REPORT ON
SUBMITTED BY
RAVI JAIN
1226109240
TO
Prof. V.L.RAO
The total installed capacity in India is 150000MW but we are facing a power deficit of
around 10%. The per capita power consumption is 665 kWh and this figure is steadily
increasing. To meet this increasing demand and reduce the current peak shortage, the
Government has planned to double the existing capacity to 3,00,000MW over the next
decade (2010-20).
India has a biomass availability of 150 million MT per annum which gives us a potential to
install 16,000MW of biomass based power plants. But only 600MW is installed and another
600MW is under implementation. To realise this huge potential we need an investment of
Rs.1,00,000 crore.
It costs around Rs.6cr/MW for a Biomass plant whereas a thermal plant requires only
about Rs.4.5cr/MW.
Availability of Biomass fuel with high calorific value (> 4000kcal/kg)
PROMOTIONAL INCENTIVES
BIOMASS CULTIVATION
Low productivity of 5 T/Hectare
Biomass cultivation over 11 million Hectares of wasteland can generate a total of 12
million direct and indirect jobs and a revenue of over Rs. 20,000 crore.
Oil content of Jatropha seeds should be increased from 33% to 50%
MAJOR COMPANIES
PRIVATE SECTOR
Clenergen Power Corporation Limited – 64 MW + 16 MW worth Rs. 1,135 crore
Oriental Green Power – 8 X 8 MW worth Rs. 730 crore
Astonfield-Areva Power – 100 MW worth Rs. 630 crore
PUBLIC SECTOR
Indian Renewable Energy Development Association (IREDA) – 250 MW
1. INDIA’S POWER SCENARIO – INTRODUCTION
2.9
7.7
Coal
Gas
24.7 Oil
53.3 Hydro
Nuclear
Renewa ble
0.9 10.5
Usage
22.9 24.8
Domestic
Industrial
Commercial
8.1
Agricultural
35.6
1.1 GROWTH OF THE SECTOR POST-INDEPENDENCE
2. SUPPLY-DEMAND GAP
There appears to be no solution in sight for the prolonged and worsening power crisis facing
the country with continuing slippages in capacity addition targets, unacceptably high levels
of transmission and distribution (T&D) losses, power thefts and rampant corruption.
The growing scarcity, poor quality and high cost of power with frequent outages is an issue
of great concern at a time when serious efforts are being made to put the economy back on
a higher growth trajectory.
With mounting power deficits, many States are facing a crisis situation. While the overall
demand-supply gap averages around 12-14%, 10 out of 28 States have a deficit of more
than 20%. The peak level power deficits are much higher.
India Inc. lost Rs 43,205 crore during 2008-09 due to high outages of power, both scheduled
and non-scheduled. Such direct losses had more than doubled since 2003 when these were
estimated at Rs 22,000 crore. The opportunity cost of power shortages in the last financial
year has amounted to Rs 2,89,000 crore or a 6 per cent loss in GDP terms.
Indians are forced to spend around Rs 30,000 crore every year on inverters and generators
because of widespread power shortages and load shedding. Residential and commercial
users in India have so far spent about Rs 1 lakh crore on buying invertors and generators;
this amount could have helped build new generating capacity of nearly 30,000 MW.
The deteriorating power supply situation is not only because of the big slippages in capacity
addition targets in successive Five Year Plans but also because of whopping T&D losses.
While the country’s installed capacity for power generation now is 1,51,073 MW, only about
96,000 MW is available for actual consumption due mostly to these losses and power thefts.
3. BIOMASS POWER SECTOR
The key drivers for Biomass energy in India are the following:
The demand-supply gap, especially as population increases
A large untapped potential
Concern for the environment
The need to strengthen India’s energy security
Pressure on high-emission industry sectors from their shareholders
A viable solution for rural electrification
Also, with a commitment to rural electrification, the Ministry of Power has accelerated the
Rural Electrification Program with a target of 100,000 villages by 2012.
The Ministry of Power has set an agenda of providing Power to All by 2012. It seeks to
achieve this objective through a comprehensive and holistic approach to power sector
development envisaging a six level intervention strategy at the National, State, SEB,
Distribution, Feeder and Consumer levels.
The straw of cereals and pulses, stalks and seed coats of oil seeds, stalks and sticks of fibre crops,
pulp and wastes of plantation crops, peelings, pulp and stalks of fruits and vegetables and other
wastes like sugarcane trash, rice husk, molasses, coconut shells etc. comes under this category.
