You are on page 1of 12

Tube Exchange on

IS TRU Generators

Purpose
The working instructions describe the exchange of tubes in the
TRUMPF generators IS 11…22, IS 30, IS 36/44.

Tube Exchange on IS TRU Generators 16.12.2005


Item No.: T 25-0006-00.BMEN-001-01
TABLE OF CONTENTS

TABLE OF CONTENTS ...........................................................2

INDEX OF FIGURES ..............................................................3

1 TUBE LABELING ...................................................................4

2 TUBE EXCHANGE .................................................................5


2.1 PREPARING THE GENERATOR ..................................................... 5
2.2 REMOVAL OF THE OLD TUBE ..................................................... 6
DESIGNATION ..................................................................................... 7
2.3 INSTALLATION OF THE NEW TUBE ............................................. 9
LABELING OF THE NEW TUBE .................................................................. 9
ORIENTATION ................................................................................... 10
CONNECTION OF THE WATER HOSES ..................................................... 11
2.4 SWITCHING THE GENERATOR ON AGAIN ................................ 12

Tube Exchange on IS TRU Generators


Chapter : Table of contents
Page 2 T 25-0006-00.BMEN-001-01
INDEX OF FIGURES

Fig.1.1 Designation RS3021 .............................................................................. 4


Fig.1.2 Designation RS2048 .............................................................................. 4
Fig.2.1 Vacuum tube in IS 11…22 ..................................................................... 6
Fig.2.2 Vacuum tube in IS 18 / 27 MHz ............................................................. 6
Fig.2.3 Tube in IS 30 ......................................................................................... 7
Fig.2.4 Vacuum tube in IS 36 / 44 ..................................................................... 7
Fig.2.5 Tube label .............................................................................................. 8
Fig.2.6 Handling the generator tube .................................................................. 9
Fig.2.7 Tube orientation for IS 11…22 ............................................................ 10
Fig.2.8 Tube orientation for IS 18 / 27 MHz ..................................................... 10
Fig.2.9 Tube orientation for IS 30 .................................................................... 11
Fig.2.10 Tube orientation for IS 36 / 44 ............................................................. 11

Tube Exchange on IS TRU Generators


Chapter : Index of Figures
T 25-0006-00.BMEN-001-01 Page 3
1 TUBE LABELING

The existing upward-pointing arrow (pointing towards the water con-


nection) has been replaced by a blue dot with a silver rim (diameter
15 mm); the existing downward-pointing arrow (pointing towards the
anode flange) has been replaced by a red dot with a silver rim (15 mm
in diameter).
If a tube with arrow labeling is replaced by a tube with dot labeling,
the labels "in" and "out" on the power output amplifier of the gener-
ator must also be replaced. The "in" sticker is replaced by a sticker with
a red dot and "out" is replaced by a sticker with a blue dot. The stick-
ers are included in the retrofitting kit.

blue red
(inflow) (outflow)

Fig.1.1 Designation RS3021

blue red
(inflow) (outflow)

Fig.1.2 Designation RS2048

Tube Exchange on IS TRU Generators


Page 4 T 25-0006-00.BMEN-001-01
2 TUBE EXCHANGE

Life threatening voltage!


The high voltages present in the generator are absolutely life-threaten-
ing and are also present at the RF output.
Even after switching off the generators, life-threatening voltages are
present at some components .
An additional danger exists due to the possibility of high voltage being
present on the water hoses!

Observe chapter "B Security" in the service manual of the


generator.

2.1 PREPARING THE GENERATOR

Ensure voltage-free ! Switch off the laser control and secure against reenergizing.
components
! Check for absence of voltage.

! Open the power output amplifier.

! Eliminate all residual voltages in the power output amplifier.


Observe the instructions given in chapter B.5: "Preparing for ser-
vice work" of the generators' service manual.

Draining the cooling ! Turn off the cooling water supply for the generator.
system
! Detach the cooling water supply at the generator (IN and OUT)
and drain the generator.

