ID Task Task Name Duration Start Finish Predecessors

Mode
1 UNILVER TANKS 54 days Fri 01/05/20 Tue 23/06/20
2 2-6000 L Blending Tanks 50 days Fri 01/05/20 Fri 19/06/20
3 Conical Bottom Fabrication 5 days Fri 01/05/20 Tue 05/05/20
4 Top disc Fabrication 5 days Fri 01/05/20 Tue 05/05/20
5 Shell Plate Fabrication 10 days Wed 06/05/20 Fri 15/05/20 4,3
6 Heating Jacket/ Dimple Fabrication 10 days Sat 16/05/20 Mon 25/05/20 5
7 Appurtenances Fabrication 4 days Tue 26/05/20 Fri 29/05/20 6
8 Assembly of bottom, shell and top 6 days Sat 30/05/20 Thu 04/06/20 7
9 Tank Accessories Installation 4 days Fri 05/06/20 Mon 08/06/20 8
10 Detailing Works 5 days Tue 09/06/20 Sat 13/06/20 9
11 Testing and Commissioning 3 days Sun 14/06/20 Tue 16/06/20 10
12 Insulation Works 3 days Wed 17/06/20 Fri 19/06/20 11
13 2-6000 L Flavoring Tanks 40 days Fri 01/05/20 Tue 09/06/20
14 Conical Bottom Fabrication 5 days Fri 01/05/20 Tue 05/05/20
15 Top disc Fabrication 5 days Fri 01/05/20 Tue 05/05/20
16 Shell Plate Fabrication 10 days Wed 06/05/20 Fri 15/05/20 15,14
17 Appurtenances Fabrication 4 days Sat 16/05/20 Tue 19/05/20 16
18 Assembly of bottom, shell and top 6 days Wed 20/05/20 Mon 25/05/20 17
19 Tank Accessories Installation 4 days Tue 26/05/20 Fri 29/05/20 18
20 Detailing Works 5 days Sat 30/05/20 Wed 03/06/20 19
21 Testing and Commissioning 3 days Thu 04/06/20 Sat 06/06/20 20
22 Insulation Works 3 days Sun 07/06/20 Tue 09/06/20 21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode
23 6000 L Holding Tank 25 days Fri 01/05/20 Mon 25/05/20
24 Conical Bottom Fabrication 3 days Fri 01/05/20 Sun 03/05/20
25 Top disc Fabrication 3 days Fri 01/05/20 Sun 03/05/20
26 Shell Plate Fabrication 5 days Mon 04/05/20 Fri 08/05/20 24,25
27 Appurtenances Fabrication 2 days Sat 09/05/20 Sun 10/05/20 26
28 Assembly of bottom, shell and top 4 days Mon 11/05/20 Thu 14/05/20 27
29 Tank Accessories Installation 3 days Fri 15/05/20 Sun 17/05/20 28
30 Detailing Works 3 days Mon 18/05/20 Wed 20/05/20 29
31 Testing and Commissioning 3 days Thu 21/05/20 Sat 23/05/20 30
32 Insulation Works 2 days Sun 24/05/20 Mon 25/05/20 31
33 1500 L Holding Tank 25 days Tue 26/05/20 Fri 19/06/20 23
34 Conical Bottom Fabrication 3 days Tue 26/05/20 Thu 28/05/20 32
35 Shell Plate Fabrication 3 days Tue 26/05/20 Thu 28/05/20 32
36 Top disc Fabrication 5 days Fri 29/05/20 Tue 02/06/20 35,34
37 Appurtenances Fabrication 2 days Wed 03/06/20 Thu 04/06/20 36
38 Assembly of bottom, shell and top 4 days Fri 05/06/20 Mon 08/06/20 37
39 Tank Accessories Installation 3 days Tue 09/06/20 Thu 11/06/20 38
40 Detailing Works 3 days Fri 12/06/20 Sun 14/06/20 39
41 Testing and Commissioning 3 days Mon 15/06/20 Wed 17/06/20 40
42 Insulation Works 2 days Thu 18/06/20 Fri 19/06/20 41
43 Access Platform 15 days Fri 01/05/20 Fri 15/05/20
44 Layout/ Marking 2 days Fri 01/05/20 Sat 02/05/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors
Mode
45 Cutting and Grinding Works 3 days Sun 03/05/20 Tue 05/05/20 44
46 Assembly Works 6 days Wed 06/05/20 Mon 11/05/20 45
47 Detailing Works 4 days Tue 12/05/20 Fri 15/05/20 46
48 4000 L Water and Vinegar Blending Tank 30 days Sat 16/05/20 Sun 14/06/20 43
49 Slope Bottom Fabrication 3 days Sat 16/05/20 Mon 18/05/20 47
50 Top disc Fabrication 3 days Tue 19/05/20 Thu 21/05/20 49
51 Shell Plate Fabrication 5 days Fri 22/05/20 Tue 26/05/20 50
52 Appurtenances Fabrication 3 days Wed 27/05/20 Fri 29/05/20 51
53 Assembly of bottom, shell and top 6 days Sat 30/05/20 Thu 04/06/20 52
54 Tank Accessories Installation 3 days Fri 05/06/20 Sun 07/06/20 53
55 Detailing Works 4 days Mon 08/06/20 Thu 11/06/20 54
56 Testing and Commissioning 3 days Fri 12/06/20 Sun 14/06/20 55
57 8000 L Storage Egg Mixtures 50 days Fri 01/05/20 Fri 19/06/20
58 Slope Bottom Fabrication 5 days Fri 01/05/20 Tue 05/05/20
59 Top disc Fabrication 5 days Fri 01/05/20 Tue 05/05/20
60 Shell Plate Fabrication 10 days Wed 06/05/20 Fri 15/05/20 58,59
61 Heating Jacket/ Dimple Fabrication 10 days Sat 16/05/20 Mon 25/05/20 60
62 Appurtenances Fabrication 4 days Tue 26/05/20 Fri 29/05/20 61
63 Assembly of bottom, shell and top 6 days Sat 30/05/20 Thu 04/06/20 62
64 Tank Accessories Installation 4 days Fri 05/06/20 Mon 08/06/20 63
65 Detailing Works 5 days Tue 09/06/20 Sat 13/06/20 64
66 Testing and Commissioning 3 days Sun 14/06/20 Tue 16/06/20 65

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task Task Name Duration Start Finish Predecessors
Mode
67 Insulation Works 3 days Wed 17/06/20 Fri 19/06/20 66
68 Preparation for Delivery 4 days Sat 20/06/20 Tue 23/06/20 67

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
Resource
12 Apr '20 Names 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Team 1

Team 2

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
Resource
12 Apr '20 Names 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Team 3

Team 3

Team 4

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
Resource
12 Apr '20 Names 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Team 4

Team 6

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
Resource
12 Apr '20 Names 19 Apr '20 26 Apr '20 03 May '20 10 May '20 17 May '20
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
May '20 24 May '20 31 May '20 07 Jun '20 14 Jun '20 21 Jun '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
May '20 24 May '20 31 May '20 07 Jun '20 14 Jun '20 21 Jun '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
May '20 24 May '20 31 May '20 07 Jun '20 14 Jun '20 21 Jun '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
May '20 24 May '20 31 May '20 07 Jun '20 14 Jun '20 21 Jun '20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: UNILEVER SANYO rev.0
Summary Manual Summary Rollup Progress
Date: Fri 17/04/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12