Most of the crop residues have a higher ash content and mainly constitutes carbon, oxygen and
hydrogen. Volatile matter content is 60-75%. The agricultural residues are hygroscopic in nature.
Ash content varies from 0.5 to 2.8 per cent.
B. Industrial wastes
These wastes include wastes from paper mills, chemical mills etc. for eg., paper wastes, plastic
wastes, textile wastes, gas, oil, paraffins, cotton seeds and fibres, bagasse etc. Plastic and rubber
wastes have good calorific value.
C. Forest wastes
Logs, chips bark and leaves together constitute forest wastes. Sawdust is the forest based industry
waste. Forest products are also used as a. domestic fuel in many developing countries.
D. Logging residues
Tree tops, small stems and roots removed from a standard logging operation and broken debris
generally considered as logging residues. It contains 40-50% moisture, 50% carbon, 40% oxygen
and nitrogen 5%.
Bark, knots, sawdust etc. are obtained from wood product industry. Moisture content of these
residues is around 20% with 67% volatile matter and 11 % organic carbon.
The bark and black liquor produced in pulp and paper factories can be used as major source of
energy in the paper industry. Moisture content varies from 5-10% with organic. carbon 8-11 per
cent.
Generally municipal solid wastes refer to a mixture of domestic, small construction and demolition
wastes left out within a community. Composition of municipal solid wastes is given in the Figure. It
shows the heterogenic nature of these waste mixtures.
Percentage (weight)
10.7 1 Paper
2 Metals
41
24 3 Glass, Stones, Ceramics
4 Plastic, rubber
5 Garbage, yard wastes
6 Miscellaneous
4.9 11.2 8.2
H. Municipal sewage sludge
The sludge contains 95% water, and 5% organic matter and nutrients as the main constituents.
These can be utilized for the production of methane through anaerobic digestion.
I. Animal wastes
The moisture content of the manures ranges from 60 to 85 percent. The nitrogen varies from 0.3
to 0.9 %, phosphorus 0.05-0.1 % and potassium 0.12 to 0.8% Available statistics indicates
production of 1300 million tonnes of dung annually from all types of animals. Of the total
produced, 84% is of cow and buffalo dung and 13% goat and sheep droppings. Dung is used as a
fuel in the form of cakes and biogas.
Availability of biomass resources in India along with their coal equivalent is shown in Table .
Technological advancement in biomass energy is derived from two spheres - biomass energy
production practices and energy conversion technologies. A rich experience of managing
commercial energy plantations in varied climatic conditions has emerged during the past
two decades. Improvements in soil preparation, planting, cultivation methods, species
matching, bio-genetics and pest, disease and fire control have led to enhanced yields.
Development of improved harvesting and post harvesting technologies has also contributed
to reduction in production cost of biomass energy. Technological advancements in biomass
energy conversion comes from three sources - enhanced efficiency of biomass energy
conversion technologies, improved fuel processing technologies and enhanced efficiency of
end-use technologies. Versatility of modern biomass technologies to use variety of biomass
feedstock has enhanced the supply potential. Small economic size and co-firing with other
fuels has also opened up additional application.
For electricity generation, two most competitive technologies are direct combustion and
gasification. Typical plant sizes at present range from 0.1 to 50 MW. Co-generation
applications are very efficient and economical. Fluidized bed combustion (FBC) is efficient
and flexible in accepting varied types of fuels. Gasifiers first convert solid biomass into
gaseous fuels which is then used through a steam cycle or directly through gas
turbine/engine.
Gas turbines are commercially available in sizes ranging from 20 to 50 MW. Technology
development indicates that a 40 MW combined cycle gasification plant with efficiency of 42
percent is feasible at a capital cost of 1.7 million US dollars with electricity generation costs
of 4 cents/ KWh.
3.3 MODERN BIOMASS TECHNOLOGY IN INDIA: EXPERIENCES
A decade of experience with modern biomass technologies for thermal, motive power and
electricity generation applications exists in India. Gasifier technology has penetrated the
applications such as village electrification, captive power generation and process heat
generation in industries producing biomass waste.
Four gasifier Action Research Centers (ARCs) located within different national institutions
and supported by the MNES have developed twelve gasifier models, ranging from 3.5 to 100
KW. Two co-generation projects (3 MW surplus power capacities) in sugar mills and one rice
paddy straw based power project (10 MW) were commissioned. While the co-generation
projects are successfully operated, the 10 MW rice straw based power project completed in
1992 ran into technological problems and is closed since last two years due to want of
suitable raw material.
