You are on page 1of 4

CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009

Paper 0119
ANALYSIS OF ICING ACCIDENT IN SOUTH CHINA POWER GRIDS IN 2008
AND IT’S COUNTERMEASURES

LI Tianyou1, 2 LI Juanjuan
1.Fujian Electric Power Co., Ltd., Fujian, Fuzhou 350003, China Xiamen Power Supply Bureau,
2.Business Administration Institute, North China Electric Fujian, Xiamen 361006, China
Power University, Beijing 102206, China E-mail:lijjuan@126.com
E-mail:ltyxm@163.net
Abstract: The South China suffered a serious icing railway traction station were seriously affected. Total
accident in the beginning of 2008, which caused a wide outage 884 35kV and above substations and 15,300 10kV
area destroyed on the power grid In this paper we used and above transmission lines, and 184,000 high-voltage
the first-hand data collected from the field in towers and 519,000 low-voltage poles were broken.
northwestern Fujian Province, analyzed the key factors Besides, data from the <Southern Power System
that caused such a serious accident. The analysis pointed Technology> showed sleet and frost had caused 7451
out that the disaster that hadn’t happened in 50 years 10kV and above power lines outage and 859 35kV and
before caused tht lines were covered by thick ice, it’s above substations outage in China Southern Power Grid
1
beyond the former design standards of devices which Corporation (CSG) , total 126247 10kV and above
didn’t consider such serious weather conditions, power towers and poles were destroyed by the end of
especially the snow-icing condition. Many lines and February 27th, 2008. It needed 39.0 billion RMB to
towers in large area were broken and fallen down. So, we rebuild and reconstruct. The loss would be greater if CSG
need to attach importance to the microclimate conditions and local power departments were involved. Take Fujian
and micro-geographical characteristics along the lines, power network as an example to analyze, low
to carry out differential design standards for such temperature with frozen rain, snow and icing was
different icing-zone, to suitable choose the route for continuing more than 10 days resulting in insulator drop,
power supply lines, to strengthen the routine inspection of wire breakage and tower failure, which caused the
the measures for combating the accidents and fighting distribution outage of Longyan, Sanming and Nanping in
with the natural calamities, etc... In addition, a guiding Northwestern Fujian Province. The lessons were
principle about strengthening the planning of power profound because of huge economic loss, wide area
sources and developing the distributed generation power failure (about 600,000 houses), long duration
sources and building LIFE CHANNEL for city grid had (almost 1 month) unavailable service and almost whole
been decided to put into practice, thus to strengthen the county outage of several counties. The damage
ability to withstand the influence caused by the natural classification of distribution and pole failure of each
calamities. voltage level in Fujian power network is separately
Keywords:icing accident,distribution network,tower shown in Table 1 and Figure 1.
failure,countermeasures Tabel.1. Distribution damage collecting table in
Fujian province in 2008
1. INTRODUCTION Earth Damage
Most parts of South China have had a heavy snow-cing Pole Wire wire lines
Voltage failure breakage Breakage Length
which haven’t happened in fifty years before. Strong cold (kV) (points) (points) (points) (km)
air intruded into Fujian Province on January 24th, 2008. 110 103 49 21 200.994

According to the reports from State Grid News on March 35 339 276 10 245.6

24th, 2008, as far as State Grid Corporation of China 10 16392 2987.78


0.4 18025 2599.3
alone, there were 545 counties (districts) and more than
Total 34867 325 31 6032.674
27 million users affected, among which 80 counties
(districts) almost lost all power supply, 15 electrified 1
China power network was divided into State Grid Corporation
of China and China Southern Power Grid Corporation

CIRED2009 Session 3 Paper No 0119


CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009
Paper 0119
of tower #18 was twisted leading to all of its conductors
falling off (see Figure 3). Further, the unendurable of the
icing weight caused the fell down of #19 tower. During
such situation, the domino effect occured in line
strain section making chain-type damage of
devices. That was the reason why many poles and
towers inclined or fell down in succession, and
this phenomenon happened in more places.