! Empty out the entire cooling system by carefully blowing it out


with compressed air.
Generators that are equipped with SIKA water monitors must be
blown out against the direction of the water flow.
Generators that are equipped with KOBOLD water monitors
must be blown out in the direction of the water flow.

! If cooling water has entered, dry the wet areas.

Tube Exchange on IS TRU Generators


T 25-0006-00.BMEN-001-01 Page 5
2.2 REMOVAL OF THE OLD TUBE

Sticker

Reactive anodes

Hoses

Fig.2.1 Vacuum tube in IS 11…22

Sticker

Reactive anodes

Hoses

Fig.2.2 Vacuum tube in IS 18 / 27 MHz

Tube Exchange on IS TRU Generators


Page 6 T 25-0006-00.BMEN-001-01
Sticker

Hoses

Reactive anodes

Fig.2.3 Tube in IS 30

Reactive anodes Hoses

Sticker

Fig.2.4 Vacuum tube in IS 36 / 44

! Remove the tube together with reactive anodes, hoses and hose
clips (Fig.2.1, Fig.2.2, Fig.2.3 and Fig.2.4).
A detailed description may be found in Chapter 5 of the operat-
ing instructions for the generator.

DESIGNATION
In the power output ! Replace the "in" sticker by a sticker with a red dot.
amplifier Replace the "out" sticker by a sticker with a blue dot.
(Position of the stickers: see Fig.2.2, Fig.2.3, Fig.2.1 and Fig.2.4).
The stickers are included in the retrofitting kit.

Tube Exchange on IS TRU Generators


T 25-0006-00.BMEN-001-01 Page 7
Removed tube ! Label the removed tube according to Fig.2.5.
For tubes without labels, write the specifications directly onto
the tube.

e.g.: IS 22

Date of installation (note down for


new tube)

may be read from the terminal of the


laser control

Date of removal

Fig.2.5 Tube label

Tube Exchange on IS TRU Generators


Page 8 T 25-0006-00.BMEN-001-01
2.3 INSTALLATION OF THE NEW TUBE

Warning!
The generator tube is a sensitive component and must be handled
carefully. Observe the following measures in order to protect the tube
from damage.

Anode body

Ceramic part

Fig.2.6 Handling the generator tube

• The tube must be handled via the anode body when it is to be lifted
and it must be avoided touching the ceramic part (see Fig. 2.6).
• Always put the tube on a soft base (on sheets of felt or rubber)
when it is outside of the packaging.
• Avoid setting the tube down too heavily, or impacting it with tools
or other objects.
• Check the tube for visible damage after opening the packaging.

LABELING OF THE NEW TUBE

! Enter the current date on the new tube (Fig.2.5: "Date of start
up in IS".)

Tube Exchange on IS TRU Generators


T 25-0006-00.BMEN-001-01 Page 9
ORIENTATION
! Install the new tube as described in the operating instructions
for the generator.
Observe the tube's orientation according to Fig.2.7,
Fig.2.9Fig.2.8 and Fig.2.10.

IS 11 … 22

blue dot

Fig.2.7 Tube orientation for IS 11…22

IS 18 / 27 MHz

blue dot

Fig.2.8 Tube orientation for IS 18 / 27 MHz

Tube Exchange on IS TRU Generators


Page 10 T 25-0006-00.BMEN-001-01
IS 30

blue dot

Fig.2.9 Tube orientation for IS 30

IS 36 / 44

blue dot

Fig.2.10 Tube orientation for IS 36 / 44

CONNECTION OF THE WATER HOSES

! Connect the water hoses such that the blue dot on the tube con-
nects with the blue dot on the generator.
The hoses are connected correctly if they are in parallel and do
not cross each other.

Tube Exchange on IS TRU Generators


T 25-0006-00.BMEN-001-01 Page 11
2.4 SWITCHING THE GENERATOR ON AGAIN

Warning!
When commissioning the generator with a new tube, a preheating
time (laser control TASC: Laser ON) of at least 30 minutes must be ob-
served before operating the generator under power (laser control
TASC: Beam On).