A rice husk based co-generation plant of 10.5 MW capacity installed by a private rice
processing firm in Punjab and commissioned in 1991 faced problems such as unavailability
of critical spares of an imported turbine and uneconomical tariffs from the state utility
despite power shortage in the state. The rapid escalation in the price of rice husk and low
capacity utilization added to the cost making the operation uneconomical.
3.5 LARGE SCALE ELECTRICITY GENERATION PROGRAMMES
The future of modern biomass power programme rests on its competitive ability vis-à-vis
other centralized electricity generation technologies. The biomass electricity programme
took shape after MNES appointed the task force in 1993 and recommended the thrust on
bagasse based co-generation.
Programme for biomass combustion based power has even more recent origin. It began in
late 1994 as a Pilot Programme launched with approval of two 5 MW projects. Interest
subsidy programmes on the lines of that for the bagasse based co-generation was extended
in 1995. The programme also initiated a grid connected biomass gasification R&D-cum-
Demonstration project of 500 Kilo Watt (KW) capacity. A decentralized electricity generation
programme initiated in 1995 provided support for total of 10 to 15 MW of small
decentralized projects aimed at energy self sufficiency in electricity deficient rural locales.
Modern biomass supply has to be driven by the dynamics of energy market. Supply of
biomass at a competitive cost can be ensured only with a highly efficient biomass
production system. Productivity of crops and trees depend critically on agro-climatic factors.
To enhance biomass productivity, the Ministry for New and Renewable Energy (MNES) is
supporting nine Biomass Research Centers (BRCs) in nine (of the fourteen) different agro-
climatic zones in India with an aim to develop packages of practices of fast growing, high
yielding and short rotation (5-6 years) fuelwood tree species for the degraded waste lands in
these zones. Some centers have existed for over a decade.
Packages of practices for 36 promising species are prepared. Biomass yield of up to 36.8
tons per hectare per year is reported from some promising fuel-wood species.
Since the knowledge of these package of practices has remained limited within the research
circles, their benefits remains to be realized. The mean productivity of farm forestry
nationally is very low at 4.2 tons per hectare per year. Exploitation of bioenergy potential is
vitally linked to the adequate land supply. While the use of cultivable crop land for fuel
remains controversial under the "food versus fuel" debate, there exists a vast supply of
degraded land which is available cheaply for fuel-wood plantations. The estimates of
degraded land vary from 66 million hectares (Ministry of Agriculture, 1992) to 130 million
hectares (SPDW, 1984). With improved biomass productivity and efficient energy
conversion, it is feasible to sustain a significant share of biomass in total energy use in India
by utilizing a fraction of this degraded land for biomass plantation.
Biomass based electric power generation technologies succeeded in niche applications such
as supplying electricity in decentralized location and industries generating biomass waste.
The large scale penetration of biomass power technologies depends on their delivered cost
and reliability in direct competition with conventional electricity sources in centralized
electricity supply. In India, the principal competing source for electricity supply is the coal
based power.
Biomass energy cost is highly variable, depending upon the source, location etc. Delivered
cost of coal also varies depending upon the extraction costs and logistic costs which vary
with the distance from the mine. Coal power plants are built with large scale technology,
with a standard size of 500 MW. Scale of grid based biomass plants vary from a 1 MW to 50
MW.
The base price of coal in India is Rs. 48 per Giga Joule (GJ) and biomass is Rs. 72 per GJ.
Evidently, the delivered cost of electricity from a 50 MW biomass based power plants is
higher compared to coal power plant by 15 percent. In future this gap can be expected to
reduce due to three reasons:
The scale difference between coal and biomass plants shall narrow,
Cost of biomass shall reduce due to improved plantation practices, and
Coal price shall increase since it is an exhaustible resource.
3.8 BIOMASS POWER UNDER FAIR COMPETITION: INTERNALIZING THE EXTERNALITIES
Associated with conventional electric power plants are some negative social and
environmental externalities. Throughout the coal and nuclear fuel cycles, there are
significant environmental and social damages. Contrarily, biomass energy offers positive
environmental and social benefits. Biomass plantation is often a best way to reclaim
degraded lands and to generate sizable employment. Fossil fuel plant operations pose local,
regional as well as global hazards. Biomass combustion also emits pollutants; however
aggregate damage during the fuel cycle is much less compared to fossil or nuclear fuel cycle.
