Professional Documents
Culture Documents
CHAPTER 1
It is Industrial structural Consultants for all Civil Engineering works in the field
of construction since 25 years. It has a planning wing, Design wing & supervision
wing separately, undertake the total project under turnkey i.e. plan, design &
supervise the total project. It has well experienced technical staff & also have field
laboratory to conduct tests as & when required for materials like cement, sand,
aggregates, concrete etc.
Company has Non destructive testing machine equipments like Rebound Hammer,
Ultra Sonic Equipment. It has well experienced good Civil Engineers & Civil
Contractors who can able to do the Industrial project in stipulated time.
Also carried out surveying part & have Total Station & well experienced Survey
team.
Sl.
Name Qualification Position Experience
No
1 Muniratnam M. Tech Team Leader 16Years
Phd. Team
Dr.B.M.Rudramuni/H.
2 M.Tech/ Leader/Proje 18 years
M.Prashanth
B.E.(Civil) ct Engineer
M.Tech..(Soil
3 Tupaad . V Team Leader 18 Years
Mech.)
Sri. Ramachandra
4 M.Tech BE Team Leader 19 Years
Murthy
M.S.(Elec) /
5 M.B.Mallikarjuna / Sr. Elec. 16Years / 15
H.M.Kotra swamy B.E.(Elec.M.Te Engineer Years
ch)
6 M.R.Vijaya Kumar M.Tech Tean Leader 15 Years
Rtd. Executive
7 G.Channa Basappa Engineer Team Leader 18 Years
BE
M.E..(Geo.Tech
8 Shiva Kumar Team Leader 15 Years
.)
9 R.T.Sreeinivas Rao M.E Team Leader 18 years
Rtd. Junior
13 Sivasankara Goud.R Engineer Team Leader 12 Years
DCE
Senior
Y.D.Naik/
14 B.E.Mechanical Mechanical 20Years
Chennabasava
Engineer
Senior
15 K.M.Veeraiah B.E Civil 16 Years
Engineer
Senior
16 Devappa Hosur B.E Civil 16 Years
Engineer
Quality
17 Diwakar Gundi B.E Civil Control 16 Years
Engineers
Senior
18 B.Mallikarjuna Gouda B.E 16 Years
Engineer
Sr.Site
19 H.M.Shivshankar B.E Civil 10 Years
Engineer
Senior
Quality
20 Ravindra Kumar B.E Civil 15 Years
Control
Engineers
Senior
21 J.RadhaKrishna B.E 12 Years
Engineer
Senior
22 J.Nagaraj B.E Civil 11 Years
Engineer
Quality
23 Moinuddin B.E Civil Control 8 Years
Engineers
Quality
24 Rajshekar D.C.E Control 21 Years
Engineer
Quality
25 R.Mahesh D.C.E Control 12 Years
Engineers
Quality
26 Saad.H.Rehaman D.C.E Control 11 Years
Engineers
Turnover of the organization details for four years from 2009 is listed below:
Premier Technical Consultants has Material testing lab and is started in the year 2014.
It is engineering services and advanced construction material testing laboratory.
Company has sufficient number of lab equipment for conducting tests on construction
material at site.
05 Kgs 05 Nos
10 Kgs 05 Nos
20 Kgs 05 Nos
To Weigh Fine & Coarse
aggregates.
3 Rapid Moisture meter 02 Nos (Alphatech Company)
To Know the moisture content in a
gravel base (Road /embankment
work) at site.
4 Core cutters with ram 50 Nos
To Know the density achieved in
case of embankment or road.
5 Slump apparatus 10 Nos
To control the water cement ratio at
the time of mixing concrete at site.
6 Sieve sets
Coarse aggregate 10 Sets
Fine aggregate 10 Sets
Samples of FA & Ca will be tested
at the site & compared with IS 383
-1970 the results if satisfied as per
code allowed for further work.
Otherwise material will be rejected.
