You are on page 1of 1

Quality campaign week

Sl.no Date & Time Area Topics to be covered


1 17-03-2019 store Materials Management procedure,
Walkthrough observations, MSDS,
TDS, DSR and NCR
2 18-03-2019 Tank-710 area Materials preservation at Site, RFI
procedure, Drawing control, Method
statement, ITPs, DSR and NCR
3 19-03-2019 Tank730 area Materials preservation at Site, RFI
procedure, Drawing control, Method
statement, ITPs, DSR and NCR
4 20-03-2019 Tank700 area Materials preservation at Site, RFI
procedure, Drawing control, Method
statement, ITPs, DSR and NCR
5 21-03-2019 Audit criteria, Project Quality Project Meeting
plan, Roles and responsibilities