+(4)]
Works cost estimate [(5)=(3)+(4)]
6 Project/Design team fees estimate
GIFA x cost/m² 7 Sub‐total [(7)=(5)+(6)]
Functional Unit Method 8 Other development/project costs estimate
9 Base cost estimate [(9)=(7)+(8)]
Building Works estimate = [( ) ( ( )) ( ( )) ( ( )) ( ( ))]
10 Risk allowance estimate [(10)=(10(a))+(10(b))+(10(c))+(10(d))]
N b off ffunctional
Number i l units
i x 10 (a) Design development risk estimate
10 (b) Construction risk estimate
cost per functional unit 10 (c) Employer's change risk estimate
Elemental Method 10 (d) Employer other risk estimate
11 Cost Limit (excluding inflation) [(11)=(9)+(10)]
Building Works estimate = 12 Tender Inflation Estimate
Sum of element cost targets 13 Cost Limit (excluding construction inflation) [(13)=(11)+(12)]
Cost target (for element) = 14 Construction inflation estimate
15 Cost Limit (including inflation) [(15)=(13)+(14)]
element unit quantities EUQ x
element
l t unit
it rate
t EUR VAT Assessment
VAT Assessment
Constituents of an order of cost
Constituent
1 Building Works estimate
2 Main Contractor's preliminaries estimate
3 Sub‐total [(3)=(1)+(2)]
4 Main Contractor's overheads and profit
5 Works cost estimate [(5)=(3)+(4)]
Works cost estimate [(5)=(3)+(4)]
Cost estimate for main 6 Project/Design team fees estimate
7 Sub‐total [(7)=(5)+(6)]
contractor’s preliminaries 8 Other development/project costs estimate
9 Base cost estimate [(9)=(7)+(8)]
[( ) ( ( )) ( ( )) ( ( )) ( ( ))]
10 Risk allowance estimate [(10)=(10(a))+(10(b))+(10(c))+(10(d))]
At this stage in the process is 10 (a) Design development risk estimate
expressed as a percentage of 10 (b) Construction risk estimate
10 (c) Employer's change risk estimate
the building works estimate 10 (d) Employer other risk estimate
11 Cost Limit (excluding inflation) [(11)=(9)+(10)]
12 Tender Inflation Estimate
13 Cost Limit (excluding construction inflation) [(13)=(11)+(12)]
14 Construction inflation estimate
15 Cost Limit (including inflation) [(15)=(13)+(14)]
VAT Assessment
VAT Assessment
Constituents of an order of cost
Constituent
1 Building Works estimate
2 Main Contractor's preliminaries estimate
3 Sub‐total [(3)=(1)+(2)]
4 Main Contractor's overheads and profit
5 Works cost estimate [(5)=(3)+(4)]
Works cost estimate [(5)=(3)+(4)]
6 Project/Design team fees estimate
7 Sub‐total [(7)=(5)+(6)]
Cost estimate for main 8 Other development/project costs estimate
9 Base cost estimate [(9)=(7)+(8)]
contractor’s overheads and [( ) ( ( )) ( ( )) ( ( )) ( ( ))]
10 Risk allowance estimate [(10)=(10(a))+(10(b))+(10(c))+(10(d))]
profit 10 (a) Design development risk estimate
10 (b) Construction risk estimate
10 (c) Employer's change risk estimate
At this stage in the process is 10 (d) Employer other risk estimate
11 Cost Limit (excluding inflation) [(11)=(9)+(10)]
expressed as % of sub-total
sub total 3 12 Tender Inflation Estimate
13 Cost Limit (excluding construction inflation) [(13)=(11)+(12)]
14 Construction inflation estimate
15 Cost Limit (including inflation) [(15)=(13)+(14)]
VAT Assessment
VAT Assessment
Constituents of an order of cost
Risk Allowance given more Constituent
significance at this stage. 1 Building Works estimate
2 Main Contractor's preliminaries estimate
Acknowledgement of the rise of 3 Sub‐total [(3)=(1)+(2)]
risk management within the 4 Main Contractor's overheads and profit
5 Works cost estimate [(5)=(3)+(4)]
Works cost estimate [(5)=(3)+(4)]
industry and the need to properly 6 Project/Design team fees estimate
identify, assess, monitor and 7 Sub‐total [(7)=(5)+(6)]
8 Other development/project costs estimate
control risks during the project 9 Base cost estimate [(9)=(7)+(8)]
