Concrete & Aggregate Productions Business

Thahtay Hydropower Project


တမံဖို့ေကျာက်အတွက် RBM တူးတင်သယ်ပို့ြခင်း။

Daily Report ( Feb -20)

Date Trip Sud Total Remark

21-Feb-20 59.00 4.50 265.50

27-Feb-20 325.00 4.50 1,462.50

28-Feb-20 325.00 4.50 1,462.50

29-Feb-20 352.00 4.50 1,584.00

စုစုေပါင်း 1,061.00 4,774.50


Concrete & Aggregate Productions Business
Thahtay Hydropower Project
တမံဖို့ေကျာက်အတွက် RBM တူးသယ်တင်ပို့ြခင်း။
Daily Report (Mar-20)
Date Trip Sud Total Remark
1-Mar-20 372.00 4.50 1,674.00
2-Mar-20 285.00 4.50 1,282.50
3-Mar-20 331.00 4.50 1,489.50
4-Mar-20 341.00 4.50 1,534.50
5-Mar-20 336.00 4.50 1,512.00
6-Mar-20 366.00 4.50 1,647.00
7-Mar-20 402.00 4.50 1,809.00
8-Mar-20 370.00 4.50 1,665.00
9-Mar-20 408.00 4.50 1,836.00
10-Mar-20 402.00 4.50 1,809.00
11-Mar-20 340.00 4.50 1,530.00
12-Mar-20 419.00 4.50 1,885.50
13-Mar-20 284.00 4.50 1,278.00
14-Mar-20 490.00 4.50 2,205.00
15-Mar-20 436.00 4.50 1,962.00
16-Mar-20 407.00 4.50 1,831.50
17-Mar-20 457.00 4.50 2,056.50
18-Mar-20 450.00 4.50 2,025.00
19-Mar-20 428.00 4.50 1,926.00
20-Mar-20 455.00 4.50 2,047.50
21-Mar-20 506.00 4.50 2,277.00
22-Mar-20 456.00 4.50 2,052.00
23-Mar-20 468.00 4.50 2,106.00
24-Mar-20 408.00 4.50 1,836.00
25-Mar-20 213.00 4.50 958.50
26-Mar-20 307.00 4.50 1,381.50
27-Mar-20 354.00 4.50 1,593.00
28-Mar-20 296.00 4.50 1,332.00
29-Mar-20 330.00 4.50 1,485.00
30-Mar-20 281.00 4.50 1,264.50
31-Mar-20 248.00 4.50 1,116.00
စုစုေပါင်း 11,646.00 52,407.00
Concrete & Aggregate Productions Business
Thahtay Hydropower Project
တမံဖို့ေကျာက်အတွက် RBM တူးတင်သယ်ပို့ြခင်း။
Daily Report (April-20)
Date Trip Sud Total Remark
1-Apr-20 261.00 4.50 1,174.50
2-Apr-20 237.00 4.50 1,066.50
3-Apr-20 180.00 4.50 810.00
4-Apr-20 213.00 4.50 958.50
5-Apr-20 205.00 4.50 922.50
6-Apr-20 289.00 4.50 1,300.50
7-Apr-20 262.00 4.50 1,179.00
8-Apr-20 281.00 4.50 1,264.50
9-Apr-20 311.00 4.50 1,399.50
10-Apr-20 379.00 4.50 1,705.50
11-Apr-20 336.00 4.50 1,512.00
12-Apr-20 290.00 4.50 1,305.00
13-Apr-20 390.00 4.50 1,755.00
14-Apr-20 384.00 4.50 1,728.00
15-Apr-20 410.00 4.50 1,845.00
စုစုေပါင်း 4,428.00 19,926.00
Concrete & Aggregate Productions Business
Thahtay Hydropower Project
တမံဖို့ေကျာက်အတွက် RBM တူးတင်သယ်ပို့ြခင်း (150,000 Sud)

Sr,No Month Sud Trip Total (Sud) Remark

01 February 4.50 1,061.00 4,774.50

02 March 4.50 11,646.00 52,407.00

03 April 4.50 4,428.00 19,926.00

စုစုေပါင်း 17,135.00 77,107.50