Governments in countries like Sweden and Denmark have now implemented measures to
internalize the externalities from conventional fuel use. Biomass offers most promising
future carbon mitigation options.
Even with low environmental taxes, electricity from coal power plant is more expensive than
biomass power plant. With high taxes, biomass electricity is far cheaper. Under a fair
competition therefore, when environmental externalities from fossil fuels are internalized,
the biomass produced electricity can be competitive vis-à-vis conventional coal power
plants. This points to a very promising future for biomass power technologies.
3.9 CONVERSION TECHNOLOGIES
3.9.1 CO-FIRING
Biomass co-firing in modern, large- scale coal power plants is efficient, cost-effective and
requires moderate additional investment. In general, combustion efficiency of biomass can
be 10 percentage points lower than for coal at the same installation, but co-firing efficiency
in large-scale coal plants (35%-45%) is higher than the efficiency of biomass-dedicated
plants. In the case of co- combustion of up to 5%-10% of biomass (in energy terms) only
minor changes in the handling equipment are needed and the boiler is not noticeably de-
aerated.
Biomass can be burned to produce electricity and Combined Heat – and – Power (CHP) via a
steam turbine in dedicated power plants. The typical size of these plants is ten times smaller
(from 1 to100 MW) than coal-fired plants because of the scarce availability of local
feedstock and the high transportation cost. A few large-scale such plants are in operation.
The small size roughly doubles the investment cost per kW and results in lower electrical
efficiency compared to coal plants. Plant efficiency is around 30% depending on plant size.
This technology is used to dispose of large amounts of residues and wastes (e.g bagasse).
Using high-quality wood chips in modern CHP plants with maximum steam temperature of
540°C, electrical efficiency can reach 33%-34% (LHV), and up to 40% if operated in
electricity-only mode. Fossil energy consumed for bio-power production using forestry and
agriculture products can be as low as 2%-5% of the final energy produced.
3.9.3 GASIFICATION
Biomass conversion into biogas can be either from fast thermo-chemical processes (e.g.,
pyrolysis) which can produce biogas and other fuels, with only 2%-4% of ash, or from slow
anaerobic fermentation - which converts only a fraction (50%- 60%) of feedstock but
produces soil conditioners as a byproduct. The biogas can be used in combustion engines
(10 kW to 10 MW) with efficiency of some 30%-35%; in gas turbines at higher efficiencies or
in highly-efficient combined cycles. Biomass integrated gasification gas turbines (BIG/GT)
are not yet in commercial use, but their economics is expected to improve. The first
integrated gasification combined cycle (IGCC) running on 100% biomass (straw) has been
successfully operated in Sweden. Technical issues appear to have been overcome. IGCC
plants are already economically competitive in CHP mode using black-liquor from the pulp
and paper industry as a feedstock
The cost of electricity from dedicated solid biomass plants depends on:
Technology
Feedstock quality and cost
Regional location
Size of the plant.
Large-size plants require biomass transportation over long distances. Small size means
higher investment cost per kW and lower electrical efficiency relative to coal plants.
3.10 BIOMASS POWER SECTOR STATUS
As of Oct 30, 2009 another 600 MW capacity projects are under implementation.
3.11 POTENTIAL
India has a biomass availability of 150 million MT per annum. This gives us a potential to
install 16,000 MW of biomass based plants. To realise this potential we need an additional
investment of Rs.1,00,000 crore.
The Table gives a clear picture of the utilized and unutilized potential of biomass power in
India.