7 Concrete Cubes 105 Nos To cast cement concrete
cubes at site.
b Ultra sonic 01 No
Knowing the time required to pass
the pulse waves b/w two points
velocity can be calculated. Based
on velocity concrete grade can be
decided
21 Survey Instruments
a Total Station (Pentax) 01 No
b Theodalite 05 Nos
c Auto level 02 Nos
d Prismatic compass 02 Nos
To know the position & levels of
existing points on drawing.
CHAPTER 2
ABOUT THE DEPARTMENT
It offers engineering design, estimation, project planning, tendering, construction
drawing, periodic site supervision, quantity survey etc. It has a planning wing,
Design wing & supervision wing separately, undertake the total project under
turnkey i.e. plan, design & supervise the total project. It has well experienced
technical staff & also have field laboratory to conduct tests as & when required for
materials like cement, sand, aggregates, concrete etc.
Company has Non destructive testing machine equipments like Rebound Hammer,
Ultra Sonic Equipment. It has well experienced good Civil Engineers & Civil
Contractors who can able to do the Industrial project in stipulated time.
To Take care of
Managing Total project
H.M.Somasekhariah execution & is
Director.
1 16 Years responsible for all
B.E (Civil)
(Team Leader / activities
M.Tech.P.hd
Structural Engg) implementation in
reviewing the entire
project.
To Take care of
Total project
H.J.RadhaKrishna Highway execution & is
shetty Engineer / responsible for all
2 18 years
Transportation activities
B.E (Civil) M.E.(str) Planner implementation in
reviewing the entire
project.
To Take care of
Total project
Patel.T.H., BOQ/Estimation execution & is
3 responsible for all
B.E (Civil) M.Tech Engineer 18 Years
activities
implementation in
reviewing the entire
project.
To Take care of
Total project
15 Years execution & is
Rudramuni BM
responsible for all
4 B.E (Civil) M.Tech, Survey Engineer
activities
Ph.D
implementation in
reviewing the entire
project.
To Take care of
Total project
execution & is
Ravindra Kumar, Contract responsible for all
5 16 Years
B.E (Civil) Specialist activities
implementation in
reviewing the entire
project.
Comparison of tests
Rajendra Prasad results obtained
6 Q.C Engineer 15 Years / with IS Standards
B.E (Civil) & submitting to
Sr.Engineer
Incharge
Co-ordination with
H.Nagaraj Q.C.E Sr.Engineer
Quantity in collection of
7
B.E (Civil) Surveyor materials & testing
12 years
the same in filed &
lab
To Take care of
Total project
execution & is
J.Nagaraj. Quantity
responsible for all
8 Surveyor /Site 10Years
B.E (Civil) activities
Engineer
implementation in
reviewing the entire
project.
Co-ordination with
Q.C.E Sr.Engineer
Tupaad Quantity in collection of
9
B.E (Civil) Surveyor materials & testing
10 Years
the same in filed &
lab
To Take care of
Total project
Site Engineer execution & is
10 R.T.Sreenivasa Rao, /Water Supply responsible for all
16 Years
B.E (Civil) M.E. and Sanitary activities
Engineers implementation in
reviewing the entire
project.
Co-ordination with
Mohammed Salman Sr.Engineer.
Sayeed Quantity 15 Years
12
Surveyor
B.E Civil
Y.D.Naik, Mechanical
Co-ordination with
13 Engineer
B.E., (Mech) M.E. 12 years Sr.Engineer.
Engineer
M.S./H.M.Kotra
16 Electrical
swamy
Engineer 10 Years
B.E. (Elec) M.Tech
Structure must fulfill its all structural saftey during its life span.
The structure must be economical with less maintenance cost.
Member design.
Involves determination of size of the member, amount and detailing of
reinforcement for resisting the design force calculated in the analysis stage.
Detailing, Drawing and preparation of schedules.
