MANPOWER

MAJOR ACTIVITIES DURATION (weeks)


(Assumed)
DUMMY 1 PERMIT SET-UP AD1 10 Architect
-
DUMMY 2 POWER/WATER/PHONE BD2 10 2 men/- week
DUMMY 3 1 backhoe
- +4
DEMOLITION CD3 90
DUMMY 4 D4 0 men/week
-
DUMMY 5 EXCAVATION/GRADE DD5 170 3 men/- week
DUMMY 6 SITE PREPARATION ED6 10 2 men/- week
DUMMY 7 FORMWORK FD7 130 8 men/- week
DUMMY 8 CONCRETE FOUNDATION GD8 160 5 men/- week
DUMMY 9 TEMPORARY ELECTRIC SERVICE HD9 10 2 men/- week
DUMMY 10 STRUCTURAL STEEL J
D10 110 16 men/- week
DUMMY 11 MASONRY K
D11 130 3 men/- week
DUMMY 12 ROOF L
D12 60 7 men/- week
WINDOWS & DOORS M 7 4 men/ week
SIDING &EXT. TRIM N 5 3 men/ week
ROUGH PLUMBING (pipes in slab, pipes in walls) O 11 9 men/ week
ROUGH ELECTRICAL (wiring in walls, switch and outlet boxes
P 12 9 men/ week
installed)
DRYWALL R 9 4 men/ week
CARPENTRY S 13 4 men/ week
INTERIOR DOORS & TRIM T 6 2 men/ week
LATH & PLASTER U 12 3 men/ week
SEPTIC OR SEWER V 4 4 men/ week
GLAZING W 5 15 men/ week
HARDWARE & MILLWORK X 4 2 men/ week
PAINT/STAIN Y 14 4 men/ week
FLOOR COVERING Z 9 6 men/ week
CABINETRY AA 16 3 men/ week
MECHANICAL WORKS BB 2 10 men/ week
FINISH PLUMBING (water heater, showers, tubs, sinks, faucets) CC 3 8 men/ week
FINISH ELECTRICAL (light fixtures, switches, outlets, fans, smoke
DD 4 7 men/ week
detector)
GLASS AND HARDWARE EE 6 10 men/ week
SIDEWALKS/DRIVEWAY FF 3 3 men/ week
BATH & TOILET HH 3 5 men/ week
FINAL INSPECTION II 1 3 men/ week
PUNCH OUT (all remaining uncompleted and defective work
JJ 2 3 men/ week
unfinished)
TURN UTILITIES ON KK 1 3 men/ week