Crop Biomass Biomass Power
Area
State Productio Generatio Surplus Potentia
(kha)
n (kT/Yr) n kT/Yr (kT/Yr) l (MWe)
Andhra
pradesh 2540.2 3232.0 8301.7 1172.8 150.2
Assam 2633.1 6075.7 6896.3 1398.4 165.5
Bihar 5833.1 13817.8 20441.8 4286.2 530.3
Chattisgarh 3815.5 6142.8 10123.7 1907.8 220.9
Goa 156.3 554.7 827.2 129.9 15.6
Gujarat 6512.9 20627.0 24164.4 7505.5 1014.1
Haryana 4890.2 13520.0 26160.9 9796.1 1261.0
Himachal
pradesh 710.3 1329.2 2668.2 988.3 128.0
Jammu &
kashmir 368.7 648.7 1198.7 237.7 31.8
Jharkhand 1299.8 1509.0 2191.2 567.7 66.8
Karnataka 7277.3 38638.5 23766.8 6400.6 843.4
Kerala 2041.7 9749.7 9420.5 5702.6 762.3
Madhya
pradesh 9937.0 14166.9 26499.6 8033.3 1065.4
Maharashtr
a 15278.3 51343.3 36804.4 11803.9 1585.0
Manipur 72.6 159.4 318.8 31.9 4.1
Meghalaya 0.8 14.0 42.0 8.4 1.1
Nagaland 27.1 87.6 149.2 27.2 3.1
Orissa 2436.6 3633.3 5350.4 1163.4 147.3
Punjab 6693.5 27813.7 46339.8 21267.0 2674.6
Rajasthan 12537.5 93654.8 204887.6 35531.1 4595.0
Tamil nadu 2454.0 24544.6 15976.6 6658.7 863.7
Uttar
pradesh 12628.2 46800.8 50416.7 11725.9 1477.9
Uttaranchal 66.4 135.8 159.9 51.6 6.6
West
bengal 5575.6 21062.8 23316.0 2959.7 368.3
105786. 139355.
Total 8 399262.1 546422.6 8 17981.8
JATROPHA
It is possible to use the wasteland (63 million hectares available at present) to grow
multipurpose biofuel plants such as Jatropha & Eucalyptus with minimum input. Once
grown, the crop has 50 years of life and fruiting can take place in two years. It yields up to
five tonnes per hectare oil seeds and produces two tonnes of biodiesel.
Jatropha & eucalyptus plants grown in 11 million hectare of land can yield revenue of
approximately Rs 20,000 crores, a year and provide employment to over 12 million people
both for plantation and running the extraction plant, he added.
There is a need to improve the oil content of Jatropha seed from the present 33% to at least
50%. Another area requiring further research is to develop seeds which can produce fruits
throughout the year.
4. BARRIERS TO ACCELERATED BIOMASS POWER DEVELOPMENT
In India, the deployment of biomass power generation technologies has been slow. The
difficulties facing the implementation of biomass power projects may differ slightly
depending upon whether the projects are drawing their biomass resources from a captive
(sugar, rice mills, etc.) as opposed to a distributed source (cotton stalks, mustard or rape
seed stalks; etc.). The development of biomass power projects involves broadly three
categories of sponsors:
Sugar Mills and Cooperatives
Private Sector/Small Entrepreneurs (largely biomass processors) and
Independent Power Producers (IPP, power generation companies)
Based on the trial and error of past experiences, the following specific barriers to
development of biomass power projects and replication of identified models have been
recognized.
Limited access to funds and difficulties in raising equity – Financial institutions are reluctant
to finance cooperatives and small investors, which expresses itself in unreasonable
securitization requirements.
Long gestation period – The experience to date has been that the project development
cycle requires several years to complete. The pre-project implementation phase (involving
project design, documentation, loan sanctions/approval) has taken more than two years in
many projects.
Low technological confidence – The lack of standardization and the introduction of high
pressure boilers (greater than 67 kg/cm2) have led to a resistance to switch over to
alternative processes and business models.
Fuel supply risks – As these projects are largely considered to make use of captive biomass,
the fuel-supply risks revolve mostly around the question of physical availability, which is a
function of rainfall, harvesting effectiveness, and productivity.
High management risks – Since the cooperative sector is subject to change in management
every five years, and is influenced by political factors, the risks for biomass power projects
becomes high.
4.8 BARRIERS FACED BY PRIVATE SECTOR
High transactions cost – Private sector/other entrepreneurs have difficulties raising loans
on existing financing norms due to perceived high risks by FIs, negotiations on PPA clauses
related to escrow/LC, etc.
Limited interest in power projects – Private sector/other investors have been unable to put
equity/debt on power development due to limited “proof-of-concept” demonstrations,
apart from rice-husk power plants.
High investment risks - For the project promoters and financial institutions, there is a
perceived high investment risk due to the limited number of visibly successful
demonstrations.
Lack of working capital – Limited access to banks for working capital requirements for
storing huge stocks of biomass materials for ensured year round operation.
Fuel supply risks – For biomass processors, the fuel-supply risks are twofold. The first set are
the physical availability, found in the case of all biomass power projects (rainfall, harvesting
effectiveness, and productivity). The second are the questions of contracted supply
encountered when dealing with distributed biomass supplies. The in-ability to lock-up
sufficient supplies of biomass from various sources will serve as a hindrance to project
finance and implementation.