CHAPTER 3
TASK PERFORMED
3.1 PROPOSED CONSTRUCTION OF RESIDENTIAL
BUILDING AT KHB COLONY, BALLARI
Type of Building: Residential
Plan : 9mX15m
Client name – K.M.kotresh
Location: Ballari
No of Storey: G+2
Bottom storey height: 3.0m
Typical storey height: 3.0m
Safe bearing capacity:185KN/m2
SCHEDULE OF OPENINGS
Main door(MD) : 1.20X2.10
Door (D) : 1.00X2.10
Door (D1): 0.75X2.10
Window (W) : 1.50X1.50
Window (W1) : 0.90X1.20
Window (W2) : 0.90X0.90
Ventilator (V) : 0.60X0.45
COLUMN C1
main wall 3.375 m
cross wall 1.845 m
G+2 Building,
Total = 3*226.38 679.14 KN
800.00 KN
3.1.3Design of column(C1):
Load on column P 800 KN
Moment on the column M 50 kNm
Pu =1.5×800 1200 KN
Mu =1.5×50 75 kNm
Pu = 1200×103 = 0.58 0.58
fck×b×D 20×230×450
Mu = 75×106 0.08
2 2
fck×b×D 20×230×450
{from chart-32 SP-16}
P = 0.08
fck
P=0.08×20=1.6%
Ast= 1.6×230×450 1656 mm2
100
3.1.4Design of footing
(F1)
Load on the column 680 kN
Load on the footing
=(1.1×680) 750 kN
2
SBC of soil (As per test report185KN/m ) 185 KN/m2
Area of footing (Af ) = load on footing = 750 4.05 m2
SBC of soil 185
Provide footing area (2.4×1.7) 4.08 m2
(qnet)Net pressure @ base = 680/4.08 166.66667 kN/m2
(2.0-0.45)
Projection beyond face of column x= 2 =0.78
Steel calculation
X1=X-d=0.78-0.55=0.23
0.55=0.23
Vu = 97.74*103 =ح0.075
bd 2400*550
From SP 16, Table 61, page 178 for Pt = 0.085%, حc= 0.33 N/mm2
Since حv < حc hence safe in one way shear
Check for two way shear: The critical section is @ a distance d/2 from face .
of the column all around
AB=450+550+550 =1000mm
2 2 M
BC=230+550+550 = 780mm M
2 2
perimeter=2(AB+BC)
=2(1000+780)
=3560mm
2.Laod calculation:
Effectivespan 6.75 m
W 26.28 KN
Say Wu 30 KN
16
bf=[(Lo/6+bw+6Df]
= [0.7*6.75/6+0.23+(6*0.150)]= 1.91 m
say 1.90 m
Tension reinforcement
Mu = 18.975×106 = 0.03
2
bd2 1900 × (550)
{from T-2 SP-16} pt=0.566% 0.085%
Shear reinforcements
Vu = 151.88x 103 1.2
bwd 230 x 550
lx=3.52m
ly=6.75m
(ly/lx)=(6.75/3.52)=1.91<2 {Hence design as two way slab}
2.Tension reinforcement :
Mu = 11.62×106 = 0.8
2 2
bd 1000 ×120
{from T-2 SP-16} pt=0.233%>0.12% minimum steel
Ast = 0.233×120×1000
100 =276 mm2
3
3.52 X10 =29.33
29.33
120
29.33<36.608 Hence ok
Fig 3.2.1
Fig 3.2.2
.2.2 EXCAVATION DETAILS
Similarly estimation work for first floor is done and the total amount is
Rs10,28,298.57.
3.3.1 ABSTRACT
3 TOTAL 2,590,419.27
4 STAIRCASE 75,000.00
4 Assigning of Loads
6 Output results
Problem Proposed:
It is commercial building which has to be construct at Ballari. It is designed for
SBC of 190KN/m2.
