GCU

Project : JTR Viaduct

Shear link dia. = 16 mm


Concrete cover = 75 mm

Allowable max. clear distance b/w bars = 75 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
800 16 17 19 20
1350 31 33 36 38
1480 34 37 40 42
1500 35 38 41 43
1800 43 47 50 53
2000 49 52 56 59
2200 54 58 63 66
2500 62 67 72 76
2800 70 76 81 86
3000 76 82 88 93

Allowable max. clear distance b/w bars = 100 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 28 30 32 33
1350 25 27 29 30
1500 29 31 32 34
1800 35 38 40 42
2000 40 43 45 47
2200 44 47 50 52
2500 51 54 58 60
2800 58 62 65 68
3000 62 66 70 73

Allowable max. clear distance b/w bars = 105 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 27 29 31 32
1350 24 26 28 29
1500 28 29 31 33
1800 34 36 38 40
2000 39 41 43 45
2200 43 46 48 50
2500 49 52 55 58
2800 56 59 63 65
3000 60 64 67 70

Allowable max. clear distance b/w bars = 150 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 21 22 23 24
1350 19 20 21 21
1500 21 22 23 24
1800 26 27 29 30
2000 29 31 32 33
2200 33 34 36 37
2500 38 39 41 42
2800 43 45 47 48
3000 46 48 50 52

Allowable max. clear distance b/w bars = 200 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 16 17 18 18
1500 17 17 18 19
1800 21 21 22 23
2000 23 24 25 26
2200 26 27 28 29
2500 30 31 32 33
2800 34 35 36 37
3000 36 38 39 40

file:///conversion/tmp/scratch/469873551.xlsx 04/13/2020
GCU
Project : JTR Viaduct

Shear link dia. = 12 mm


Concrete cover = 75 mm

Allowable max. clear distance b/w bars = 75 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
800 16 17 19 20
1350 31 34 36 38
1480 35 37 40 43
1500 35 38 41 43
1800 43 47 50 53
2000 49 53 57 60
2200 54 59 63 66
2500 62 67 72 76
2800 71 76 82 86
3000 76 82 88 93

Allowable max. clear distance b/w bars = 100 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 28 30 32 34
1500 29 31 33 34
1800 36 38 40 42
2000 40 43 45 47
2200 45 47 50 53
2500 51 55 58 60
2800 58 62 65 68
3000 63 66 70 73

Allowable max. clear distance b/w bars = 120 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 25 26 28 29
1500 25 27 28 29
1800 31 33 35 36
2000 35 37 39 41
2200 39 41 43 45
2500 45 47 50 52
2800 51 54 56 58
3000 55 58 61 63

Allowable max. clear distance b/w bars = 150 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 21 22 23 24
1500 21 22 23 24
1800 26 28 29 30
2000 30 31 32 33
2200 33 34 36 37
2500 38 40 41 43
2800 43 45 47 48
3000 46 48 50 52

Allowable max. clear distance b/w bars = 200 mm (subject to crack width check)

Pile diameter Minimum Outer Row Rebars


(mm) 40 32 25 20
1480 17 17 18 18
1500 17 18 18 19
1800 21 22 22 23
2000 23 24 25 26
2200 26 27 28 29
2500 30 31 32 33
2800 34 35 36 37
3000 36 38 39 40