Mastertop 195 AF (formerly known as Florguard Overlay)

Thin-set aggregate filled concrete floor re-surfacing system


the floor ensuring that the material is pulled out as
Description thinly as possible.
The System.
Mastertop 195 AF is used to provide a system for Whilst the Concresive 1414 bonder bond is still wet
thin-set industrial floor toppings in excess of 20mm the topping mix should be placed and tamped to fill
to concrete floors. The Mastertop 195 AF is a voids and expel air and then straight-edged to the
powder, quartz aggregate (4-9mm) blend with level required. Proper wetting-out of the topping mix
cementitious binders and shrinkage compensation to the bond coat is essential for good long-term bond
additives. success.

Preparation Floating
The concrete floor surface must be free of laitance, Wood-float the surface to ensure complete
oil, dust or loose particles, which will interfere with elimination of pinholes and to expel entrapped air
the topping bond. Scabbling or other mechanical and eliminate surface bubbles. Floating with the
methods of surface treatments may be necessary wood-float flat on the surface draws out air and
dependent on the condition of the floor. consolidates the topping mix. Protect the surface
against early drying through exposure to wind or sun.
Epoxy Bonding – Recommended method of Either cover with thin plastic sheeting or spray with
bonding Masterkure 111CF evaporation control solution.
Mix and apply Concresive 1414 epoxy bonding agent When the topping has set sufficiently to commence
in accordance with the recommended procedure steel floating, float, initially keeping blade flat onto
contained in the relevant data sheet. the surface and using circular movement.
When the surface has further tightened by setting,
Acrylic Bonding final finishing may commence.
Whilst the first batch of topping is being mixed apply Each time a float or trowel is removed from the
the mixed Concresive 1414 epoxy bonder surface wipe it clean otherwise semi-set paste will
over the area on which this mix will be placed. become sticky and difficult to remove. To avoid
trowel drag (fine cracks due to semi set material
Mixing Instructions being pulled by the trowel), await proper hydrative
The topping is batched by adding approximately 3 set before attempting to finish and wipe the trowel
litres of water to each bag of Mastertop 195 AF Blade with a 1:5 "Rheomix 111"/water solution to
stop sticking.
powder. Machine mixing is best, but a board or
wheelbarrow may be used for hand mixing on small
jobs. The mix should be a soft mortar consistency.

Placing
Place lats or strip forms to establish the desired
finished level. Using a stiff brush or soft rubber
squeegee spread the Concresive 1414 evenly over
Mastertop 195 AF (formerly known as Florguard Overlay)
Power Floating Allow sufficient lead-time to manufacture special
Despite its relatively thin section, carefully colours.
controlled, Mastertop 195 AF may be power floated
and machine finished. To avoid stripping of the Storage
overlay mortar from the substrate, care must be Store under cover, out of direct sunlight and protect
taken to allow sufficient set to take place to from extremes of temperatures.
accommodate the weight and movement of the Failure to comply with the recommended storage
power float machine. conditions may result in premature deterioration of
the product or packaging. For specific storage
advice consult BASF Construction Chemicals SA’s
Protection and Curing
Technical Services Department.
Protect the finished work against wind and sun and
allow curing overnight. First thing next day apply a
liberal coat of Masterkure 181 curing compound, and Safety precautions
As with all chemical products, care should be taken
allow drying. The floor should be allowed at least 3
during use and storage to avoid contact with eyes
days curing before putting into light duty use and 7
mouth, skin and foodstuffs (which can also be
days before full use.
tainted with vapour until product is fully cured or
dried). Treat splashes to eyes and skin
Stress Relief Joints immediately. If accidentally ingested, seek
Follow normal industry practice as regards panel immediate medical attention. Keep away from
sizes and shrinkage stress relief. The system is low children and animals. Reseal containers after use.
shrinkage, high strength, but large panels will need
stress relief joints. (follow C&CI recommended Note
practice). Recommend panels not exceeding 3 x 3 Field service, where provided, does not constitute
meters square. supervisory responsibility. For additional information
contact your local BASF Construction Chemicals SA
Packaging representative. BASF Construction Chemicals SA.
25 kilogram polylined bags. reserves the right to have the true cause of any
Yield - ± 10.5 Litres / bag. difficulty determined by accepted test methods

Estimating Data Quality and care


All products originating from BASF Construction
20mm thick 48kg's / m²
25mm thick 60kg's / m² Chemicals’ SA facility are manufactured under a
30mm thick 72kg's / m² management system independently certified to
conform to the requirements of the quality,
Colours environmental and occupational health & safety
Charcoal, Red, Brown, Tan, Green, various tints of standards ISO 9001:2000.
Grey and untinted cement.

Whilst any information contained herein is true, accurate and represents our best knowledge and experience, no warranty is given or
implied with any recommendations made by us, our representatives or distributors, as the conditions of use and the competence of any
labour involved in the application are beyond our control.
As all BASF’s technical datasheets are updated on a regular basis it is the user's responsibility to obtain the most recent issue.
BASF Construction Chemicals South Africa (Pty) Ltd
P.O. Box 420, Westonaria, 1780 852 Sixteenth Road, Midrand
11 Pullinger Street, Westonaria, 1779 PO Box 2801, Halfway House, 1685
Tel: +27 11 754 1343 Tel: +27 11 203 2405
Fax: +27 11 754 1105