A three storey concrete building is taken into consideration for the purpose of
validation as shown in fig. The building is located in seismic zone II. The soil
conditions are medium stiff and the entire building is located on a raft foundation .The
R.C. frames are with infilled. The lumped weight due to dead loads is 4.75 kN/m2 on
floors and roof. The floors and roof are to cater for a live load of 4 kN/m2. The
parapet wall load on roof is 4 KN/m and wall load on floors is 14 kN/m. Material used
M20 concrete and Fe-415 steel.
Load combination
3D Model of the project- Extrude view shows the Beams, Columns and Slab
assigned to grid.
3.5 LOADING
The structure is designed to resist the gravitational force, lateral force, Dead
load, live load, Earth quake load and other load coming on the structure throughout
entire life span. This mainly depends on size and shape of building. These loads are
calculated based on the provision of IS 875 (Part 1)
Dead load
Taking thickness of wall as 230 mm thick and parapet wall as 200 mm thick.
Story height is 3.2m (commercial building). In ETAB we should not assign
dead load, it takes default value based on thickness of slab.
ITEMS INTENSITY
wall load 0.23 * 3.2 * 19 = 13.98 KN/m
Parapet wall load 0.2 * 0.9 * 19 = 3.5 KN/m
weight of slab 0.15 * 25 = 3.7 KN/m
Floor Finish 1 KN/m
LIVE LOAD
The live load will come from non structural elements or moving load. Live
load is a varying load. It always varies throughout life span of the building.We
take live load of 4 KN/m2 on floor slab and 2 KN/m2 on roof slab respectively.
EARTH QUAKE LOAD
The method used for seismic analysis is equivalent static analysis. The loads
are applied at respective node. Earthquake loads mainly depends on
1. Earthquake zone factore
2. Type of soil
3. Height of the building
WIND LOAD
Wind load is consider for tall building like sky scrapers. Wind load is not consider in
this project.
3.6 DESIGN
Column (C1)
Node 13 Max Reaction = 1593.53 KN
Design of column(C1):
Factored Load on column, Pu 1593.53 kN
Factored Moment on the column, Mu 57.58 kNm
Pu = 1593.53×103 = 0.77
fck×b×D 20×230×450
Mu = 57.58×106 0.06
2 2
fck×b×D 20×230×450
P = 0.14
fck
P=0.14 ×20=2.8%
Ast=2.8×230×450 2898 mm2
100
Provide Reinforcement = 8 # 20mm + 2 # 16mm
2.2
2.9
say = 1.225
Steel calculation
Mu = 393×106
bd2 2200×5502 = 0.59
X1 = x – d
= 1.225 – 0.55
= 0.675
=183.16×(2.2×0.55)
221.62 KN
Vu =1.5×221.62 332.40 kN
Vu = 332.4*103 = 0.275 N/mm2
bd 2200*550
From SP 16, Table 61, page 178 for Pt = 0.169%, حc= 0.33 N/mm2
Since حv < حc hence safe in one way shear
Check for two way shear: The critical section is @ a distance d/2 from face .