Fig 1. Pole failure of each voltage level in Fujian province


2. ANALYSIS OF THE MAIN CAUSES OF
HUGE DAMAGE
2.1 The Damage Of A Large Number Of Power
Lines And Equipments As Result of Icing Accident
1) Thickness Of Ices Covering The Lines Greatly
Exceeded Design Standards Fig 3. The situation of straight tower #18 of 110kV Hetai line
Fujian province locates north latitude between 3) Icing Trees On The Sides Of The Corridor Were
23°31′and 28°18′, has a typical subtropical Broken And Pressed On The Lines
climate. Mountains and hills with altitudes from 250m Ice-coating trees like Mao Bamboo and Chinese Fir on
to 1000m make up the vast majority of Fujian‘s territory. the sides of tower corridor in icing accident zone were
It was raining in Northwestern Fujian province from bent or broken and pressed on the lines, which made
January 25th to February 1st followed frozen rain and lines burdening not only the icing strength but such
sleet. Pre and post icing accident, most weather external force, caused the weaker tower or wire was
temperature in disaster area kept about 0℃. Lines in broken firstly. Such phenomena generally happened on
disaster area were mostly situated windward slopes, media or low voltage distribution lines.
watershed, wind gap and hillside over 550m, thickness of 2.2 It’s Hard To Eliminate Ice Covering On The
ices covering the lines commonly reached 40mm and the Distribution Lines And To Restore The Lines
worst even over 80mm (see Figure 2). Lines in Fujian
Even if no pole failure and wire broken happened in
province are designed as withstanding ice of 10mm and
safety factor of 2.5. Therefore, lines, towers and other media or low voltage distribution, no ice melting
equipments couldn’t reach the requirements of actual measures could be taken. The restoration carried out only
anti-icing. Icing conductors and earth lines happened
upward-downward and forward-backward self-oscillation, after ice and snow melted, thus it caused a long duration
low frequent, large amplitude galloping under the wind of power interruption. It was a distinct feature for
force. Adding unequalled icing, asynchronous ice melting distribution network that suffering from the icing
and deicing, all of these caused large scale conductors
and earth lines broken and pole and tower failure. accident. The icing phenomena on a pole of distribution
line was shown in Figure 4.

Fig 2. An 110kV central conductor icing scene


2) Unbalanced Line Stress Of The Icing Lines Caused
Wire Breakage And Tower Damage Fig 4. The icing phenomena on a pole of distribution line
Field survey showed that heavy-damaged lines had 2.3 The Problems Existed On The Connection
characteristics of long span (even over 500m) and high
Between The County Net And The Provincial Grid
drop height. Covered by ice, the line sag became larger
which increased horizontal tension and vertical load of The power tie-lines between the county net and
lines. For instance, 110kV Hetai line’s span between provincial grid broken was one of reasons why several
tower #18 and #19 is 814m. Tower #18 was located on
counties were almost whole county outage. Some
the top of a higher hill, while tower #19 was on the foot
of another hill, the drop height between two towers was connections between them were single circuit or even
about 80m. Due to unbalanced tensile force, the top part double circuits, but all of them were in the same situation

CIRED2009 Session 3 Paper No 0119


CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009
Paper 0119
suffering the same accident. Thus, reliable supply speed to provide the first-hand data for power grid
couldn’t be ensured under such serious weather and preventing from icing accident.
caused the absence of power sources. 3.2 Take Differential Design Standards And
2.4 The Problems Of Material Reserve Used In Appropriately Raise The Grid Planning Design
Rush Repair Standards In Special Areas
Lack of power equipments and materials reservesd for For the lines in the snow disaster-prone areas, their
rush repair, such as insulators, conductors, poles, etc was design level of withstanding icing thickness should be
exposed. Especially for power poles, tens of thousands increased, it should be at least 15mm for the general area
poles were needed at once and it wasn’t possible only to and 40-50mm for partial heavy ice areas. The
rely on local dispatch. The outside province recourse had fortification standards for power grid needs to raise, for
to be taken, but it took much more time and the cost was some distribution lines, the standards should be in
increased. accordance with enduring strong ice and snow climate at
2.5 After Icing Accident, The Restoration Condition least in 30 years. For special, probably disaster
Was So Bad That It Paid Great Efforts And Time To happening area, its design technical conditions should be
Recover rationally improved on the basis of both reliability and
Icing accident had passed, but it remained raining. The economy to cope with the possibility of happening
line materials, such as the poles and accessories and even special meteorological disasters. The line routes being
the machines, couldn’t be delivered to the mountain area planned and designed should avoid some landforms like
by cars. So, a large number of people were dispatched high-altitude, wind gap as far as possible. For high
from different places to send them to the restoration site. altitude area (above 500m), the span must be strictly
The great efforts were made and it prolonged the time for controlled, recommending no more than 400m. At the
restoration. same time, strain towers should be adequately increased
3. COUNTERMEASURE to prevent the extension of incident. Finally, the
With the global warming and continuous deterioration construction quality of grouting of tower foundation and
of environment, some originally abnormal rare climates conductor sag should be grimly controlled as design
arise in some areas. This icing accident exposed the requirements.
insufficiency of power network to withstand serious 3.3 Pay Great Attention To The Selection Of Line
natural disaster. It needs to take multi-measures to Routing And Design Of District Backbone Network
actively prevent power network from icing accident to For lines which supply the local backbone should avoid
efficiently reduce outage time. in the areas such as icing-hit frequently, alp and air gap
3.1 Divide Icing-zone And Establish Icing-zone where bring a lot of disadvantages of daily maintenance,
Monitor And Warning the accident rate of lines, rush repair and so on, and
According to weather information over years combined forest area brings more resistance of clean-up passages
with current special situation of climate changing, and is easier to cause large-scale tower falling down and
in-depth study of effects of meteorological condition on wire broken. In addition, if it’s inevitably for lines to be
power lines should be implemented. At the same time, located in bad condition areas, enhanced differential
the collection of micro-meteorological data along the design and rebuilding should be taken according to the
lines and researches need to be strengthened to study most atrocious weather to resist the worst natural
different micro-climatic conditions in different sections disaster.
and put forward and picture the probability distribution It needs at least 2 lines from different routes as tie-lines
of grid icing. In the snow disaster-prone areas, between county net and provincial grid. And the routes
monitoring stations of ice conditions should be should be along the traffic roads as possible as it can.
established to predict the probable thickness of ice 3.4 Attach Enough Importance To The Utilization
through the observation of ambient temperature, wind Of Distributed Generation