Operational risks – These include the use of high-pressure boilers with multi-fuel based
biomass power plants; the lack of experience using distributed biomass materials.
4.9 BARRIERS FACING INDEPENDENT POWER PRODUCER MODEL
High transaction costs - The absence of fuel depots means that the cost of setting up of
depots and difficulty in establishing fuel linkage for year round operation, lead to high
transaction costs.
Limited access to financing – For power projects seeking to use distributed biomass
resources, there are no established lenders.
Lack of working capital – Limited access to banks for working capital requirements for
storing huge stocks of biomass materials for ensured year round operation.
Lack of infrastructure – The ability to connect small-scale generators to the grid is limited.
Fuel supply risks – The fuel-supply risks again fall into two categories, with perhaps the
second group being the most formidable for this group of producers. The first set are the
physical availability, found in the case of all biomass power projects (rainfall, harvesting
effectiveness, and productivity). Secondly, the questions of contracted supply are
encountered when dealing with distributed biomass supplies. The inability to lock-up
sufficient supplies of biomass from various sources will serve as a hindrance to project
finance and implementation. Fuel-supply agreements and mechanisms are critical to
projects for these actors.
Operational risks – There are operational risks associated with utilizing high pressure boilers
with multi fuel based biomass power plants and the limited demonstration ability of
different entrepreneurial models to suit the local situation and biomass types.
5. GOVERNMENT REGULATIONS
India is one of the countries that is most involved in developing the use of renewable
energies and is trying to make the opportunity for investors more attractive than costly.
The recent changes in the Renewable Power policies and the incentives provided by the
government have been able to attract private investments in the Biomass Power sector,
both, domestic and FDI.
6.1 DOMESTIC
• Green Planet Energy Private Limited has invested a sum of 9.6 billion rupees
(US$228/€145 million) on setting up 14 biomass power projects in the state of Punjab.
This has added 147MW of renewable energy to the state's portfolio.
• AllGreen, a leading renewable energy developer in India, plans to raise US$100 Million
to set up ten 6.5MW biomass-to-energy projects across India over three years. The first
three, projected to go on-stream by March 2010, will be in Karnataka, Tamil Nadu and
Madhya Pradesh.
• Oriental Green Power, a renewable energy generation company promoted by Shriram
EPC, Chennai, is planning to set up eight biomass-based power plants across the country
with an investment of Rs 1,000-Rs 1,100 crore. The proposed eight plants - each having a
power generation capacity of up to 8 mega watts (MW) - would come up in Tamil Nadu,
Andhra Pradesh, Maharashtra, Punjab and Rajasthan over the next two years.
• Ind-Barath Energy Utkal (IBEUL) has put forward plans to set up a 20MW biomass power
plant at Chiplima near Sambalpur in Orissa. IBEUL's biomass plant is to be built on a 40
acre site and the company has already lodged the plans with the state government
owned Industrial Promotion and Investment Corporation of Orissa (Ipicol) and the Orissa
Renewable Energy Development Agency (OREDA). The company expects the plant to be
operational 18 months after the Orissa government has allocated the land for the
project.
6.2 FDI
• Clenergen Corporation India Pvt. Ltd, a wholly owned subsidiary of Clenergen
Corporation USA, will install two new biomass power projects, a 16MW plant in Tamil
Nadu and a 64MW plant in Karnataka. The company has estimated an expenditure of
around $236 million for the proposed plants, and plans to raise $83 million in equity
from the Indian stock markets. Clenergen expects the Tuticorin plant in Tamil Nadu to be
commercially operational in the last quarter of 2010.
• French nuclear power specialist Areva and US-based Astonfield Renewable Resources
are teaming up to invest about €100m ($142bn) in biomass power plants across India.
Under the terms of the deal, announced by the companies last week, 10 biomass
facilities with a capacity of about 10MW each will be built. Areva will cover 40 per cent
of project costs, with Astonfield funding 60 per cent.
7. CONCLUSION
The very high potential of biomass, India’s capacity to add 16,000 MW through biomass,
biomass generation becoming financially viable, an established institutional framework with
industrial base, increased awareness of environmental issues and energy security issues are
the factors that will help the penetration of biomass power generation. However, this
depends on how the challenge of adapting to the changing face of the power sector in India
is handled.
REFERENCES
http://www.scribd.com/doc/16930431/2009-Power-Scenario-in-India
Indian Power Scenario, 2009
Rahul Vikram, National Power Training Institute (NPTI)