cycle 10 [( ) ( ( )) ( ( )) ( ( )) ( ( ))]
Risk allowance estimate [(10)=(10(a))+(10(b))+(10(c))+(10(d))]
10 (a) Design development risk estimate
10 (b) Construction risk estimate
10 (c) Employer's change risk estimate
10 (d) Employer other risk estimate
11 Cost Limit (excluding inflation) [(11)=(9)+(10)]
12 Tender Inflation Estimate
13 Cost Limit (excluding construction inflation) [(13)=(11)+(12)]
14 Construction inflation estimate
15 Cost Limit (including inflation) [(15)=(13)+(14)]
VAT Assessment
VAT Assessment
Constituents of an order of cost
Tender inflation and Construction Constituent
inflation 1 Building Works estimate
2 Main Contractor's preliminaries estimate
Both expressed as a percentage 3 Sub‐total [(3)=(1)+(2)]
which can be computed using 4 Main Contractor's overheads and profit
5 Works cost estimate [(5)=(3)+(4)]
Works cost estimate [(5)=(3)+(4)]
published indices such as: 6 Project/Design team fees estimate
•Retail price index 7 Sub‐total [(7)=(5)+(6)]
8 Other development/project costs estimate
•Tender price index 9 Base cost estimate [(9)=(7)+(8)]
•Building
Building cost indices (BCIS) 10 [( ) ( ( )) ( ( )) ( ( )) ( ( ))]
Risk allowance estimate [(10)=(10(a))+(10(b))+(10(c))+(10(d))]
10 (a) Design development risk estimate
10 (b) Construction risk estimate
10 (c) Employer's change risk estimate
10 (d) Employer other risk estimate
11 Cost Limit (excluding inflation) [(11)=(9)+(10)]
12 Tender Inflation Estimate
13 Cost Limit (excluding construction inflation) [(13)=(11)+(12)]
14 Construction inflation estimate
15 Cost Limit (including inflation) [(15)=(13)+(14)]
VAT Assessment
VAT Assessment
Order of cost estimate reporting
Minimum content
a) Project Title
b) Project description
c) Statement of cost (including cost limit)
d) Details of the information and
specification on which the cost plan was
prepared
e) A statement of floor areas
f) Basis of cost estimate (i.e. assumptions)
g) Estimate base date (to which inflation
has been applied)
h) Estimated costs of and request for
decision on any alternative proposals
i) Inclusions and exclusions
Purpose of elemental cost planning
To p
provide advice to designers
g to enable a p
practical and
balanced design within budget
VAT Assessment
Constituents of an elemental cost plan
Constituent
1 Building Works estimate
2 Main Contractor's preliminaries estimate
3 Sub‐total [(3)=(1)+(2)]
4 Main Constrictor's overheads and profit
Quantities for building works 5 Works cost estimate [(5)=(3)+(4)]
6 Project/Design team fees estimate [(6=(6(a))+(6(b))+(6(c))]
j / g [( ( ( )) ( ( )) ( ( ))]
shall be determined in (a) Consultants' fees
accordance with Part (b) Main contractor's pre‐construction fee estimate (if applicable)
(c) Main Contractor's design fee estimate (if applicable)
4:Tabulated Rules of 7 Sub‐total [(7)=(5)+(6)]
8 Other development/project costs estimate
Measurement for elemental 9 Base cost estimate [(9)=(7)+(8)]
B t ti t [(9) (7)+(8)]
cost planning (i.e. group 10 Risk allowance estimate [(10)=(10(a))+(10(b))+(10(c))+(10(d))]
10 (a) Design development risk estimate
elements 1 to 9) 10 (b) Construction risk estimate
10 (c) Employer change risk estimate
10 (d) Employer other risk estimate
11 Cost Limit (excluding inflation) [(11)=(9)+(10)]
12 Tender Inflation Estimate
13 Cost Limit (excluding construction inflation) [(13)=(11)+(12)]
14 Construction inflation estimate
15 Cost Limit (including inflation) [(15)=(13)+(14)]
VAT Assessment
Group elements for estimating building works
Group Element 1 Substructure
RICS Books
ISBN: 9781842194461
Item Code: 17792
310 Pages
Paperback
Mar 2009
Price: £45.00