of the column all around
AB=450+550+550 = 1000 MM
2 2
BC=230+550+550 = 780 MM
2 2
perimeter=2(AB+BC)
=2(1000+780)
= 3560 mm
Vu =1.5×1025.72 = 1538.57 kN
2.Load calculation:
Eff span 6.54 m
From ETAB Analysis M u= 179.74 kNm
Vu= 281.09 kN
bf = [(Lo/6+bw+6Df]
= [0.7*6.54/6+0.23+(6*0.150)]= 1.89 m
say 1.90 m
Tension reinforcement
Mu = 179.74×106 = 0.60
bd2 1900 × (400)2
Shear reinforcements
Vu = 281.09 x 103 3.05
bwd 230 x 400
(L/d)max =(L/d)basic×k1×k2×k3
(L/d)max =26×1×1.7×1
(L/d)max = 44.2
6.54×103 = 16.35
400
lx=2.23m
ly=6.33m
(ly/lx)=(6.33/2.23)=2.7>2 {Hence design as one way continues slab}
Mu = Wd*L2 + WL*L2
10 9
Mu = 7.125*4.082 + 6*4.082
22.95 KN-m
10 9
2.Tension reinforcement :
Mu = 22.95×106 = 1.35
2 2
bd 1000 ×130
(L/d)max =(L/d)basic×k1×k2×k3
(L/d)max =(L/d)basic×k1×k2×k3
(L/d)max =26×1×1.4×1
(L/d)max = 36.4
2.23×103 = 17.2
130
Fig 3.8.1
Fig 3.8.2
Fig 3.8.3
Fig 3.8.4
CHAPTER 4
REFLECTION NOTES
4.1 INTERNSHIP OBJECTIVES:
The theoretical knowledge of organization is important in understanding the
fundamental concepts and ideas surrounding the creation and sustainability of many
organizations that exist within our societies. Through theory we can able identify the
models of why organizations were created, and how they continue to adapt and reform
over time. Yet, even as theory is extremely insightful, it only helps to provide us with
the starting point, and it is important to remember that at some point there must be a
practical application of these ideas and concepts. For university students, one way to
apply the theories and concepts learned is by participating in internship programme.
Since there is no substitution for practical work experience, internships are an
excellent ways to for students to apply what they are learning in real life experiences,
in hopes that they will have a greater understanding of their specific field of study.
This was a great opportunity for me to learn because I had little knowledge of these
communication tools.
4.2 DUTIES OF AN INTERN
4.3.1 DESIGN.
1) After the analysis we did for concrete frame design and we checked for design.
2) After design check, we can see that whether columns and beams pass or fail.
3) By knowing the column and beams are passed, we can see area of the steel of
columns and beams; we can also get the value of Rebar percentage.
4) We can get values for the shear force, axial force and bending moments on the
report and also get the flexural details.
4.3.2 SOFTWARES
E-TABS software is used to analyze and design the multistoried buildings ,
residential building, commercial building.
1) It knows how to model the concrete frame design, steel frame design, composite
frame design, shear wall design and spectrum analysis, time history analysis.
2) It knows the time saving, easiest method analysis and design.
3) It knows the checking the member is pass or fail.
4) It knows output and display option.
5) It knows the detailing of building.
4.3.4 ANALYSIS.
1) I got good idea about the analysis by viewing the plan, then we decided the depth
and width of the beams and columns.
2) By E tabs software we assign section properties of beams, column and slabs.
3) We are applied the loads as per Indian codes (IS-875 part -1-2-3-4-5) then check
for the model.
4) By knowledge above points analysis is carried out.
5) After the analysis the axial force, shear forces, bending moments and torsional
moments will be obtained.
6) Analysis done for residential buildings.
The basic needs required for the structural part like column orientation based on
1) Major axis principles and minor axis principles.
This based only on moment of inertia about the x- axis and y-axis.
2) Based on load distribution.
Load distribution towards the beams to column whichever is maximum we will orient
the column on that face like major axis.
I got basic concepts of beam orientation and finding depth and width of the
column as based on wall thickness if only on residential building for only for width
.like other building it may varies width.
I learned manual design of beams, column , slabs and footing by assigning the
work as per codal based design .
I got preparation of excel sheets based manually design like beams like singly
reinforced beam, doubly reinforced beam and deep beam. In columns like uniaxial
moment , biaxial moment and long column an footing like isolated footing , combine
footing ,eccentric footing. In slabs one way slabs and two way slabs.
Different personalities:
Living with the community.
Showing the existence.
CONCLUSION
Internship gave us a chance to work with the employers who are very helpful
and supportive.
Few fresh graduates can choose their employers and the city of residency.
We met powerful and influential leaders in our company, who can later guide
us and help.
REFRENCES