CIRED2009 Session 3 Paper No 0119


CIRED 20th International Conference on Electricity Distribution Prague, 8-11 June 2009
Paper 0119
It was local small hydroelectric units that let several it needs to reconstruct power network for distribution
heavy disaster county-level power grids restore power mixed overhead lines and cables.
supply firstly during the accident, and then a dependent 3.7 Periodically Evaluate And Inspect The Ability
power network was formed to supply the whole county Of Preventing Disasters Of Power Network
such as Jianning County, the city of Sanming. When two It needs to have the expert team periodically evaluate
tie lines between county and provincial power network the ability of preventing emergencies or disasters of
outage because of tower failure and wire breakage caused power network. The evaluation includes disaster trends in
the whole county power off, the county relayed on eight the region, the possible capability of the emergency
small hydropower stations in the county to form a small handling mechanism, annual network performance (such
power network and restore power service lasting for one as reliability, failure rate, etc), the equipped conditions of
month. The output of eight small hydropower stations local emergency security sources and power supply
were shown in the figure.5, the smallest was 0.4MW, the devices for key users, the storage of disaster relief
largest was 5MW. Therefore, distributed generation for materials and so on. Through evaluation and examination,
preventing a large scale outage has an irreplaceable effect. risks and major weaknesses are found, then the direction
We need to pay attention to the development and and measures of enhancing the ability of power network
construction of local distributed generation along with the to prevent disasters in next phase can be made.
development of large-capacity power units. In addition, others such as cleaning up the line path,
strengthening the inspection and maintenance of lines,
studying ice-melting technology for media and low
voltage distribution , replacing the overhead lines of some
major users with underground cables are also the
measures promoted against disasters.
4. CONCLUSION
Global abnormal weather frequently happened, natural
disasters such as icing disaster, earthquake, flood disaster,
etc. continued to occur, all of which challenged the ability
of grids to resist disasters. Some countermeasures were
suggested by using the first-hand data collected from the
icing field and analyzing from the technical views,
including the establishment of monitoring station for the
Fig. 5. Jianning County’s grid wiring diagram during accident icing-zone, adoption of differential design standards for
3.5 Equip With Emergency Security Power Source the lines, the selection of the line routing and design of
For some key departments and units, such as water backbone network, development of distributed generation
supply, media, finance, and government agencies and so and construction of LIFE CHANNEL for urban network.
on, it needs to equip with emergency security sources or Of course, it’s a systematic project to strengthen and
plan as a whole to make sure to have a normal and safe improve the ability of anti-disaster of power grid, which
power network operating in the case of emergency. not only involves power system planning, construction
3.6 Set Up LIFE CHANNEL For City Grid and management, but the social emergency handling
To answer the disaster, it’s necessary to set up special capability and other issues. It needs continuous
urban basic security power grid - LIFE CHANNEL for exploration and improvement in practice.
city power grid to ensure power supply to social vital
parts, high-risk enterprises and important institutions for
combat against emergency. The basic configuration of
urban security network is underground cable network, so

CIRED2009 Session 3 Paper No 0119

You might also like